Preview

Three Point Technique to Estimate Task Duration, Es-Ef, Ls-Lf Procedure to Indentify Critical Path.

Good Essays
Open Document
Open Document
1246 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Three Point Technique to Estimate Task Duration, Es-Ef, Ls-Lf Procedure to Indentify Critical Path.
The total duration of the construction project by adding the estimated task duration serially would give us 70 weeks. But some tasks within some activities can be done in parallel sequence or simultaneously, which would significantly reduce the construction project completion time using the critical path method (CPM). In this method the longest path is the critical path which runs through one of the route in the project network diagram from start to finish. This project network diagram is illustrated on the printed assignment page, we have 10 tasks listed from A to J. Below is an activity list of the tasks; ACTIVITY | ACTIVITY DESCRIPTION | IMMEDIATE PREDECESSORS | ESTIMATED DURATION (WEEKS) | A | Clearing the vacant lot | none | 7 | B | Securing permits | A | 11 | C | Digging a foundation | A | 12 | D | Putting in forms for the concrete | A | 9 | E | Pouring the concrete foundation | B | 2 | F | Putting up structural framing | B, C | 10 | G | Running electrical/water/sewage | C | 3 | H | Finishing the interior | D,E,F, G | 2 | I | Finishing the exterior | D | 6 | J | Landscaping the property | H, I | 8 | | Total estimated task duration | | 70 WEEKS |
Figure 1.1
The variables provided for the optimistic, most likely and pessimistic task time estimates in the printed assignment table were used to calculate the estimated duration in Figure 1.1 above. The formula below used to derive at the estimated task duration in Figure 1.1 above was the three-point technique;
E= (O +4(M) + P) 6 The critical paths for this construction project and the path lengths are highlighted below; we would use this to calculate the earliest finish time for the project. CRITICAL PATH TASKS | PATH LENTHS IN WEEKS | 1. start: A-B-E-H-J- finish | 7 + 11+ 2+ 2+ 8 = 30 | 2. start: A-B-F-H-J- finish | 7 + 11+ 10+2+8 = 38 | 3. start: A-C-G-H-J- finish | 7 + 12+ 3+ 2+ 8 = 32 | 4:start: A-C-F-H-J- finish | 7+

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    The project is pouring a concrete patio in my backyard. The results will be a new patio to entertain guests. I am allowing two additional weeks in case there is inadequate funding or scheduling conflicts for the project ending in May of 2008. The two extra weeks are there in case there is an unexpected expense elsewhere, or I can’t get my brother to my house to help out because of scheduling conflicts. Each activity is defined within a week’s time.…

    • 784 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    In the book of John, the author said, “We must work the works of him who sent me while it is day; night is coming, when no one can work” (John 9:4, ESV). In biblical worldview, many scriptures identify time and work related approaches. Project duration is an important aspect of the project. Klansek, U., & Psunder, M. (2008) stated, “Each activity within project network is characterized by its precedence relations, duration, and resource requirements”. After doing Part 1 of the Red Zuma project, I realized that many factors can affect the project duration. For example, if the resources are overallocated they can get leveled. When resources get leveled within the slack it can cause changes in areas such as the critical path and duration. It is…

    • 317 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    1. The activities involved for the project schedule can be represented using Central Path Method (shown below) showing various interdependence and parallelism among activities.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Most likely time estimate is an estimate of the maximum time an activity will require.…

    • 6920 Words
    • 28 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    A group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times in weeks. Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.…

    • 590 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    The Campus Wedding

    • 1429 Words
    • 6 Pages

    There are four main steps to the Critical Path Method. The first step is to identify each activity to be done in the project and estimate how long it will take to complete each activity. The activities are usually labeled A, B, C, D, etc. each letter will have a number next to it representing the amount of time the activity will take, usually labeled in days or weeks. The second step is to determine the required sequence of activities and construct a network reflecting the precedence relationships. To do this, it is best to first find the immediate predecessors, which are the activities that need to be completed immediately before the next activity. The predecessors are used to draw the network diagram. Once the diagram is drawn, the next step is to determine the critical path, which is the path where the sum of the activity times is the longest. The final step is to determine the early start/finish and late start/finish schedule for each activity. Slack time may occur when there is some leeway in the start and finish time. The early start and early finish times are written on the upper left and upper right corners respectively of the activity nodes in the diagram. These are the earliest possible times that the activity can start and finish. The late start and late finish times are written on the lower left and upper right corners respectively of the nodes. To calculate the early times, start with the first…

    • 1429 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Okay

    • 991 Words
    • 4 Pages

    Research is a sequential method of enquiry, directed towards a clear implicit or explicit objective. Describe in detail the steps to be carried out in a typical research study.…

    • 991 Words
    • 4 Pages
    Good Essays