Aib Problems -Project Manangement
ActivityDurationPredecessors
A3 Days---
B4 Days---
C6 Days---
D2 DaysA, B
E1 DaysC
F3 DaysD
G3 DaysE, F
H7 DaysD
I10 DaysG
a. For the above information, draw an AIB diagram.
[pic]
Slack or Float = LF – EF or LST – EST
Activities on the critical path have zero slack/float.
b. What is the Scheduled Completion of the Project? 22 Days c. What is the Critical Path of the Project? B-D-F-G-I
d. What is the EST for Activity D? Day 4
e. What is the LST for Activity G? Day 9
f. What is the EF for Activity B? Day 4
g. What is the LF for Activity H? Day 22
h. What is the float for Activity I? 0 Days
Problem 2
The following data were obtained from a project to build a pressure vessel:
ActivityDurationPredecessors
A4 weeks---
B4 weeks---
C3 weeksB
D2 weeksA, C
E3 weeksB
F5 weeksD, E, G
G2 weeksB
H6 weeksF
I3 weeksG
J1 weekI
a.Construct a network for the project.
[pic]
Slack or Float = LF – EF or LST – EST
Activities on the critical path have zero slack/float.
b.Calculate the scheduled completion time and identify the critical path. Scheduled completion time = 20 weeks
Critical Path = B, C, D, F, H
c.What is the slack time (float) for activities A, D, E, and G? A=3 weeks
D=0 weeks
E=2 weeks
G=3 weeks
Problem 3
The following data were obtained from a project to design a new software package:
ActivityDurationPredecessors
A3 Days---
B6 Days---
C4 DaysA
D2 DaysC, B
E3 DaysA
F2 DaysD, E, G
G2 DaysB, C
H1 DayG
a.Construct a network for the project.
[pic]
Slack or Float = LF – EF or LST – EST
Activities on the critical path have zero slack/float.
b.Calculate the scheduled completion time and identify the critical path(s). Scheduled...