Preview

opma 317

Satisfactory Essays
Open Document
Open Document
395 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
opma 317
2. Work Breakdown Structure

1. Open Building
1.1. Recruit Staff
1.1.1. Set Staff Requirements
1.1.2. Recruit Potential Staff
1.1.2.1. Advertise Openings
1.1.2.2. Screen Applicants
1.1.2.2.1. Check References
1.1.2.2.2. Conduct Interviews
1.1.3. Train Hired Employees
1.2. Construct Building
1.2.1. Hire Contractor
1.2.1.1. Research Potential Contractors
1.2.1.1.1. Check Past Projects
1.2.1.1.2. Look Into Reputations
1.2.1.2. Obtain Quotes
1.2.1.3. Choose Contractor
1.2.2. Landscape Site
1.2.3. Complete Interiors
1.2.4. Inspection
1.2.5. Final Cleanup
1.3. Create Final Drawings and Obtain Building Permits
1.3.1. Obtain Board Approval
1.3.1.1. Prepare Rough Drawings
1.3.1.2. Prepare Budget
1.3.1.3. Prepare Proposal
1.3.2. Ensure Project is Legal
1.3.2.1. Contact Municipality
1.3.2.2. Check Building Codes
1.4. Install Furniture
1.4.1. Order Furniture
1.4.1.1. Discuss With New Employees
1.4.1.2. Determine Required Amounts
1.4.1.3. Obtain Quotes
1.4.1.4. Select Supplier

4. Path Identification

1,2,3,4,9,13 – 45 weeks
1,2,3,4,8,10,11,12,13 – 48 weeks
1,2,5,7,12,13 – 47 weeks
1,2,6,7,12,13 – 21 weeks

5. Project Duration and Cost

Normal Project Duration is 48 weeks.
Normal Project Cost: $2,168,000

6. Project Crashing

Activity To Crash
# of Weeks to Crash By
Total Crash Cost
Path 1,2,3,4,9,13
Path 1,2,3,4,8,10,11,12,13
Path 1,2,5,7,12,13
Path 1,2,6,7,12,13
2
1
$3000
44
47
46
20
1
1
$4000
43
46
45
19
1
1
$4000
42
45
44
18
11
1
$8000
42
44
44
18
7,8
1
$23000
42
43
43
17
7,8
1
$23000
42
42
42
16
4,7
1
$33000
41
41
41
15
4,5
1
$35000
40
40
40
15
4,5
1
$35000
39
39
39
15
4,5
1
$35000
38
38
38
15
4,5
1
$35000
37
37
37
15

8. Activity Delay

Since two weeks were added to task #3 - Obtaining Final Drawings and Building Permits, in order to complete the project in the original normal time with minimal costs, he would crash activities #2, and #1 since these activities would reduce the project by two weeks’ time at a minimal cost of $7000 as shown by our project crashing

You May Also Find These Documents Helpful

  • Powerful Essays

    • The project schedule is liberal in respect to time for completion of each phase, because not keeping up with the…

    • 1244 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points)…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Cas 315

    • 1522 Words
    • 7 Pages

    This case has been adapted from the textbook (6th edition) Discussion Case Question 8-6 and Discussion Case 6-8:…

    • 1522 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    2. Delay in caging material and other needed materials for project completion. This is lack of needed items to re-build shelter cages inside and outside.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Ou B120 Tma01

    • 947 Words
    • 4 Pages

    I have been asked to identify and explain any problems at the Ottershaw branch of…

    • 947 Words
    • 4 Pages
    Good Essays
  • Good Essays

    many constructional projects had broken its budget. There are a lot of reasons, such as increasing scope, extending time, and inflation.…

    • 311 Words
    • 2 Pages
    Good Essays
  • Good Essays

    4 Hour House

    • 915 Words
    • 4 Pages

    Need to have clear goals. In this case the clear goal was to build a 3 bedroom, 2 bathrooms and have it in ready to move-in conditions in under 4 hours.…

    • 915 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Annotated Bibliography

    • 680 Words
    • 3 Pages

    Assaf, S.A. and Al-Hejji, S. (2006) Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-57.…

    • 680 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Ghost Stories

    • 749 Words
    • 3 Pages

    * Ask from the headquarter construction firm to provide him a number of workers either from the main office or countries around to enable the project to be finished in predefined time frame. However, administrative staff coordination may cause the project excessive cost.…

    • 749 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    A&D High Tech

    • 4238 Words
    • 17 Pages

    We are presenting two alternatives for carrying out the project in a shorter time frame, like working overtime or hiring extra resources. We have mixed the two alternatives so that the tasks that are quality sensitive/critical will be crashed by subcontracting additional resources to avoid employee fatigue that can effect the quality of the work, while the tasks that are indivisible or have a learning curve that need to be done by one resource will be crashed by overtime work.…

    • 4238 Words
    • 17 Pages
    Powerful Essays
  • Satisfactory Essays

    Providing new jobs, both during and after work, specialized training for employees, developing team spirit of entrepreneurship.…

    • 488 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Spanning the Globe

    • 689 Words
    • 3 Pages

    This brings up the failure of training and development. Lack of pre-planning for this assignment resulted in the increase in time period of the assignment from 18 months to 3 years. This was mainly due to Fred’s inability and unwillingness to work with other local engineers and the local government in India.…

    • 689 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Fitzberg Tire Company

    • 796 Words
    • 4 Pages

    The Fitzburg Tire Company's construction manager, Max Bierman, has been working on a plant in Cuernavaca, Mexico. This plant is Bierman's first assignment outside the U.S. and it is not going according to his expectations. After merely three months, the project is running behind schedule and overriding its forecasted budget. The occurring…

    • 796 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Bella Healthcare India

    • 551 Words
    • 2 Pages

    2. The initial goal of the project was too ambitious and too fast than comparable projects, which is difficult to achieve;…

    • 551 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    EDA 3046 unisa

    • 2056 Words
    • 8 Pages

    They were formed to develop and coordinate the growth of environmental education in the sub continental region.…

    • 2056 Words
    • 8 Pages
    Satisfactory Essays