Case Responses
Problem 1 Answers:

a) Draw a network diagram for the project. See diagram on second page (go to view network diagram)

b) Mark the critical path and state its length. The critical path is in red color (go to view tracking Gantt). The length of the critical path is 18 days of duration.

c) If the Maser has to be completed 2 days earlier, would it help to: i. Buy preassembled transmissions and drive trains? Yes, however is dependent of supplier inventory

ii. Install robots to halve engine-building time? Yes, however it is dependant of the existing technology from the manufacturer, a cpst analysis would be necessary to take the decision.

iii. Speed delivery of special accessories by 3 days? Yes, if the company is willing to pay the expedite charges; the lead time could be reduce considerably.

d) How might resources be borrowed from activities on the non-critical path to speed activities on the critical path? With the proper resource leveling additional team members could be allocated to help on the critical path. The intent is not to over allocate resources.

Problem 2 Answers:

1. Identify the critical path and its activities for Rockfest. How long does the project take? With the information provided, the project will take 34 weeks to complete. The critical path is in red color.

2. Which activities have a slack time of 8 weeks or more?
With the information provided and the dependencies that I created based on my assumptions, these are the tasks that have more than 8wk slack time:
Task P (finalize sponsors).
Since there are a lot of activities that are not linked (successors), it is somewhat difficult to predict additional activities with > 8wk slack time.

3. Identify five major challenges a project manager faces in events such as this one. i. Rain delays in the construction. ii. Government agency permits for construction delays. iii. Telecommuting with

You May Also Find These Documents Helpful

  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    Pm592 Week 5 Assignment

    • 589 Words
    • 3 Pages

    3. Assess the project performance to date? Do you get to have the celebration? NO, at the end of month 4, over budget and behind schedule.…

    • 589 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    If the project is shorted to 38 weeks, R.C. Coleman will be able to achieve the goal of 80% completion at 40 weeks. R.C Coleman should crash activities to reduce the expected project completion time to 38 weeks.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    1. The project is estimated to be completed in 260 working days. The project starts on January 2nd, 2015 and ends on January 8th, 2016.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    This project will take a week. Your rough draft is due Tuesday of this week, and your final copy is due on Friday of this week. You MUST turn in your rough draft in order to receive credit for this project. It is completed in phases, and the schedule is imperative. 100 points…

    • 349 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Management

    • 252 Words
    • 2 Pages

    2. Assume that the project is time constrained and try to resolve any over allocation problems by leveling within slack. What happens?…

    • 252 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Grt Task 1

    • 19334 Words
    • 78 Pages

    Correct Answer: D QUESTION 5 During which of the following process groups is the availability of required resources for the project determined? A. Executing…

    • 19334 Words
    • 78 Pages
    Powerful Essays
  • Good Essays

    4. Assume the project is resource constrained and resolve any over allocation problems by leveling outside of slack. What happens? What are the managerial implications?…

    • 810 Words
    • 4 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    (B.) What is the slack time (float) for activities A, D, E, and G? [8 points] (Points: 15)…

    • 692 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    As of the 26th of August, what is the project schedule and cost? What are the trends? What is the critical path?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Hand-in Assignment

    • 258 Words
    • 2 Pages

    4. What are the slack values for activities C and F? Interpret the meaning of their slack values?…

    • 258 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    marketing

    • 856 Words
    • 4 Pages

    According to Gray & Larson (2006), they think that the earliest finish time of the final activity of project in the forward pass is identified as the project duration through beginning at the first activity and then adding the activity duration. In the network diagram drawn, the project duration is 88 days.…

    • 856 Words
    • 4 Pages
    Better Essays