Preview

Project Management

Satisfactory Essays
Open Document
Open Document
252 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management
Pinteroffice memorandum to: | tANIA pARKER | from: | MOHAMMED ZOAHEB | subject: | ms project part 2 | date: | June 14, 2013 | cc: | [Name] | | | 1. Which if any of the resources are over allocated? * Marketing staff * R&D * Legal staff 2. Assume that the project is time constrained and try to resolve any over allocation problems by leveling within slack. What happens?
The Marketing staff and legal staff over allocated problem is solved, however R&D cannot resolve over allocation issues, R&D is still over allocated. There were not enough resources for non-critical activities to absorb the demand for the resource. 3. What is the impact of leveling within slack on the sensitivity of the network?
The sensitivity of the network is increased. The slacks are reduced which lead to a loss of flexibility. The probability of activities delaying the project is increased because the reduction of slack creates more critical activities and critical paths.

4. Include a Gantt chart with the schedule table after leveling within slack.
As in the Gantt chart, there are more critical activities (marked on red).

5. Assume the project is resource constrained and resolve any over allocation problems by leveling outside of slack. What happens?
Using leveling outside of slack, the over allocation problems are resolved. However, the length of the project has increased and the new end date is now 19/7/2012. 6. Include a Gantt chart with the schedule table after leveling outside of slack.
This is included with the other

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Unit 421 Unit 7

    • 686 Words
    • 3 Pages

    of such resource loading and develop a more leveled schedule. This forms your Exercise 2 for this week.…

    • 686 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    MGT2 Task3

    • 5037 Words
    • 21 Pages

    Increase the project team size to catch up and speed up progress reducing potential for any further schedule…

    • 5037 Words
    • 21 Pages
    Powerful Essays
  • Better Essays

    Each team member needs to bring a suggestion for a solution as well as verification that tasks that you are responsible for at this point have been completed. As a team we must provide honest and open estimates about what we are doing to complete this project. We may have to do some partial overlapping in the next few weeks, but we will get this project completed successfully and on time. Some partial overlapping should get the project back on track and help with the budget…

    • 914 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    4) What would be the caution of adding more resources to a task to resolve resource conflicts? As you assign resources to tasks, Project checks the resource’s calendar to make…

    • 511 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    2. Once the resource leveling is completed, the over allocated resources decrease from 4 to 2. The over allocated problems are design engineer and industrial engineer, with the greatest total slack for detailed marketing plan decreasing. In the end the project task changes in the duration period after resources leveling.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    a. How many EMPLOYEES can work on a project? There is no set limit of employees to work on one given project.…

    • 334 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Kevin Erle Case Summary

    • 454 Words
    • 2 Pages

    I purposely did not mention the feasibility of hiring additional, temporary staff {although this might be a possibility given sufficient funding}, because the added costs of hiring and laying off people can be excessive. By leveling existing resources, these added cost can be…

    • 454 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Problem-Based Learning Case Study 1. Define a project. How does the Alton Bridge meet the five characteristics of a project? Projects are a set of related tasks to be executed over a fixed period and within certain cost. The Alton bridge accomplish with a shared resource, the task is interrelated and cross functional team work and it involved uncertainty.…

    • 603 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    If for some reason you cannot meet the requirements set by the members of the team, you need to notify everyone ASAP so we can help cover the slack, COMMUNICATION is the key to our group's success!…

    • 312 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    MGT203 CH4

    • 723 Words
    • 7 Pages

    B is not on a critical path and has slack of 4; therefore, do not shorten as it will not change the project completion time. Shorten C, D, and G one week each. C and D are on parallel critical paths, reducing them both will only reduce project completion time by 1 week.…

    • 723 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    Grt Task 1

    • 19334 Words
    • 78 Pages

    Correct Answer: D QUESTION 5 During which of the following process groups is the availability of required resources for the project determined? A. Executing…

    • 19334 Words
    • 78 Pages
    Powerful Essays
  • Good Essays

    Gantt Chart

    • 406 Words
    • 2 Pages

    A common error made by those who equate Gantt chart design with project design is that they attempt to define the project work breakdown structure at the same time that they define scheduled activities. This practice makes it very difficult to follow the 100% Rule. Instead the WBS should be fully defined to follow the 100% Rule,[6] then the project schedule can be designed.[7]…

    • 406 Words
    • 2 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    The estimated project completion date is TUE 11/13/13 with duration of 127 days. After leveling and re-allocating work along the project line, the project got delayed for 3 days so that the completion day moved up to FRI 11/21/13 (total duration of 130 days). (MS Project 2007)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Gantt Chart

    • 284 Words
    • 2 Pages

    A Gantt chart is a type of bar chart, developed by Henry Gantt in the 1910s, that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. Some Gantt charts also show the dependency (i.e. precedence network) relationships between activities. Gantt charts can be used to show current schedule status using percent-complete shadings and a vertical "TODAY" line as shown here.…

    • 284 Words
    • 2 Pages
    Good Essays
  • Good Essays

    The Morrison Company

    • 1011 Words
    • 5 Pages

    o Significant increases in sales and shortage of available raw material cause problems in the production process…

    • 1011 Words
    • 5 Pages
    Good Essays