Preview

Network Diagrams and Schedule Analysis

Better Essays
Open Document
Open Document
1396 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Network Diagrams and Schedule Analysis
Network Diagrams and schedule analysis

NETWORK DIAGRAMS ARE SCHEMATIC DISPLAYS OF PROJECT SCHEDULE ACTIVITIES AND THE INTERDEPENDENCIES BETWEEN THESE ACTIVITIES. WHEN DEVELOPED PROPERLY, THIS GRAPHICAL VIEW OF A PROJECT’S ACTIVITIES CONVEYS CRITICAL SCHEDULE CHARACTERISTICS REQUIRED TO EFFECTIVELY ANALYZE AND ADJUST SCHEDULES – THUS RESULTING IN ACCURATE AND FEASIBLE SCHEDULES. THIS DOCUMENT ADDRESSES WHAT SHOULD BE CONSIDERED IN THE DEVELOPMENT OF A NETWORK DIAGRAM, HOW NETWORK DIAGRAMS ARE CREATED, AND HOW THEY MAY BE ANALYZED TO IDENTIFY NECESSARY CORRECTIVE ACTIONS AND ENSURE OPTIMAL SCHEDULE DEFINITION.

Network Diagram Creation

Network diagrams can be created manually but are also available as project views in project scheduling tools such as Microsoft Project. (See Microsoft Project, View→ More Views → Network Diagram).

Inputs: • Project Scope Statement – The schedule definition required in network diagram development must be based on the approved scope documented in the Project Scope Statement. If network diagram and schedule definition does not account for all required deliverables in scope, the resulting network diagram and schedule will not accurately reflect the time necessary to complete the work. • Work Breakdown Structure (WBS) – The Project Team must include WBS project work in the network diagram to ensure comprehensive reflection of project activities. • Historical Project Information – The accuracy of network diagram/schedule estimation is strengthened by actual schedule metrics from past projects. Project teams should consider past level of effort and duration for comparable project activities. • WBS Dictionary – The WBS Dictionary defines task durations, dependencies, predecessor and successor relationships, and resources – all of which need to be defined prior to network diagram creation to ensure that the network diagram accurately reflects the schedule required to successfully complete the project. • Resource

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints?…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Good Essays

    Huntsville Plant

    • 654 Words
    • 3 Pages

    “Creating a WBS is a structured approach for organizing all the project work and deliverables into logical groupings and subdividing them into more manageable components to help ensure that all the work and deliverables to complete the project are identified and included in the baseline project plan. It is a hierarchical tree of deliverables or end items that will be accomplished or produced by the project team or contractor during the project. “…

    • 654 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Best Essays

    1. Nowadays, majority of projects, irrespectively of their scope or nature, can be outlined by various charts and diagrams. Such kind of representation of a project gives a clear picture of the project’s activities along with their start and finish dates and the sequence they are performed. This also aims to provide smooth coordination and implementation of the project, which is very crucial to the management.…

    • 3462 Words
    • 14 Pages
    Best Essays
  • Good Essays

    Pert Mustang

    • 1016 Words
    • 5 Pages

    A table containing the project activities, the time estimates and the precedence relationship will be prepared and a network diagram will be drawn to structure the immediate predecessor activities. The critical activities will be identified to indicate that the project can be completed within 45 working days.…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    One way to consider resources is to take them into account when drawing the logical relationships among activities in the network diagram. In addition to showing the technical constraints among activities, the network logic can also take into account resource constraints. The sequence of activities can be drawn to reflect the limited availability of a number of resources. If resources are to be considered in planning, it’s necessary to indicate the amounts and types of resources needed to perform each activity. For this reason, a resource profile is often developed.…

    • 2049 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Patton-Fuller Community Hospital is a nonprofit Healthcare organization in the city of Kelsey that has provided quality healthcare services to Kelsey and surrounding communities since 1975. The stakeholders are employees, patients, visitors, investors, the board of directors and the community.…

    • 1599 Words
    • 7 Pages
    Powerful Essays
  • Powerful Essays

    MGT Task1 v2

    • 1065 Words
    • 9 Pages

    Work Breakdown Structure: This section explains building out of WBS Dictionary which communicates decomposition of deliverables into task, process, and assigns a team lead responsible for each phase. This dictionary explains work item definitions, work item sequencing, labor resource assignments for each work item, work item durations and deliverables.…

    • 1065 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Poultry Industry Projects

    • 678 Words
    • 3 Pages

    One of the main tools used in these projects is the work break down structure (WBS). This tool allows the team to know what operations are going on at any given moment. A work breakdown structure is a key project deliverable that organizes the team 's work into manageable sections. The Project…

    • 678 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Case Study 1 1

    • 874 Words
    • 4 Pages

    Second, with the expected time for each task available, we plotted the network diagram for the project (as shown in the next page).…

    • 874 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Woody2000 Case Study

    • 740 Words
    • 3 Pages

    Identify and describe a set of project schedule milestones from project concept to project completion.…

    • 740 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Your company has met with University officials to develop a list of activities required to make Rock’n Bands a reality. The list on Page 2 includes twelve activities as well as their durations and immediate predecessors. The project plan is also described visually on page 2 with a network diagram. The subscripts on each activity denote the number of weeks of work that activity is expected to require. Arrows denote the order of activities. For instance, activity E cannot be started until activity A is completed, and activity H cannot be started until both C and D are complete. The start and end nodes are dummy nodes and do not need to be worked on. Note that at the beginning of the project, activities A, C and D are available to start working on, as they have no predecessor activities. Be sure to understand the diagram before reading further.…

    • 1009 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    Identify the specific activities and milestones. Determine the proper sequence of the activities. Construct a network diagram. Estimate the time required for each activity. Determine the critical path. Update the PERT chart as the project progresses.…

    • 1979 Words
    • 8 Pages
    Powerful Essays
  • Powerful Essays

    Work Breakdown Structure

    • 1880 Words
    • 8 Pages

    A WORK BREAKDOWN STRUCTURE (WBS) IS A DECOMPOSITION OF ALL THE WORK NECESSARY TO COMPLETE A PROJECT. A WBS IS ARRANGED IN A HIERARCHY AND CONSTRUCTED TO ALLOW FOR CLEAR AND LOGICAL GROUPINGS, EITHER BY ACTIVITIES OR DELIVERABLES. THE WBS SHOULD REPRESENT THE WORK IDENTIFIED IN THE APPROVED PROJECT SCOPE STATEMENT AND SERVES AS AN EARLY FOUNDATION FOR EFFECTIVE SCHEDULE DEVELOPMENT AND COST ESTIMATING. PROJECT MANAGERS TYPICALLY WILL DEVELOP A WBS AS A PRECURSOR TO A DETAILED PROJECT SCHEDULE. THE WBS SHOULD BE ACCOMPANIED BY A WBS DICTIONARY, WHICH LISTS AND DEFINES WBS ELEMENTS.…

    • 1880 Words
    • 8 Pages
    Powerful Essays