Preview

Net Present Value and Software Project Management

Satisfactory Essays
Open Document
Open Document
1655 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Net Present Value and Software Project Management
INF3708/201/3/2013

SOFTWARE PROJECT MANAGEMENT TUTORIAL LETTER 201 FOR
INF3708
SOLUTIONS

Solutions (Highlighted) - Assignment 01 – Semester 1
ASSIGNMENT 01 - COMPULSORY
Study material Total marks Hughes & Cotterell: Chapters 1 – 4 25 marks = 100%

UNIQUE NUMBER: 203647

1. A 1. 2. 3. 4. 5.

is said to be “A specific plan or design” or “A planned undertaking” System Scope Project Software Management

-2-

INF3708/201

2. Software Project Management scope normally comprises the following: a. Project Feasibility b. Project Initiation c. Project Planning d. Project Execution e. Project Control f. Project Termination Which of the above combination is correct for Project Management scope? 1. a, b, e, and f only. 2. a, c, and e only. 3. b, d, and f only. 4. a, b, c, d, e, and f. 5. a, b, c, and e only. 3. Within the Project Execution activity, project management scope certainly also encompasses the systems development life cycle as follows: i. Systems Planning ii. Systems/Requirements Analysis iii. Systems Design iv. Systems Implementation v. Systems Maintenance and Support Which of the above statement(s) is/are true? 1. i, and v only. 2. i, iii, and v only. 3. ii, and iv only. 4. iv, and v only. 5. i, ii, iii, iv, and v. 4. Similarities between General Project Management and Software Project Management in terms of the fundamental concepts include: i. Scope ii. Time and deadlines iii. Cost / budget iv. Human resources v. Quality control vi. Communication vii. Setting and meeting objectives viii. Requires a feasability study and planning Which of the above combination is true? 1. All the eight statements are true. 2. i, iii, v, and viii only. 3. ii, iv, vi, and vii only. 4. i, ii, iii, and viii only. 5. i, ii, iii, iv, vi, vii and viii only.

-3-

5. Which of the following statement(s) is/are true concerning the differences between General Project Management and Software Project Management in terms of inherent characteristics of software and the

You May Also Find These Documents Helpful

  • Good Essays

    Project Charter

    • 1699 Words
    • 7 Pages

    The Project will accomplish an immediate need to develop and implement an Enterprise Information system upgrade. The A-Team will develop a project charter, scope, and a project plan to create and implement an Enterprise Information System for the SCI Corporation and the need for upgrading their IT infrastructure. We will Plan, Procure, Install and Individualize each workstation with needed software and setup requirements, along with many other aspects of the IT infrastructure. Its ‘purpose is to Procure information technology services to support the mission for the Service Constructions Inc. IT upgrade.How does this project relate to overall goals and objectives of the company?…

    • 1699 Words
    • 7 Pages
    Good Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    7. (TCO G) Which of the following is not an advantage of using project management software?…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    Scope: Scope of the project is identified up front and once completed can meet the end deliverable for the project; however, scope can also change during the project life cycle. If the scope is not defined properly or understood up front the chances of failing the project can be high.…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Explain what project scope is and why it is important. Describe the areas of project feasibility that are examined in the analysis phase of…

    • 1348 Words
    • 5 Pages
    Powerful Essays
  • Better Essays

    The requirements are to be defined by the stakeholders and after the information has been discussed and agreed upon it can be documented to define the scope. " In the project scope definition, the elements within the scope and out of the scope are well defined in order to clearly understand what will be the area under the project control. Therefore, you should identify more elements in detailed manner and divide them among the scope and out of scope." ("Tutorialspoint", n.d.). The project scope is defined so that scope creep may be avoided and deadlines can be met. In the analysis of the scope the financial resources required to complete the work will be discussed. Then the positive and negative impacts to the company will be analyzed as the feasibility.…

    • 1174 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Resources: Ch. 11 of Essentials of Management Information Systems. See pages 386 to 394 for information on Project Management. This section covers everything you need to know in this assignment. The assignment must follow APA formatting and use proper citations and references. Include citations of the textbook within the paper in addition to providing a reference page…

    • 321 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    ITMG624

    • 4112 Words
    • 21 Pages

    This course explores successful project management for information technology projects. The System Development Life Cycle (SDLC) models are defined including the waterfall, spiral, incremental release, and prototyping models. Students will differentiate between these models and apply corresponding project management methods to identify critical checkpoints and reviews. Risk management, as applied to technology projects, is examined. Key project indicators are discussed, and students will explore defining measurement criteria for determining critical success factors on a project. The course defines the application of knowledge, skills, tools, and techniques to project activities and includes a tutorial for Microsoft Project. Emphasis is placed on the three dimensions of the information technology project constraints: scope, time, and cost. Students are recommended to have access to Microsoft Project. Course software requirements with the appropriate versions are listed under the Resources.…

    • 4112 Words
    • 21 Pages
    Powerful Essays
  • Powerful Essays

    Project Management

    • 689 Words
    • 3 Pages

    Project indirect cost represents overhead cost. Indirect cost varies directly in time. For instance, if our daily overhead cost is 250 euro, any reduction in project duration has to represent a saving of 250 euro per day. Project direct cost is clearly charged to a specific work package such as labor, materials and equipments. In order to create a cost-duration graph we have to apply three major steps:…

    • 689 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Project Management is a methodical approach to planning and piloting project processes and tools from start to finish. According to the Project Management Institute, the processes are guided through five stages: initiation, planning, executing, controlling, and closing. Project Management tools can be applied to almost any type of project and are widely used across the world. As there are no limits to its use, Project Management, and its tools can be employed to control anything from the complex processes of software development to the building of a garden shed.…

    • 597 Words
    • 3 Pages
    Good Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    7. (TCO G) Which of the following is not an advantage of using project management software?…

    • 814 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Project Management

    • 5252 Words
    • 28 Pages

    4. Matrix organizations transfer control of workers to project managers for the duration of the project.…

    • 5252 Words
    • 28 Pages
    Good Essays
  • Satisfactory Essays

    Volkswagen Mexico Case

    • 459 Words
    • 2 Pages

    All companies are faced with completing projects, whether it is to make a product, complete a service or an outcome such as a research project. Project Management helps to ensure that the projects are done effectively and efficiently. Project management is the “application of knowledge, skills, tools, and techniques to meet the project requirements.” (Project management body, 2008) There are 5 process groups associated including initiating, planning, executing, monitoring and controlling, and closing. Managing a project is complex, a Project manager needs to define and identify requirements, needs, concerns, and balance constraints such as recourses, schedules, budget and risks.…

    • 459 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Every software project must have a manager who leads the development team and is the interface with the initiators, suppliers and senior management. The objective of every project manager is to deliver the product on time, within budget and with the required quality. Although the precise responsibilities of a project manager will vary from company to company and from project to project, they should always include planning and forecasting. The major activities in software project management can be segregated under the following heads –…

    • 443 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    PMLC MODEL

    • 1177 Words
    • 5 Pages

    (Wysocki, 2012, p321) stated ‘the project management/projects landscape is based on two characteristics, goal and solution’ in complexity and uncertainly classification on the project.…

    • 1177 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Scrap

    • 2839 Words
    • 12 Pages

    PROJECT ORGANIZATION............................................................................................................................. 8 2.1 2.2 2.3 SOFTWARE PROCESS MODEL....................................................................................................................................... 8 ORGANIZATIONAL STRUCTURE.....................................................................................................................................8 PROJECT…

    • 2839 Words
    • 12 Pages
    Satisfactory Essays