Preview

Critical Path Method

Good Essays
Open Document
Open Document
894 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Critical Path Method
CPM - Critical Path Method

In 1957, DuPont developed a project management method designed to address the challenge of shutting down chemical plants for maintenance and then restarting the plants once the maintenance had been completed. Given the complexity of the process, they developed the Critical Path Method (CPM) for managing such projects.

CPM provides the following benefits:

Provides a graphical view of the project.

Predicts the time required to complete the project.

Shows which activities are critical to maintaining the schedule and which are not.

CPM models the activities and events of a project as a network. Activities are depicted as nodes on the network and events that signify the beginning or ending of activities are depicted as arcs or lines between the nodes. The following is an example of a CPM network diagram:

CPM Diagram

[pic]

Steps in CPM Project Planning

Specify the individual activities.

Determine the sequence of those activities.

Draw a network diagram.

Estimate the completion time for each activity.

Identify the critical path (longest path through the network)

Update the CPM diagram as the project progresses.

1. Specify the Individual Activities

From the work breakdown structure, a listing can be made of all the activities in the project. This listing can be used as the basis for adding sequence and duration information in later steps.

2. Determine the Sequence of the Activities

Some activities are dependent on the completion of others. A listing of the immediate predecessors of each activity is useful for constructing the CPM network diagram.

3. Draw the Network Diagram

Once the activities and their sequencing have been defined, the CPM diagram can be drawn. CPM originally was developed as an activity on node (AON) network, but some project planners prefer to specify the activities on the arcs.

4.Estimate Activity Times

Weeks are a commonly used unit of time for activity

You May Also Find These Documents Helpful

  • Satisfactory Essays

    The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 5 Days --- B 8 Days --- C 6 Days A D 4 Days C, B E 5 Days A F 4 Days D, E, G G 4 Days B, C H 3 Day G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Best Essays

    One of the most convenient and practical ways to represent a project in form of a diagram is using Project Network Diagram (PND). Heldman (2011) defines PND as a graphical view of a certain project, showing its activities (dependent and independent) along with their timing and the sequence they will be performed.…

    • 3462 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project?…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Redraw the following charts after Inserting activity N (duration 5) in them. Assume in each case it (N) must precede all activities whose initial letter is >= F (but succeed all others). Recalculate the chart and identify the CP…

    • 963 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    TPV1 Sample Questions

    • 453 Words
    • 3 Pages

    Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies?…

    • 453 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Phase 4 DB

    • 379 Words
    • 1 Page

    Critical Path Method (CPM) is yet another tool for the project manager to use to organize, plan, and control the development of a project. It calculates the longest path to get to the end of a project and tells which activities are critical. It ca be used for projects of any size and illustrates the dependencies between scheduled activities. However, it does not tell you anything about the resources or where they fit into the project.…

    • 379 Words
    • 1 Page
    Satisfactory Essays
  • Powerful Essays

    One way to consider resources is to take them into account when drawing the logical relationships among activities in the network diagram. In addition to showing the technical constraints among activities, the network logic can also take into account resource constraints. The sequence of activities can be drawn to reflect the limited availability of a number of resources. If resources are to be considered in planning, it’s necessary to indicate the amounts and types of resources needed to perform each activity. For this reason, a resource profile is often developed.…

    • 2049 Words
    • 9 Pages
    Powerful Essays
  • Better Essays

    After the project has been planned it is time to begin executing the project lifecycle. At this point, the project manager integrates two groups of project management processes. Some of these processes are classified as “executing” and some are classified as “monitor and control”. This plan focuses on the “executing” project management processes. It has seven main steps.…

    • 1106 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Read Me First

    • 1484 Words
    • 6 Pages

    This course’s material methodically moves through the PLC. You learn more about what a project is, what the elements of a project are, and how terms like software development life cycle (SDLC) fit into project management.…

    • 1484 Words
    • 6 Pages
    Satisfactory Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    1. The activities involved for the project schedule can be represented using Central Path Method (shown below) showing various interdependence and parallelism among activities.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    Pert Mustang

    • 2682 Words
    • 11 Pages

    3. Most everyone should be able to describe some project they have been a part of. Common ones include preparing a high-school yearbook, planning a major party, building a new home, and organizing a banquet for a club or student group. Take time to elicit examples of activities and their interrelatedness. Press the students for the reasons behind their rating of the project manager. If the student is the project manager, ask the student what s/he thinks are positive attributes for a project manager in such an example. Problem 1 (page 79): Given: Activity precedence relationship and activity times To do: a. draw the network diagram b. Calculate the critical path for this project c. How much slack is in activities G, H, and I? Solution: a. AON network diagram…

    • 2682 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    D.U Singer Hospital

    • 5200 Words
    • 21 Pages

    Question 1: Construct the nine elements of the plan identified................................................. 4 i. ii. iii. iv. v. Statement of Objectives.................................................................................................. 4 Work Breakdown Structure............................................................................................. 5 An activity on node (PERT) network ........................................................................... 6 A determination of the critical path(s) and the duration along the path. ..................... 7 An activity list, early-start schedule, slack list and master schedule. Assume every…

    • 5200 Words
    • 21 Pages
    Good Essays
  • Good Essays

    The development activities would begin with the planning and requirements phase where all of the application flow, modules and calculations would be defined in detail along with some psudo-code to clarify all of…

    • 613 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Planning & Scheduling

    • 2577 Words
    • 11 Pages

    Keywords: Planning, Scheduling, Activity Network Diagram, Gantt Charts, Cycle Time, Critical Path Method (CPM), Program Evaluation and Review Technique (PERT)…

    • 2577 Words
    • 11 Pages
    Powerful Essays