Preview

Natural Blends

Good Essays
Open Document
Open Document
556 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Natural Blends
Project Management Case Assignment - Use Microsoft Project to analyze this case. This is an example of a construction project. The construction for a large corporate building must be started by February 15th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. The details of the project activities are as follows – The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared. The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins. Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 15th, 2010 which is a Monday and that you work five days a week for 8 hours every day. Analyze the following questions based on the estimates of the above activities 1) When do you complete the project?

You May Also Find These Documents Helpful

  • Good Essays

    Nt1330 Unit 4

    • 4542 Words
    • 19 Pages

    The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.…

    • 4542 Words
    • 19 Pages
    Good Essays
  • Better Essays

    Cee 201 Final Project

    • 2071 Words
    • 9 Pages

    Introduction What a better way to end the year in CEE 201 with a construction project that deals with bidding. Our studies throughout the year have been focused upon engineering economics transitioning into linear programming models in order for engineers to make educated decisions in real life situations. In order to supplement this thought process, the construction game was created that deals with placing bids, ordering labor, and hiring workers to make a year’s end profit. This game is structured around placing bids against other teams within the class for three rounds over three years. If the bid is won for your team, your company completes the project and the profit is later computed. As with every reasonable game, there are rules to be followed. Each team has secured a capital of ten million dollars total for the three fiscal years. Before bids are placed, your company must purchase all the concrete and labor that will be required throughout the year. Unused money will increase by four percent each year in the stock market while additional funds beyond the ten million venture of capital funding will be secured via a loan with a ten percent annual interest rate. With purchasing concrete and construction workers, there are constraints to find certain values. Each construction worker will work up to two thousand hours per year and receive an annual salary of fifty thousand dollars. Unions demand that hired workers are paid whether they are actually put to work or not and the unions have agreed that workers may divide their hours of labor between multiple projects. Each cubic yard of concrete costs one hundred dollars and includes cost of purchase and transportation. Unused labor does not carry over into the following year, but concrete does. Unused concrete can be salvaged for ten dollars per cubic yard at the end of year three. Unused labor will be sold to a temporary agency for fifteen dollars an…

    • 2071 Words
    • 9 Pages
    Better Essays
  • Satisfactory Essays

    Mgmt 122 Case 1

    • 487 Words
    • 2 Pages

    b. Assign costs to a 3,000 square foot job that requires 70 contact hours, 20 design hours, and 14 days to complete.…

    • 487 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    The project staff analysed with basis in a series of factors like training staff, adequate to legislative requirements, measuring risks, availability of the budget and quality standards to set a timeline. Once every step is scheduled, the whole staff can work with a estimated and real parameter of timeline.…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    5. Mattox Company is building a new plant that will take three years to construct. The construction will be financed in part by funds borrowed during the construction period. There are significant architect fees,…

    • 1907 Words
    • 8 Pages
    Good Essays
  • Powerful Essays

    Essay

    • 1594 Words
    • 7 Pages

    The construction must start on January 14, 2004 and must be completed within fifteen months. Liquidated damages (penalty clause) of $250,000 per calendar day of delay beyond March 31, 2005 is written into the contract. On the other hand, Ace will receive an Early Completion Bonus of $100,000 per day for each workday the project is completed before March 31, 2005.…

    • 1594 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    operation management

    • 252 Words
    • 1 Page

    Read the Specialty Contractors case (download) and submit your analysis of the exercise - i.e., identify which activities should be crashed and by how much time, what is the cost of doing this and how soon can the project be completed. (Hint: Use the greedy algorithm taught in class even though it is not guaranteed to always find the optimal solution.) [Please submit your assignment as an attachment.]…

    • 252 Words
    • 1 Page
    Satisfactory Essays
  • Powerful Essays

    Blended

    • 5457 Words
    • 25 Pages

    Phone: 979-209-8607 You may leave a voicemail , but you must include your name and the question in the message. Do not leave a message to ‘call you’. I need to know why you want to talk to me so I may have an answer ready for you when I call you back.…

    • 5457 Words
    • 25 Pages
    Powerful Essays
  • Satisfactory Essays

    Project management week 2

    • 284 Words
    • 3 Pages

    Control Scope a. Inputs i. Project mgmt. plan ii. Work Performance info iii. Requirement Doc iv.…

    • 284 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    1. What is the estimated project completion date? (Assume there are no holidays and ignore the sunk cost of the planning team’s effort)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Tank Workpt

    • 469 Words
    • 2 Pages

    Advanced Planning Section has been examining some unusual projected problems and requests your assistance on the particular one described below.…

    • 469 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    1. Evaluate the three scenarios proposed by the project team along the lines of the criteria presented in the case…

    • 1596 Words
    • 46 Pages
    Powerful Essays
  • Powerful Essays

    A. OBJECTIVES OF THE PROJECT: (Problem area/s to be investigated, objectives of the project and expected results.)…

    • 6720 Words
    • 27 Pages
    Powerful Essays
  • Satisfactory Essays

    This is all my own work and other sources are properly credited - I certify that the attached assignment is my own work. Material drawn from other sources has been appropriately and fully acknowledged by providing author/creator, source and other bibliographic details. Such referencing meets unit-specific requirements of format and style.…

    • 379 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    At the meantime, the company manager decide to tender an interior design project in Subang Jaya, the contract sum is RM 1,640,000 (Ringgit Malaysia : One Million and Six Hundred Forty Thousand Only). If the company got the Letter of Award for that project, the project may start at the end of August 2008. This project will taken 2 months to complete. Then, the company has to make sure they have enough funds…

    • 415 Words
    • 2 Pages
    Good Essays