Preview

Calculating and Interpreting a Project Network Diagram

Better Essays
Open Document
Open Document
1185 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Calculating and Interpreting a Project Network Diagram
In the world of project management, utilizing the three-point technique can prove to be an invaluable tool. In addition to the three-point technique applying the earliest-start (ES), earliest-finish (EF), latest-start (LS), and latest-finish (LF) procedure to identify the critical path, the project completion time, and the slack for each task can prove to be set of invaluable data that will assist the project manager in accurately determining task duration estimates for the entire scope of work for the project. In this week’s assignment we will explore a construction company and the associated time estimates for each task as it relates to their entire project.
In Table 1.0 you will find the results of our initial analysis which includes the optimistic (O), most likely (M), and pessimistic (P) estimation for duration times it will take to complete each task (A-J). Additionally, when taking the estimated numbers of O, M, and P and applying the equation “E = (O + 4M + P)/6 provided by Wysocki (2009, pp. 152) we are able to obtain the results of (E).” Furthermore, Table 1.0 provides the results of the ES to FS procedure “which consists of the earliest times at which a task can start and finish” (Wysocki, 2009). This process is known as the “forward pass through the network diagram” (Time management). Also the “LS to LF procedure “which consists of the latest times at which a task can start and finish without delaying the completion date of the project” is calculated (Wysocki, 2009). This process is known as the “backward pass through the network diagram” (Time management). Both the ES to FS and LS to LF procedures were calculated based on all the dependencies between each of the tasks outlined below.
The last section of Table 1 highlights the slack time available for any given task (A-J). In order for the slack time to be calculated for each task the project manager must subtract the LF from the EF in each task. “All of the jobs on the critical path, by



References: Steven Bonacorsi (2011). Critical Path Mapping [Accessed 20th March, 2011]. Available from: http://www.projectsmart.co.uk/critical-path-mapping.html Time Management [Online]. (unkown) [Accessed 20th March, 2011]. Available from: http://examples.oreilly.com/9780596102340/hfpmp_ch06_errata_pp257-265.pdf Wysocki, K. R. (2009). Effective Project Management. 5th ed. Indianapolis, IN: Wiley Publishing, Inc. p151 – 197

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints?…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    The project staff analysed with basis in a series of factors like training staff, adequate to legislative requirements, measuring risks, availability of the budget and quality standards to set a timeline. Once every step is scheduled, the whole staff can work with a estimated and real parameter of timeline.…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Introduction to Project Scheduling IX. The Critical Path Method (CPM) X. Program Evaluation and Review Technique (PERT) XI. Project “Crashing”…

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    AIB Problem

    • 565 Words
    • 3 Pages

    Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) Answer: 30 days b) Identify the critical path (6 points) Answer: B, C, D, F, H c)…

    • 565 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    1. The activities involved for the project schedule can be represented using Central Path Method (shown below) showing various interdependence and parallelism among activities.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Scope Statement

    • 463 Words
    • 2 Pages

    The time required to complete execution phase is 147 because the number of tasks to…

    • 463 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Assembly Line Design

    • 525 Words
    • 3 Pages

    The following tables give the tasks, task times, and predecessors that are to be performed on an…

    • 525 Words
    • 3 Pages
    Satisfactory Essays