The Accounting Software Installation Project Case Study
1. EXECUTIVE SUMMARY

Accounting Software Installation Project started four months ago and is managed by Karin Chung. Karin thought she had everything planned before the project started. Each company division had trained and informed task force members and six the contractors involved in the project contributed to the work breakdown structure, cost, timeframes and specifications of the project. Karin got all the important role players together at the beginning of the project and conducted a one day partnering workshop where all the major accounting heads of the different divisions, one member of each task group and key persons from each contractor were invited. The main purpose of the workshop was to improve team building amongst the different divisions with its task groups and the contractors.

Two months after the start of the project the first of several problems occurred that should have been a major concern to Karin as the project manager. Karin did not address the problems and because of her actions the project was falling apart after four months.

No integration of project activities took place and that was the main reason why contractors were blaming each other and the project was two months behind schedule.

Although problems have been identified that should have been a major concern to Karin, there was no risk scheduling in place from her side.

Lack of leadership and poor project management by Karin was a big concern. There was no managing of effective control on project performance, no reporting lines were in place and no progress reports have been completed.

Karin, the project manager had bad communication skills, she created confusion, resulting in the breaking down of relationships between the different role players. She did not play a leadership role. All of that resulted in poor team work between the different contractors and the task team members from the different company divisions.

There was no cooperation between the

You May Also Find These Documents Helpful

  • Satisfactory Essays

    A Professional Failure

    • 358 Words
    • 2 Pages

    The most important thing I learned from this experience is the key role of a project leader, a person who could select the right people in the team, coordinate the relationship between client team and technology team, monitor the progress to ensure not shift to the target. Without such a leader, although we had world-class technology team and emotion, this project finally failed. The particular experience is important to me because I am aware that I am lack of project management skill to maximum my solid technology skills to well sever my clients. This is a major…

    • 358 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Bella Healthcare India

    • 551 Words
    • 2 Pages

    3. The project was far behind the schedule, causing heavy cash burden on the company.…

    • 551 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Case 3 Risk Management

    • 1053 Words
    • 5 Pages

    The essential of having a successful project management team is very important. Having strategic risk management techniques is essential. When planning a project team, it is sometimes strongly advised to think in a futuristic mindset by thinking of the “what if’s” how do’s, how comes, and planning out all the possible risks. There may be various explanations of the project team failures, including poor communication among the team, misconstruing of its shared facts, and unclear and uncertain positions. Also the roles and responsibilities of the team members. (Fottler, Kloppenborg, McAfee, & Nkomo, 2012). Without a clear sense of communication as well as instructions between the project team, it is virtually impossible to have a successful clear-minded team. Without clear sharing of information among the project team, there lies an opportunity for misinterpretation, and spreading false information. In additional…

    • 1053 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    7. Unproductivity. This is a huge problem when project deadlines must be met. This project requires multiple steps to get it done…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Rachel needs to improve her system of checking her email/voice mail. She had several unplanned breaks and should improve the way she is managing interruptions and the project status meetings. She has not established the right process of communication between marketing and the project management team. She wasted time taking responsibility of Victoria’s project instead of bringing it to the portfolio management team.…

    • 272 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Orion Shield Project

    • 5525 Words
    • 23 Pages

    Executive Summary The basic concepts of project management calls for proper planning, organization and the management of a variety of resources in order to successfully achieve a certain goal. One of the most important objectives of project management is the ability to deliver a product or service within a certain time constraint or “on time” as well as being fiduciary responsible or “within budget.” Thus, it can be seen that good project management makes efficient use of time, money, personnel, materials and supplies, and methods of communication in order to successfully complete a project. Unfortunately, these basic methods of project management were not…

    • 5525 Words
    • 23 Pages
    Powerful Essays
  • Good Essays

    The first reason is poor planning. Big projects can be very complicated, if your team are not sure what they are supposed to be doing there will be sections missing, there may even be people working on the exact same thing. Also, as shown by the second example bellow, not accounting for all factors when planning can result in failure.…

    • 849 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Kathy, the project manager, obviously did not have the people skills or knowledge of the culture needed to be successful on this project. Had she researched the culture, listened to her team members, and worked with them rather than over them, this project would have been more successful. Also she should implement incentives for the team.…

    • 620 Words
    • 3 Pages
    Satisfactory Essays
  • Better Essays

    Senior Management

    • 1685 Words
    • 7 Pages

    6) Lack of project ownership from the senior management team – It was only Frank Carau and Ben Walker, who are juniors that are handling the project. It does not have enough clout to direct and influence the project on the senior management levels. However, with the leadership and sponsorship of Phil Faraci, the project came into a turn-around from being a slow-paced to fast-paced project, from being a…

    • 1685 Words
    • 7 Pages
    Better Essays
  • Good Essays

    Investiong in Tufs

    • 524 Words
    • 3 Pages

    Another thing that went wrong in the project is the imbalance between its scope and the scheduling of the project as result of the management pressure to produce fast result regardless of what feasible. This problem would have avoided if the scheduling of the project take into account what was possible more than what was desired given the scheduling of the project.…

    • 524 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    * Rigid budget process => IT struggling to keep up with the resources (refer to Budgeting and IT strategies)…

    • 296 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    BAE Case

    • 520 Words
    • 2 Pages

    The project team and the consultants have a communication gap which led to the lot of issues. Likewise, the work is not allotted in time as the projected previous work was prolonged than the proposed completion time which made the delay in completion. There were some issues between workers due to lack of communication like the materials were ordered, when the delivery was there the employee was unaware that those are needed and he sent back the delivery thinking that those are not necessary for construction. In this way, it took more days to get redelivery and the work got postponed in the gap.…

    • 520 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    BUSI 682: Project Analysis

    • 1573 Words
    • 7 Pages

    project could produce the results they expected, or still expect. It is terrible a project must early,…

    • 1573 Words
    • 7 Pages
    Good Essays
  • Good Essays

    Appointing people who believe and committed to the project into leadership position to lead the team and make time for communication from team and other leadership (Wager, Glaser, 2009). Another issue that was an indicator of failure to this project was the requirements analysis was rushed several key workflow and system integration issues were missed. To minimize this indicator a thorough requirement analysis is done to ensure that all workflow analysis to support the change in workflow and the system requirements analysis to ensure the requirements needed for the system to work are aligned with the strategic goals of the organization (Wager, Glaser, 2009). Budget cut to the project was a big indicator the would lead to failure of this project because in the status review meeting it was presented that the project was on scope, on schedule, and on budget led to leadership taking resources from the CPOE project. It is important the present a true picture…

    • 762 Words
    • 4 Pages
    Good Essays
  • Better Essays

    1. No proper project structure - this made the execution and management of the project very ineffective.…

    • 1618 Words
    • 7 Pages
    Better Essays

Related Topics