Interview Question and Answer for Sap Sd

Only available on StudyMode
  • Download(s) : 297
  • Published : March 13, 2013
Open Document
Text Preview
1. What is total float?
2. What are the difference between free float and total float? 3. What is a constraint?
4. What are the difference between MS Project and Primavera? 5. How to load cost & resource in a program?
6. What is WBS?
7. What is a milestone? What are the types of milestone?
8. What are the difference between flag and milestone activity? 9. What is a critical activity?
10. What is resource allocation and leveling?
11. What is a Baseline Program?
12. What are BSWS, BSWP, and ACWP?
13. What are SV and CV?
14. What is a Budget and how do you compare budget against Actual cost? 15. What is an S – Curve?
16. What is the difference between P3.1, P3E, and P5 etc. 17. What is an open end activity?
18. How often you update your program?

1) In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: subsequent tasks ("free float")
project completion date ("total float")
An activity on critical path has "zero free float", but an activity that has zero free float might not be on the critical path. Total float is associated with the path. If a project network chart/diagram has 4 non-critical paths then that project would have 4 total float values. The total float of a path is the combined free float values of all activities in a path. The total float represents the schedule flexibility and can also be measured by subtracting early dates from late dates of path completion.[1] Float is core to critical path method. Example

Consider the process of replacing a broken pane of glass in the window of your home. There are various component activities involved in the project as a whole; obtaining the glass and putty, installing the new glass, choosing the paint, obtaining a tin tty once it has set, wiping the new glass free of finger smears etc. Some of these activities can run concurrently e.g. obtaining the glass, obtaining the putty, choosing the paint etc., while others are consecutive e.g. the paint cannot be bought until it has been chosen, the new putty cannot be painted until the window is installed and the new putty has set. Delaying the acquisition of the glass is likely to delay the entire project - this activity will be on the critical path and have no float, of any sort, attached to it and hence it is a 'critical activity'. A relatively short delay in the purchase of the paint may not automatically hold up the entire project as there is still some waiting time for the new putty to dry before it can be painted anyway - there will be some 'free float' attached to the activity of purchasing the paint and hence it is not a critical activity. However a delay in choosing the paint in turn inevitably delays buying the paint which, although it may not subsequently mean any delay to the entire project, does mean that choosing the paint has no 'free float' attached to it - despite having no free float of its own the choosing of the paint is involved with a path through the network which does have 'total float'.

In continuation of the PMP terminology discussions here, here and here, let’s talk about Time Management knowledge area. Here are a few. Duration vs Effort
When we are estimating the time required to complete an activity, we use the words effort, duration etc… Is duration and effort same? NO. Effort is the actual amount of time spent to carry out an activity. This can be expressed in terms of person hours, man days or man months. It shows the total number of hours/days/months that each person spent working on each of the activities. Duration is the amount of time taken to carry out an activity. That is the start time and end time which is nothing but the time elapsed to complete the activity. Duration is measured in hours/days etc.. This doesn’t count the number of people working on the activity. For example: An activity takes 4 hours to work by one person.  The...
tracking img