Eng. Management
Bahcesehir University
Department of Industrial Engineering
INE4009 Engineering Management
Final Exam Paper

Q.1. For the set of tasks given below, do the following: a. Develop the precedence diagram. (5 marks) b. Determine the maximum cycle time in seconds for a desired output of 500 units in a 7-hour day. Why might a manager use a cycle time of 50 seconds? (10 marks) c. Determine the minimum number of workstations for output of 500 units per day. (5 marks) d. Calculate the percentage idle time for the line. (5 marks)

Task Task time Immediate (seconds) Predecessors A 45 _ B 11 A C 9 B D 50 _ E 26 D F 11 E G 12 C H 10 C I 9 F,G,H J 10 I 193

Q.2 ABC Company uses overtime, inventory and subcontracting to absorb the fluctuations in demand for its playgrounds for children. An aggregate production plan is devised annually and updated quarterly. Cost data, expected demand, and available capacities in units for the next four quarters are given here. Demand must be satisfied in the periods it occurs; that is, no backordering is allowed. Design a production plan that will satisfy demand at minimum cost. (25 Marks)

Expected Regular Overtime Subcontract
Quarter Demand Capacity Capacity Capacity 1 650 750 100 500 2 1250 950 150 500 3 1350 1050 200 500 4 2750 1050 200 500

Regular

You May Also Find These Documents Helpful

  • Good Essays

    Having Bob pick up the sandwich bag and put it on the order rack instead of Adam, will make the process capacity slightly go up, so it would increase the revenue a little bit.…

    • 871 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    The second production plan is the chase aggregate plan. In this plan, the aggregate production rate is equal to the demand forecast. As you can see in Table 2, we will hire 26 employees and lay off 18 employees during these 8 months. From these results, they indicate a fluctuation in the size of the workforce, ranging from a high of 21 employees to a low of 3 employees. This means the company must have enough space, tools, and equipment for up to 21 employees during 8 months. In addition, the total cost of this plan is $331,800, and the unit cost is $18.64 ($331,800 divided by 17,800 units).…

    • 177 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    ECO 550 FINAL EXAM

    • 1177 Words
    • 4 Pages

    7. A plant manager is attempting to determine the production schedule of various products to maximize profit. Assume that a machine hour constraint is binding. If the original amount of machine hours available is 200 minutes., and the range of feasibility is from 130 minutes to 340 minutes, providing two additional machine hours will result in the:…

    • 1177 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Dss Consulting

    • 480 Words
    • 2 Pages

    Our first plan (Plan A) includes hiring 4 new employees in January to cover the 2100 units of demand but firing them in February, we will fire these additional employees because the production would be covered. In March, April, and May will fire 4, 3, 3, employees respectively. By doing so, the labor costs are significantly reduced and the unit demand will be covered. In June we neither hire nor fire because our units of demand are covered. However, in July, and August, unit demand picks up and we will hire 5, and 7 employees respectively. In September we fire 4 employees and October we fire 2 employees cutting our labor cost, but still reaching our unit demand. In November we hire 7 employees due to the increase of Holiday sales, and in December we hire 6 employees. By doing so we have a Gross profit of $1,125,189…

    • 480 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Exam 2 Operations Management

    • 2658 Words
    • 11 Pages

    If the actual output of a piece of equipment during an hour is 500 units and its best operating level is at a rate of 400 units per hour, which of the following is the capacity utilization rate?…

    • 2658 Words
    • 11 Pages
    Good Essays
  • Good Essays

    Variable Cost and Company

    • 1030 Words
    • 5 Pages

    Prepare a production budget for the third quarter showing the number of units to be produced each month and for the quarter in total.…

    • 1030 Words
    • 5 Pages
    Good Essays
  • Good Essays

    managerial ehics

    • 1395 Words
    • 5 Pages

    3. Identify and explain the major factors in the social environment that create an atmosphere in which business criticism takes place and prospers. How are the factors related to one another? Has the revolution of rising expectations run its course? Or is it still a vital reality?…

    • 1395 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Management and Business

    • 6774 Words
    • 22 Pages

    Note: Final Sign Off can only be done when the student has completed both theory and practical components of the unit. (Please attach evidence of theory and practical at the back of the coversheet)…

    • 6774 Words
    • 22 Pages
    Powerful Essays
  • Powerful Essays

    Management 1

    • 2584 Words
    • 11 Pages

    1. Evaluate the classic management functions and their relationship to each other, including the extent to which they may or may not be interrelated.…

    • 2584 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    operation management HW1

    • 1231 Words
    • 5 Pages

    units. The workstation produces this part at the rate of 200 units per day. What…

    • 1231 Words
    • 5 Pages
    Good Essays
  • Better Essays

    Toy World Inc Cas Solution

    • 1352 Words
    • 5 Pages

    Toy World, Inc. is a company that has been manufacturing toys for children since 1973. Since 1976, the company has enjoyed profitable operations. At the end of 1993, revenue and profit came close to $8 million and $270 thousand respectively. With Jack McClintock as president and Dan Hoffman as production manager, the two have tried to find a strategy to adjust operations to the volatility of the toy market. Sales in the toy market are seasonal, reaching peaks in the months of August through December, while remaining relatively flat during the remaining months of the year. This seasonality has affected the company’s production schedule. During the off season, inventory is low, skilled workers are underutilized, and machinery is left idle. When the busy season finally arrives, Toy World is forced to hire more workers, pay additional overtime wages, and operate at full capacity. Dan Hoffman sees inefficiencies in this schedule and proposes a level production plan that would eliminate overtime wages and fully utilize skilled workers. Under his plan, toys would be manufactured evenly every month, allowing inventory levels to build in the months leading up to the holidays. In addition to using cash, the company must also take on additional loans to compensate for the high inventory levels. In an industry that has relatively low capital requirements, Hoffman’s strategy may increase overall profitability, but it jeopardizes the company’s liquidity.…

    • 1352 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    a. This plan conforms to the regulations of the general frame of the program in…

    • 1335 Words
    • 12 Pages
    Satisfactory Essays
  • Good Essays

    Technological convergence is the tendency for different technological systems to evolve towards performing similar tasks. Convergence can refer to previously separate technologies such as voice (telephony features), data (productivity applications) and video that now share resources and interact with each other, synergistically creating new efficiencies. Convergence in this instance is defined as the interlinking of computing and other information technologies, media content and communication networks that have arisen as the result of the evolution and popularization of the Internet as well as the activities, products and services that have emerged in the digital media space. Many experts view this as simply being the tip of the iceberg, as all facets of institutional activity and social life such as business, government, art, journalism, health and education are increasingly being carried out in these digital media spaces across a growing network of ICT devices. Also included in this topic is the basis of computer networks, wherein many different operating systems are able to communicate via different protocols. This could be a prelude to artificial intelligence networks on the internet and eventually leading to a powerful super intelligence via a Technological singularity. Technological Convergence can also refer to the phenomena of a group of technologies developed for one use being utilized in many different…

    • 3820 Words
    • 16 Pages
    Good Essays
  • Powerful Essays

    Engineering Management

    • 2638 Words
    • 9 Pages

    Lessard, C. & Lessard, J. (2007). Project Management for engineering design. The United States: Morgan & Claypool Publishers.…

    • 2638 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Aggregate Planning

    • 897 Words
    • 4 Pages

    Aggregate planning is the process of developing, analyzing, and maintaining a preliminary, approximate schedule of the overall operations of an organization. The aggregate plan generally contains targeted sales forecasts, production levels, inventory levels, and customer backlogs. This schedule is intended to satisfy the demand forecast at a minimum cost. Properly done, aggregate planning should minimize the effects of shortsighted, day-to-day scheduling, in which small amounts of material may be ordered one week, with an accompanying layoff of workers, followed by ordering larger amounts and rehiring workers the next week. This longer-term perspective on resource use can help minimize short-term requirements changes with a resulting cost savings.…

    • 897 Words
    • 4 Pages
    Good Essays