Project Management
Final Exam

Ivaylo Peev
Ivailo.peev@abv.bg
PM 401 – Project management
Aris Zogopoulos
Final Exam
March 5, 2012 1. Determine bread-and-butter, pearls, oysters and white elephants projects. (15%)

Developing project portfolio matrix is the most important part of creating a project. Fours quadrants determine the matrix - Bread-and-butter, pearls, oysters and white elephants. Bread-and-butters project means evolutionary improvements to current products and service and it is low risk project with law reward. Pearls involve revolutionary commercial advances using proven technical advances. Oysters entail technological advance with high commercial payoffs. A white elephant project is that at one time showed promise but is not longer viable. 2. What do you know about the project indirect and direct costs? Prepare a cost-duration graph (15%)
Project indirect cost represents overhead cost. Indirect cost varies directly in time. For instance, if our daily overhead cost is 250 euro, any reduction in project duration has to represent a saving of 250 euro per day. Project direct cost is clearly charged to a specific work package such as labor, materials and equipments. In order to create a cost-duration graph we have to apply three major steps: 1. Find total costs for selected project duration. 2. Find indirect cost 3. Calculate direct and indirect cost for these selected durations.

3. Which are the nine traits/ skills associated with being an effective project manager? (20%)

4. Answer the following multiple choice questions (50%)

Multiple choice questions

1. Which of the following is used a Hewlett- Packard for building relationships with key players that will determine a project’s success?

A. MBWA

2. In the Research Highlight, Ancona and Caldwell identified key patterns of activity which contribute to creating a high performance team. Which of the following is not one of those?

A. Negotiator

3.

You May Also Find These Documents Helpful

  • Better Essays

    Caledonia Products recently acquired a new financial analyst assistant. Before “unleashing” the new assistant into a solo position Caledonia Products has set a huge task. The new assistant has to take under consideration a new investment, of creating and distributing a new product. The new project would last five years and cost a total of $1,000,000 over the course of the five years. The assistant will be both calculating the cash flows associated with the new investment as well as evaluate several mutually exclusive projects, (Titman, Keown, & Martin, 2011). The assistant must answer several key questions:…

    • 1189 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Chapter 9 Quiz

    • 609 Words
    • 9 Pages

    Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example of reducing project duration caused by:…

    • 609 Words
    • 9 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Comm294

    • 1634 Words
    • 7 Pages

    The costs in the table above include:  Custom fibre optic cable: Guy purchases the custom fiber optic cable from a German supplier at a rate of $17.50/m. The supplier confirmed the price of $17.50 up to and including 6600 metre spools. For spools beyond 6,600 metres, the order requires a heavier cable and the cost increases by $2.50/m for the entire spool. ( i.e. , for every metre in the spool).  Cable installers are contract labourers and are paid $1,100 per 100 metres of cable installed.  Building amortization is allocated at $2,500 per job.  The project costs include a charge of $5,000 for an engineer. Memos in the project files indicate that one engineer was just able to handle projects of this size, however, with the higher amounts of cable, there was a diminished ability of the engineer to service the project. It was recommended that in the future, any job (project) greater than 5,000 metres…

    • 1634 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    Project Management

    • 694 Words
    • 3 Pages

    References: Brown, C. (2011). Requirements risk. Business Analysts Articles: Business Analysis and Systems Analysis. Retrieved from http://www.modernanalyst.com/Resources/Articles/tabid/115/articleType/ArticleView/articleId/212/Requirements-Risk-Management.aspx.…

    • 694 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Project Management

    • 1515 Words
    • 7 Pages

    Construct a Cost-Benefit Analysis matrix for an organization that is considering replacing its internal payroll system with a payroll outsourcing service. Include direct and indirect revenue enhancements and direct and indirect cost reductions.…

    • 1515 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Project Management

    • 440 Words
    • 2 Pages

    1. Project managers frequently face competing constraints. Identify these common constraints and describe approaches that project managers can use to make the trade-offs required to succeed…

    • 440 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Management

    • 2565 Words
    • 9 Pages

    - Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion. They may also exert influence over the project's objectives and outcomes.…

    • 2565 Words
    • 9 Pages
    Powerful Essays
  • Better Essays

    Project Management

    • 844 Words
    • 4 Pages

    The projects environment as it relates to cultural /social is one of healing, health and wellbeing of the population or community. The expansion of the facility will impose little impact on the environment as we will be using an existing building and all green practices and policies will be instituted when possible.…

    • 844 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Project Management

    • 329 Words
    • 2 Pages

    3. Compose the tasks that would be needed to complete a Gantt chart (project schedule) for outsourcing the company’s payroll system. Compare the advantages and disadvantages of using a Gantt chart versus using the Performance evaluation and review technique (PERT) and critical path method (CPM) when managing projects.…

    • 329 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Analysis of Direct Costs

    • 346 Words
    • 2 Pages

    The analysis of direct material and other direct costs and what could be done about it is that when a particular organization prepares for the budget in relation to the cost of direct material or direct labor then, it has to consider the inflation rate and the standard rates in the industry. In relation to the direct labor cost, the organization has to analyze of the industrial standard of the payment made by the organizations to the labors. If the organization does not do so then, some kind of issues may arise. The organization may or may not be able to make sell and/or get their product out in timely matter for their customers. Moderately often costs are capable of instantly saved from merely organization price variances, typically a very easy savings to implement. One of the biggest challenges in analyzing other direct costs is ensuring that they have not been captured in another part of the total cost. As with labor and material costs, other direct costs are those costs that are able to accredit to specific cost objectives and are not previously identified as a direct material cost, direct labor cost, or indirect cost. Although these costs are usually stimulating as indirect, because the proposed contract requires a large, unusual, or one-time expenditure, it might be charged to a specific cost objective.…

    • 346 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Management

    • 1620 Words
    • 7 Pages

    A _______________ is a temporary endeavor undertaken to create a unique product, service, or result.…

    • 1620 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    d. interview a small number of top managers to identify their goals and criteria for achieving success.…

    • 1176 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Energy has always been a must for national development. Nearly every aspect of development from reducing poverty and raising living standards to improving health care, industrial and agricultural productivity requires reliable access to modern energy resources. Countries may have different reasons for considering starting a nuclear power project to achieve their national energy needs, such as: lack of available indigenous energy resources, the desire to reduce dependence upon imported energy, the need to increase the diversity of energy resources and/or mitigation of carbon emission increases.…

    • 5734 Words
    • 23 Pages
    Powerful Essays
  • Good Essays

    Project Management

    • 124711 Words
    • 499 Pages

    The most exciting and significant episode of scientific progress is the development of thermodynamics and electrodynamics in the 19th century and early 20th century. The nature of heat and temperature was recognized, the conservation of energy was discovered, and the realization that mass and energy are equivalent provided a new fuel, – and unlimited power. Much of this occurred in unison with the rapid…

    • 124711 Words
    • 499 Pages
    Good Essays
  • Good Essays

    Project Management

    • 545 Words
    • 3 Pages

    After mentioning the five quality metrics, which one are we going to use to identify the problem we are now facing?…

    • 545 Words
    • 3 Pages
    Good Essays