Project Charter

3rd
NATIONAL
TRUST

Project Name
The Eastland Mall Branch Bank Project

Customer/ Client
Board of directors and their mandated representative,
CEO Mr Buzz Adams

Project Manager
Vince Stewart

Duration
06 September 1976 to 04 September 1978 (2 years)

CONTENT PAGE
1.Purpose of the Project Charter…………………………………………….4 2.Background……………………………………………………………………4 3.Project Name………………………………………………………………….4 4.Customer………………………………………………………………………5 5.Project Manager………………………………………………………………5 6.Problem Statement…………………………………………………………..5 7.Project Visions and Objectives……………………………………………5 8.Proposed Solutions…………………………………………………………..6 9.Project Phases………………………………………………………………..6 10.Inclusions and Exclusions…………………………………………………7

10.1Inclusions………………………………………………………………7
10.2Exclusions……………………………………………………………..7 11.List of Assumptions………………………………………………………….8 12.Constraints to the Solutions………………………………………………..8 13.Stakeholder……………………………………………………………………9 14.Project Team………………………………………………………………….9 15.Scope Charter………………………………………………………………..10 16.Charter Approval…………………………………………………………….11 17.Signatures…………………………………………………………………….11 18.Eastland Mall Branch Saturday Hours Project Plan…………………..12

18.1Work Breakdown Structure….....................................................12
18.2Project: Inputs and Outputs…………………………………….…13
18.3Deliverables……………………………………………………….….16
18.4Receivables………………………………………………………….17 19.Implementing Saturday Hours Budget……………………………….…18 20.Implementing Saturday Hour Schedule………………………………...20
20.1Gantt Chart……………………………………………………….….20 21Eastland Mall Branch Project Organisational Chart…………………23

1. Purpose of the Project Charter
A project Charter ensures that everyone with a stake in the project’s success has fundamental knowledge about the project and is working towards the same objectives. It increases the feasibility of the project work plan by creating a common understanding of the individual roles and responsibilities, timelines, deliverables, and processes. It is a critical project management tool, serving as a reference to keep the project on track and focused, and can help mitigate issues throughout the project by providing a source of information about the project structure and goals. The Project Charter should be formally endorsed by the project sponsor.

2. Background
Third National Trust (TNT) has been a key role player within the financial sector for 82 years, and is located in a major Midwestern city in Europe. It has Assets totalling $2.1 billion with 91 branches serving the commercial interests and residential mortgage markets. Third National Trust is firmly established as one of the five dominant banks, however in comparison to their competitors the bank was lagging behind in its use of technology and services offered, which led to the closure of several of its national branches. In order to remedy the ailing situation the Board of Directors appointed a new CEO, Buzz Adams, whose belief was that computers and communications technology is the answer to redefining Third National Trust as a worthy competitor within the financial market. The appointed Project Manager, Vince Steward to will manage the Eastland Mall Branch Bank project in terms of the objectives outlined below.

3. Project Name

The project was launched on the 6 September 1976 and officially named The Eastland Mall Branch Bank Project

4. Customer
The customer in the Eastland Mall Branch Bank project is the board of directors and their mandated representative, CEO Mr Buzz Adams

5. Project Manager
Vince Steward as appointed by Mr J O’Boyle the Senior Vice- President of Systems and Software Programming. Mr Stewart has been employed with Third National Trust since 1972 and took a keen interest to Project Management over the years. He worked on the analysis and software for a series of cheque transportation studies. He fast became the leading...