Preview

Project Management

Good Essays
Open Document
Open Document
4378 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management
Chapter 13

Project Management

© 2008 Prentice-Hall, Inc.

Introduction
 Most realistic projects are large and complex  Tens of thousands of steps and millions of dollars 

  

may be involved Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high The first step in planning and scheduling a project is to develop the work breakdown structure Time, cost, resource requirements, predecessors, and people required are identified for each activity Then a schedule for the project can be developed

Introduction
 The program evaluation and review technique

   

(PERT and the critical path method (CPM are two PERT) CPM) popular quantitative analysis techniques to help plan, schedule, monitor, and control projects Originally the approaches differed in how they estimated activity times PERT used three time estimates to develop a probabilistic estimate of completion time CPM was a more deterministic technique They have become so similar they are commonly considered one technique, PERT/CPM

Six Steps of PERT/CPM
1. Define the project and all of its significant activities or tasks 2. Develop the relationships among the activities and decide which activities must precede others 3. Draw the network connecting all of the activities 4. Assign time and/or cost estimates to each activity 5. Compute the longest time path through the network; this is called the critical path 6. Use the network to help plan, schedule, monitor, and control the project
 The critical path is important since any delay in

these activities can delay the completion of the project

PERT/CPM
 Given the large number of tasks in a project, it is

1. 2.

3.

4.

easy to see why the following questions are important When will the entire project be completed? What are the critical activities or tasks in the project, that is, the ones that will delay the entire project if they are late? Which are the non-critical

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The scope of the project will need an outline so the work which needs to be performed is available. Prioritizing, budgets and timelines are in this phase as well.…

    • 447 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Chapter 7: Advanced Project Network Analysis and Scheduling (pp. 240-272, 275-277) Earned Value Project Management Chapter 7: Plan and Schedule the Project (pp. 63-74) Course Project, Part 1 (CP-1) Due Graded Discussion Topics…

    • 390 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    The Critical Path is the Shortest Time in which the Project Can Be Completed. Any delay in Critical Path activities delays the project. Critical Path Activities have no slack time Variability in Activity Times: CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a Probability Distribution for Activity Times to allow for Variability.…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Better Essays

    The Work Breakdown Structure (WBS) contains the different activities within a project. Every activity necessitates outputs from several experts following different measures and timelines. The total of these activities represent the end deliverable. In order to control the task effectively the project supervisor must track the logical order of the various parts. He must visualize the final project deliverable. Views regarding project management, benefits and restrictions, bottlenecks, changes to risk or time in a crisis, and four points touched.…

    • 1092 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    4. The critical path for the project is found by calculating slack as per CPM as shown in the table below. The activities marked in green forms the critical path, I e.,…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    business

    • 279 Words
    • 2 Pages

    Define the project – write a project narrative then develop a project plan, including the processes that would be used to manage financial, technical, human and physical resources.…

    • 279 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Project Management

    • 3681 Words
    • 15 Pages

    Project constraints delay the start of project activities. Three project constraint need to be considered in scheduling.…

    • 3681 Words
    • 15 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    What is a critical path, and why is it important to project managers? How do you…

    • 702 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Two recent graduates, Michael and Elyssa, own Cables By Us, a company that produces cable assemblies. Business has been good so Michael and Elyssa have decided to expand their product line to include a new cable product. The new product will be manufactured in the current facility in an area not now in use. Michael and Elyssa have decided to use a project management approach to bring the new product on line and have identified eleven activities and their precedence relationship as shown in Table 1. The duration for each activity has been estimated by three times estimates in weeks. They also manage to get information on the normal cost of each activity, their crash time and associated cost, shown in Table 2. You have been appointed by Michael and Elyssa to analyze the data and advise them on the project. You are expected to prepare a detail report based on your findings and present them to your client.…

    • 3058 Words
    • 13 Pages
    Powerful Essays
  • Good Essays

    Allocation of resources

    • 561 Words
    • 3 Pages

    The resource allocation and budgeting process is one of the most powerful stages of planning. Resource allocation refers to the distribution of resources, and in particular finance, from the center to peripheral (outer) levels. Budgeting implies the more detailed determination of precisely how these funds are to be used.…

    • 561 Words
    • 3 Pages
    Good Essays