Preview

A&D High Tech (A)

Good Essays
Open Document
Open Document
613 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
A&D High Tech (A)
Case #3
A&D High Tech (A): Managing Projects for Success:
A Negative View
1. What is the estimated project completion date? (Assume there are no holidays and ignore the sunk cost of the planning team’s effort)
The estimated project completion date is TUE 11/13/13 with duration of 127 days. After leveling and re-allocating work along the project line, the project got delayed for 3 days so that the completion day moved up to FRI 11/21/13 (total duration of 130 days). (MS Project 2007)
2. What is the total cost? How much of the total cost are labor costs? Capital costs?
Total Cost: $98,500 + $844,980 = $943,480
Labor Cost: $ 844,980 (given result of project)
Capital Cost:
(12 Windows 2000 workstations*$3,000) + (5 Window 2000 servers*$12,500) = $98,500
3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.
The critical path is added to the appendix of this case report. As shown in Figure 1 and 2, many tasks are correlated so that one critical phase can affect the other. Here, we divided the entire process into three parts: namely by “Detailed Design” part (on the left hand of the network diagram), “Create Functional Requirements (upper side),” and “Development & Unit Test (bottom left side).” Even though, we leveled the resource referring on automated re-allocation methods, except for 7 phases in this project, most of the critical stages remained still critical. These seven stages are “Create data requirements,” “Gather testing requirements,” “Create System Test Plan & Test Cases,”“Write system test scripts,” and on the other part of the network diagram, “Updating and Calculating Shopping Cart,” Submit Order,” “Check Order History & Order Status,” and “Create ERP Interface Requirements.” Considering that most of the leveled tasks are components of “Detailed Design” and “Development & Unit Test,” (tasked that still remained critical, even...
1.What is the projected

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    The Gantt chat in the Microsoft project shows each activity and estimated duration as when it will be completed. The Gantt chat also reveals that the estimated completion time for the entire project will be July 6, 2012 which is one week after the projected date set by the board of directors which is June 30, 2012. This is clearly indicates that the project would not be completed on time as it was projected. In my opinion I think July 6, 2012 is not too far from the expected project completion date, therefore I would suggest the project manager to revise the schedule and reschedule.…

    • 611 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Chapter 11-33 Week 3

    • 963 Words
    • 4 Pages

    The difference in favor of continuing with current production and turning down the special order is $30,000 ($80,000 - $50,000).…

    • 963 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    BSBMGT402A ASSESSMENT 1

    • 2713 Words
    • 14 Pages

    In a previous task, you developed a project flow chart and identified a critical pathway for…

    • 2713 Words
    • 14 Pages
    Satisfactory Essays
  • Better Essays

    Collaborative

    • 736 Words
    • 3 Pages

    7a: The project is estimated to be completed on July 12, 2012. The project will take 135 working days.…

    • 736 Words
    • 3 Pages
    Better Essays
  • Good Essays

    Pert Mustang

    • 1016 Words
    • 5 Pages

    A table containing the project activities, the time estimates and the precedence relationship will be prepared and a network diagram will be drawn to structure the immediate predecessor activities. The critical activities will be identified to indicate that the project can be completed within 45 working days.…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    1. The project is estimated to be completed in 260 working days. The project starts on January 2nd, 2015 and ends on January 8th, 2016.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    and sells 80,000 Zets each year at a selling price of $40 per unit. The company’s unit…

    • 562 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    INF 410 Project Management

    • 1187 Words
    • 4 Pages

    Risk Identification. State the importance of identifying risks and categorizing them as high, medium or low probability. Explain why risks associated with the critical path of the project need special attention. Respond to at least two of your classmates’ postings.…

    • 1187 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    1. When is the project estimated to be completed? How long will the project take?…

    • 280 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    It Project Management

    • 7394 Words
    • 30 Pages

    Begin organizing your project files by making decisions on the relevance of materials and make some estimates for tracking your project. Refine your project plan.…

    • 7394 Words
    • 30 Pages
    Good Essays
  • Good Essays

    1. When is the project estimated to be completed? How long will the project take?…

    • 576 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Yes, critical path activities should managed differently as they are directly effects project schedule and its success. The Critical Path requires specific…

    • 2429 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    A&D High Tech

    • 4238 Words
    • 17 Pages

    A&D High Tech is a US medium size company that started to operate in the business of computer systems products and services in 1988. Due to fierce competition and decreasing profit margins, the company founder and CEO was seeking other growth opportunities by adopting two new strategies, namely:…

    • 4238 Words
    • 17 Pages
    Powerful Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is your opinion on the potential for the project to be completed on time?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays