Supporting Activity
Provide real-world examples of activities where each dependency type is used: finish-to-start, start-to-start, finish-to-finish, and start-to-finish.

Finish-to-Start: the most common causal relationship hence no explanation is necessary for its usage.
Start-to-Finish: Rarely used but is useful when developing a schedule backwards from a fixed end date.
Start-to-Start: this represents a true relationship between two activities and has nothing to do with their predecessors. If I happen to have two tasks that start at the same time because of a predecessor, that is better represented as two finish-to-start relationships (e.g. systems testing & developing documentation can both begin once development is complete, but there is no relationship between systems testing & developing documentation so we wouldn’t want to use a Start-to-Start dependency here). This dependency is often used with a lag to represent the connection between two activities that run in parallel but cannot start at exactly the same time (e.g. apply the first coat of paint & apply the second coat of paint). A true Start-to-Start example is a race between two runners where each runner is represented as a separate activity – while they will likely finish at different times, both must start at exactly the same time.
Finish-to-Finish: this is generally used to represent activities that must complete at the same time so as to not impact their successor activities or one or more of the objectives for the project. A non-project example of this is the act of preparing food at a restaurant – the chefs must ensure that the main course and garnishes are ready at exactly the same time so that plating can be done without impacting quality.

Which metric does a project manager have most control over: cost variance, schedule variance, cost performance index, or schedule performance index? Explain how so. Which one does a project manager have least control over?

A project manager has most

You May Also Find These Documents Helpful

  • Good Essays

    Defines all the work required to complete a project successfully, and should ensure that the…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    b. Finish to Finish relationships require that two linked activities share a similar completion point. An example would be in a 10 step/activity project, some of the steps may have the same completion point, i.e. steps 4 and 5. This means you do not need to wait until step 4 is completed prior to starting step 5, you can work them at the same time and complete them on the same completion date.…

    • 310 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    constrained because a. each of the activities are independent from the c. the activities use different resources to be other activities. completed. b. one activity cannot be started until the d. some activities use the same resources that may predecessors are finished. not be available. ANS: B Feedback A Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. B Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. C Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. D Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. PTS:1 DIF: M OBJ:1. Create a network…

    • 17168 Words
    • 69 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Breed's New World Teams

    • 772 Words
    • 4 Pages

    | These concepts are set up for a relatively short period of time to complete a task. The people will work during the projects or task and when it’s finished they will split e.g. a property development team.…

    • 772 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    What Is Project Schedule

    • 359 Words
    • 2 Pages

    Is the framework of project management, a milestone is a special event that receives special attention such as a Defense Acquisition (below): Although milestones are put before the end of a phase so that the corrective actions in a case of problems can still be met and the deliverable can be completed in time. Milestone charts are similar to bar charts although milestone charts identify scheduled starts, or completion of major deliverables and a key external interface.…

    • 359 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Greendale Stadium Case

    • 1281 Words
    • 6 Pages

    1. Will the project be able to be completed by the May 20 deadline? How long will it take?…

    • 1281 Words
    • 6 Pages
    Better Essays
  • Good Essays

    Quality - The amount of time put into individual tasks determines the overall quality of the project. Some tasks may require…

    • 1112 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Using the arrow and node method, you can depict project dependencies. In the diagram to the right, you see that Event C depends upon activities from Events A and B to be completed, and Event D depends upon Event C’s activities to be completed.…

    • 446 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    A project is said to be complete when the output not only conforms to pre-defined requirements but also to quality standards of the category it falls in. e.g.…

    • 1816 Words
    • 8 Pages
    Powerful Essays
  • Powerful Essays

    Project management

    • 10285 Words
    • 42 Pages

    Each project is composed of a series of jobs or tasks that must all be completed before we can say, “We finished the project.” These tasks are referred to as the “activities” of a project.…

    • 10285 Words
    • 42 Pages
    Powerful Essays
  • Better Essays

    Earned Value Management

    • 2630 Words
    • 10 Pages

    In the context of earned value there are key measurements that a project manager should keep their attention on. Both schedule variance and cost variance gives a project manager an overview of the project’s status. Schedule variance is the deviation of time in relation to the planned progress and earned progress. This helps the project manager to determine whether the project is behind schedule or if it is on schedule. On the other hand, cost variance is the deviation between earned value and actual cost of the progress. It determines if the current progress of the project is already over budget or not.…

    • 2630 Words
    • 10 Pages
    Better Essays
  • Satisfactory Essays

    When I'm working on a project, I don't want just to meet deadlines. Rather, I prefer to complete the project well ahead of schedule.…

    • 4715 Words
    • 13 Pages
    Satisfactory Essays
  • Powerful Essays

    Gbp/Usd

    • 4417 Words
    • 18 Pages

    A task is an activity completed within a defined period of time. A dependency is a link among project tasks. A deliverable is a tangible or intangible object (a report, a document, technical diagram of the product etc.) produced as a result of the project. A deliverable may be composed of multiple smaller deliverables. A milestone is a measurement of progress toward an outcome. A typical milestone might be the completion of a product design. A resource (e.g. people, equipment, facilities, funding etc.) is something that is required for the completion of a project tasks.…

    • 4417 Words
    • 18 Pages
    Powerful Essays
  • Powerful Essays

    Pmp Sample Questions

    • 21898 Words
    • 88 Pages

    5. You are the project manager for the NBG Project. This project must be completed within six months. This is an example of which of the following?…

    • 21898 Words
    • 88 Pages
    Powerful Essays
  • Good Essays

    Another activity that must be performed during the termination phase is assuring that all payments have been collected from the customer. Many contracts include a progress payment clause, which states that the customer will make the final payment at the completion of the project. In some cases, the final payment is a high percentage of the total project price—for example, 25%. Also it should be verified that all payments have…

    • 519 Words
    • 3 Pages
    Good Essays