A production manager for an exercise equipment manufacturing company needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Using the following table and product structure for the UltimaSteppers:
Item | Lead Time | On-Hand Inventory | Components | Stepper | 2 | 20 | A(1), B(3),C(2) | A | 1 | 10 | D(1),F(2) | B | 2 | 30 | E(1),F(3) | C | 3 | 10 | D(2),E(3) | D | 1 | 15 | | E | 2 | 5 | | F | 2 | 20 | |
Level
0
1
2
Q1: construct the Bill of Material (BOM)
Q3: Develop a Gross Requirements Plan for the UltimaSteppers
Q2: Develop a net material requirements plan for the UltimaSteppers
Q1:
The requirements for an order of 50 UltimaSteppers:
Part A: 1 x number of Stepper's = (1)(50) = 50
Part B: …show more content…
receipt | | | | | | | | 30 | P.O. release | | | | | | 30 | | | | | | | | | | |