Preview

Huntsville Project - Week 5 Risk Matrix Analysis

Satisfactory Essays
Open Document
Open Document
311 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Huntsville Project - Week 5 Risk Matrix Analysis
Class: PM586 Online
Week 5 Risk Matrix Analysis

Identification | Assessment | Response Plan | Risk | Consequence | Probability | Impact | Trigger | Resp. | Response | Cost / time overrun | Budget Overrun | Low | High | .Rising commodity prices
. Increase in labor cost | PM | Close monitoring of budget and time | Permit Delay | Might cause delay and missed schedule | High | High | Delayed securing of permit. | | All requirements must be submitted on time and on schedule. Since permits are done by outside agency, so if all odds fail, then the schedule would have to be adjusted accordingly. | Inclement Weather | Delayed work | High | Low | Mother Nature | | Weather is something that can't be predicted but scheduling can be done such that construction begin and end during the summer season. |

Increased cost and time are a major concern in this project, the probability is low however, if it does occur the impact will be quite high, because it will definitely cause an overrun in the budget and or missed schedule. This risk can be mitigated by closely monitoring the budget against the actual cost and making sure that the project is always within the allocated cost and on schedule.
Permit poses risk because this is something that is completely out of the organization’s terrain, it has to be submitted to the local government office and they have to come out for inspections and this has to be on their own schedule and this could be out of schedule for this project, to mitigate this, the application for permits have to be submitted on time giving more than enough time to hear back from the local government.
Inclement weather, the risk is high but the impact is low, but there is little to nothing we can do about this, it is an act that cannot be controlled and all we can pretty much do is to schedule construction for summer and landscaping for

You May Also Find These Documents Helpful

  • Good Essays

    Is3110 Unit 4

    • 406 Words
    • 2 Pages

    If the project is completed on time then there is no risk for completion. All of the regular risks that apply to a project built on time apply to this one regardless of whether you are building a new infrastructure or modifying an older one. If the project is finished one month early, the quantitative risk really does not exist. It is basically comparable to completing the project on time. Since the project is quoted at 3 million dollars it will stay the same regardless of how fast the project is finished. However, you may see differences. When you rush a project this large you could possibly cut corners or receive poor quality results. If the project is finished two months late there are additional risks. If the company expects to make $20 million dollars annually, and assuming that the 4% penalty is levied against this yearly figure and not within smaller period of time, one month late means that US Industries Incorporated loses $800,000 annually. There doesn't appear to be any additional risk, however, further penalties and the possible eventual loss of the contract to a competitor could result in a poor product. There again appears to be no real quantitative risk involved if the project is finished a month early with the security requirements. If the originally quoted $3 million dollars remains the same regardless of how fast the project is finished and not coupled with hourly or daily wages, then there is nothing to lose financially. However the companies go beyond the required 1.5% completion benchmarks that the contract demands. Rushing a project of this scale also comes with rushed results possibly cut corners or poor quality. The credibility of the company is at stake with such a high profile, high income project such as this, and it is important to use all of the time available to ensure the best product is on display for any customer. The finished project should meet both the time and security requirements but not the service agreement. There does not…

    • 406 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    The project is pouring a concrete patio in my backyard. The results will be a new patio to entertain guests. I am allowing two additional weeks in case there is inadequate funding or scheduling conflicts for the project ending in May of 2008. The two extra weeks are there in case there is an unexpected expense elsewhere, or I can’t get my brother to my house to help out because of scheduling conflicts. Each activity is defined within a week’s time.…

    • 784 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The risks that could be involved are natural disasters such as Earthquakes, structural failure, fires, extreme weather creating floods or blizzard like conditions, and loss of power or shortage.…

    • 656 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    The benefits of risk response control are improves effectiveness and efficiency of the risk approach during the project implementation. Risk response control includes the following elements throughout the project:…

    • 1596 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Our goal is to inform all stakeholders of possible risks that can impact our project in a negative way. This will also inform us as to the status…

    • 1116 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    An increased resources and materials can cause issues that will affect the project severely if not monitored and addressed in time. The probability may be low, but can change due to several economic and/or political issues that may arise. If such an event happens, it can easily have a ripple effect throughout the project. It can cause the budget to be derailed, which can cause the project be put on hold until more affordable materials can be acquired, or the project as a whole not come to completion. To address this issue, the budget and the economic situation must be closely monitored.…

    • 362 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    5. Equipment delay. Equipment needed to complete the project is delayed. Un-availability of equipment. Equipment availability is important as well.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    CLICK TO DOWNLOAD PROJ 592 Project Cost and Schedule Control Week, TCOs, and Topics Readings Assignments Week 1 TCOs A & B Project Definition, WBS, and Cost Project Management for Business, Engineering and Technology Chapter 5: Planning Fundamentals (pp.157-195) Earned Value Project Management Chapter 6: Scope the Project (pp.47-61) You Decide Graded Discussion Topics Week 2 TCOs B & C Financial Plan Project Management for Business, Engineering and Technology Chapter 8: Cost Estimating and Budgeting (pp. 289-331)…

    • 390 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    RISK ASSESSMENT

    • 1988 Words
    • 8 Pages

    Suspetabiltiy of Defalcation??judgments about materiality are made in light of surrounding circumstances, and are affected by the size or nature of a misstatement, or a combination of both; and…

    • 1988 Words
    • 8 Pages
    Good Essays
  • Powerful Essays

    Essay

    • 1594 Words
    • 7 Pages

    In order to meet this aggressive schedule, the project will require around the clock construction crews, detailed project management, good construction weather, and some modern construction techniques.…

    • 1594 Words
    • 7 Pages
    Powerful Essays
  • Better Essays

    Working to understand the risks a project may endure along with the cost associated is critical in every project management plan. Understanding potential risks based on the project type, resources needed, timeline and budget still leaves gaps that creates uncertainty for actually predicating the outcome of the project. There is not a true way to predict when and where a project risk will occur but designing a plan to properly address and manage those risks will increase confidence while eliminating the element of surprise.…

    • 1195 Words
    • 5 Pages
    Better Essays
  • Good Essays

    I had my hearing; they told me I had a 15,000 dollar bond. The judge asked me if I wanted to be appointed a lawyer or wanted to hire one. I told the judge I have no money, my mom barely gets buy and I would like to have a free one. He told me in my current situation that if I get bonded out that I could still get a free lawyer to help me with my case. Hope my mom can get me out today.…

    • 1071 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Risk Assessment

    • 768 Words
    • 3 Pages

    Several new network storage, security, and throughput hardware appliances need to be installed and configured. (Is there room/power/personnel to support this new hardware?)…

    • 768 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Risk Assessment

    • 2166 Words
    • 9 Pages

    I believe without the will to take risk a person would possibly lead an unfulfilling life. We as individuals take risks every day in most every thing we do. We learn from risk taking the possible dangers and how as an individual, decide how we will manage our lives. However those of us who have the capacity to take a risk accept the consequences. I therefore believe those of us who are at a greater risk of harm due to having less capacity to understand the risk to themselves and others, would need support in understanding the risks they take.…

    • 2166 Words
    • 9 Pages
    Good Essays
  • Satisfactory Essays

    The purpose of this project is to build a football stadium to create our own identity in the area of Construction.…

    • 386 Words
    • 2 Pages
    Satisfactory Essays