Proj 592 - CP3
PERFORMANCE ANALYSIS
After setting the entire project to 40% complete on Oct 1, 2008 we can see that the project is behind schedule. The schedule variance of the entire project is $ (736,599) and Schedule performance index is at 0.68, which indicates that for every $1.00 spent in the project we are only getting $0.68 worth of work done. Since we do not have actual cost data, the MS Project calculates the budget is under budget by a negligible $80.
Performance Analysis (Cost)
Table 1
Task Name
Cost Variance
CPI
Estimate at Completion
Baseline Cost
Theme Park Project
80
1.00
4,449,920
4,449,920
Site Layout & Side Grading
-
1.00
10,000
10,000
Footings & Foundations
-
1.00
103,600
103,600
Masonry
-
1.00
281,200
281,200
Frames, Columns & Beams
-
1.00
370,800
370,800
Joists & Roof Deck
32
1.00
515,520
515,600
Slab on Grade
-
1.00
218,200
218,200
Rough Carpentry
6
1.00
103,184
103,200
Interior Studs
-
1.00
10,400
10,400
Interior Drywall
-
-
65,600
65,600
Painting
-
-
66,000
66,000
Elevator
8
1.00
135,579
135,600
Doors
-
-
47,600
47,600
Custom Theme Painting
-
-
24,000
24,000
Flooring
-
-
85,200
85,200
Finish Carpentry
-
-
10,200
10,200
Bathroom Compartments/Acc
-
-
1,560
1,560
Plumbing
3
1.00
186,991
187,000
HVAC
3
1.00
264,993
265,000
Electrical
5
1.00
195,782
195,800
Mechanicals Complete
-
-
-
-
Attraction Install & Training
23
1.00
1,943,795
1,944,400
Furniture Installation
-
-
153,400
153,400
System & Security Training
-
-
2,040
2,040
Final Walkthrough
-
-
520
520
Grand Opening
-
-
30,000
30,000

Looking at the table above, we can conclude that the project is on budget and may not need much corrective actions. The MS Project predicts that the Budget at completion at $4,453,480, which is a little more than the planned $4,449,920. There might be some cost overruns in the future due to the schedule delay. This could affect the project’s Budget at completion. The current calculation of under budget is misleading the next table (Schedule Performance) shows the project

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Nt1330 Unit 4

    • 4542 Words
    • 19 Pages

    The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.…

    • 4542 Words
    • 19 Pages
    Good Essays
  • Powerful Essays

    Proj 598 Pp1

    • 3918 Words
    • 16 Pages

    Note: Click somewhere within your table of contents, press F9, select the “update entire table” radio button, and click “OK” to refresh it automatically.…

    • 3918 Words
    • 16 Pages
    Powerful Essays
  • Satisfactory Essays

    Ilab Week7

    • 297 Words
    • 2 Pages

    According to the Project summary, this project is currently on schedule. The project summary is currently indicating that the project is coming in under budget by $1,720.00.…

    • 297 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Proj 592 Cp1

    • 1371 Words
    • 6 Pages

    Our intention is to open an all-inclusive beauty salon in Athens, OH. Athens, OH is located 1 hour away from Columbus, OH. Its largest employer is Ohio University although it is home to Wal-Mart, Lowes, and many other smaller businesses. Currently there is a lack of professional services related to beauty. For the most part if these services are needed, clients are forced to drive 1 hour to take advantage of them.…

    • 1371 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    JDT@ task 1A

    • 625 Words
    • 2 Pages

    Gannt Chart and/orWBS Create a gannt chart and list all the projects, the estimated time to completion as well as estimated cost. List each part of the project and give it a time line on the chart. Using this you can track it daily, weekly, monthly, or whenever you wish. Could also use a WBS to breakdown the projects and put a time line on each part of the project to show how each team member worked on it. Using this will show you how close you can get to being finished by year end as the case study states it was finished 6 months early.…

    • 625 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Proj 587

    • 5689 Words
    • 6 Pages

    Course Project Draft Comcast Portfolio Management Plan Project Comcast is one of the United States leading telecommunications companies operating today. Currently, Comcast serves 22.9 million cable customers, 16.7 million high-speed Internet customers, and 8.4 million telephone services customers. In 1963, Ralph J. Roberts founded the company originally branded as American Cable Systems in Tupelo, MS. In 1969 the company was renamed Comcast Corporation. The name blends the words communications and broadcast. From the late 1960s and into the late 1990s, Comcast Corporation had acquired, developed or invested in multiple companies that include QVC, Storer Communications, American Cellular Network Corporation, Metrophone, US Cable Operations, The Golf Channel, and the E.W. Scripps Cable Systems. In 1996 Comcast launched its first high speed Internet option. In 2000 Comcast acquired new customers in multiple states from Adelphia Cable Systems and ATT Broadband. Later in 2002 Comcast and ATT Broadband completed a merger. Comcast was one of the first cable companies to offer high definition and video on demand television services, also in 2002. In 2005 Comcast started to offer digital voice telephone services. Since the initial telephone service was offered, Comcast has grown into the third largest provider of home telephone service. Comcast and GE brokered an agreement that would give a controlling share and management duties of NBC Universal in 2009. NBC Universal is a worldwide entertainment company and has a diverse portfolio that includes multiple television networks, motion picture companies and amusement parks. Comcast Corporation owns the NHL team Philadelphia Flyers and the NBA team Philadelphia 76ers as well as the arena where both play, Wells Fargo Center. Comcast also owns Fandango, a movie information company. Comcast Corporation is the main tenant of the Comcast Center. Comcast is currently in the process of merging with Time Warner Cable in which,…

    • 5689 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    The Gantt chat in the Microsoft project shows each activity and estimated duration as when it will be completed. The Gantt chat also reveals that the estimated completion time for the entire project will be July 6, 2012 which is one week after the projected date set by the board of directors which is June 30, 2012. This is clearly indicates that the project would not be completed on time as it was projected. In my opinion I think July 6, 2012 is not too far from the expected project completion date, therefore I would suggest the project manager to revise the schedule and reschedule.…

    • 611 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    There was significant misunderstanding of the complexity of this project. Not having a sufficient timeline and accurate planning of all tasks allowed room for the project to go over the timeline because there was no planning for testing and failures. In addition, staff working more than one project at a time and not being solely dedicated showed initiative…

    • 476 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Zuma Project

    • 1253 Words
    • 6 Pages

    If the project is not resource constrained, then the finish date of the project will be 12/22/2008,…

    • 1253 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Costs and Earned Value

    • 557 Words
    • 3 Pages

    How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?…

    • 557 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    The estimated project completion date is TUE 11/13/13 with duration of 127 days. After leveling and re-allocating work along the project line, the project got delayed for 3 days so that the completion day moved up to FRI 11/21/13 (total duration of 130 days). (MS Project 2007)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    My simulation scores show the area of most need for improvement in the areas of cost projecting and financial decision making. While working on the project in the beginning. I do not believe that I spent enough time with the work breakdown schedule and the project charter, as the project was behind schedule for the full duration of the project life cycle requiring multiple revisits to request further funds to cover project costs. It will be in my best interest in future projects to familiarize myself fully before determining financial…

    • 1509 Words
    • 7 Pages
    Good Essays
  • Good Essays

    the trophy project

    • 770 Words
    • 4 Pages

    Trying to address the problem Reichart was told not to meddle in the functional manager’s allocation of resources and budget expenditures. After Six month into the project, a requested progress report to higher level management revealed that the project was in big trouble. In the report it could be deduced that the project was one year behind schedule and a whole 20% over budget. Moreover; the number of workers supplied to the project was not enough to get the project back on schedule.…

    • 770 Words
    • 4 Pages
    Good Essays