Preview

Course Project - Huntsville Plant Project Sample Only

Good Essays
Open Document
Open Document
708 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Course Project - Huntsville Plant Project Sample Only
Huntsville Plant Project Activities Schedule Analysis
With the current estimates for activity durations and dependencies of some activities on others, the earliest that the Huntsville Project can be finished is July 7, 2012 – 1 week late of the desired schedule. However, it should not be a big problem to fit these activities in the desired schedule as 1 week delay is relatively small compared to the total project duration of 66 weeks. The following activities are on the critical path (Gido, Celements, 2012, pg. 156) of the project, determining the 66 week minimum time that the project needs according to the current schedule:
Select Architect, Create Pre-Prod Plan  Establish Bldg Concept  Create Bldg Design  Procure Site  Obtain Permits & Approvals  Construct Bldg  Install Equipment  Perform Pre-Prod Plan  Perform Prod Start-up  Begin Distribution
Not just that these activities cannot be delayed any further, their total time need to be reduced by at least 1 week so that the project can be finished on time. Following are a few techniques that can be used to cover this 1 week gap:
1. Include weekends for some activities:
Current schedule comprises of activities to be performed only on the weekdays. If just 3 weekends are included in any one of the above activities, the total time can be easily reduced by 6 days which will be enough to meet the desired deadline. This will cost the same because 1 week’s work scheduled to be completed after the deadline will be performed before the deadline. It’s the same payment for same work, just the work will be performed at an earlier than scheduled time.
2. Reduce an activity’s duration:
It might be possible to optimize the sub-tasks in an activity to reduce its estimated length. For example, “Construct Bldg” is scheduled to be 40 weeks and the contractor might be able to reduce this to 39 weeks maybe at an additional cost as constructions company meet tight deadlines all the times. Another option here will be to



References: Gido, Jack. Clements, James. (2012). Successful Project Management [5] (VitalSource Bookshelf), Retrieved May 26, 2013, from http://online.vitalsource.com/books/

You May Also Find These Documents Helpful

  • Powerful Essays

    MGT2 Task3

    • 5037 Words
    • 21 Pages

    Increase the project team size to catch up and speed up progress reducing potential for any further schedule…

    • 5037 Words
    • 21 Pages
    Powerful Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    References: Gido, Clements. Successful Project Management, 5th ed., 5th Edition. South Western Educational Publishing, 02/2011. <vbk:9781133614487>.…

    • 715 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    There are times when it will be necessary to expedite a project’s schedule. The term we use is to “crash” the project schedule.…

    • 2212 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    The reasons that we propose this are because that this is the method that will save the company the most time. Not only does it save the company time, but if the company were to ever fall into trouble with labor union strikes, this plan is guaranteed to be the most cost effective when facing with the steep penalties of not meeting the time limit. In addition if everything goes very smoothly the company will finish the project 8 weeks earlier than expected and save money on overhead expenses.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    We can expedite the project by reducing the amount of time we have slated for some of our larger tasks. By recalculating and essentially shortening the schedule we can decrease our project by 10%. “A change in the estimated duration of any activity on that path will cause a corresponding change in the slack for that path.” (Gido and Clements 167). Currently we have several tasks that we can reduce time:…

    • 758 Words
    • 4 Pages
    Good Essays
  • Good Essays

    To plan work to meet agreed deadlines you should first priotise what is more important and less import and set aside more time fore the more important work.…

    • 805 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Powerful Essays

    After reviewing the WBS and chart Gantt created for Tasks 3 and 4 in part 2, I propose the additional activities below that be added to help me estimate resources and durations.…

    • 667 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Zuma Project

    • 1253 Words
    • 6 Pages

    If the project is resource constrained, then the finish date will be 2/18/09, since there was an additional 40 days added to the project duration. Additional personnel should be added in order to meet the desired new deadline.…

    • 1253 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Woody's Project Outline

    • 600 Words
    • 3 Pages

    Installation of semi-automatic woodworking production train-research how to employ Industry Foundation classes (IFC) (Boukamp, Akinci 2007);…

    • 600 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Discussion 2 Gantt Chart

    • 472 Words
    • 2 Pages

    A Gantt chart, commonly used in project management, is one of the most popular and useful ways of showing activities (tasks or events) displayed against time. On the left of the chart is a list of the activities and along the top is a suitable time scale. Each activity is represented by a bar; the position and length of the bar reflects the start date, duration and end date of the activity. This allows us to see at a glance:…

    • 472 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Construction and installation will be sub-contracted to local construction companies according to installation and commissioning specifications from the engineering consulting firm with approval of project team.…

    • 480 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is your opinion on the potential for the project to be completed on time?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    The additional resources for speeding up a critical activity could come from the non-critical ones. To use the house-building example, if F is to be reduced to eight days to counter the delay, the resources of labour, materials and machinery could be taken, as they both have spare time. This will allow a better and more efficient use of the firm’s resources. This shows how the existence of float times and it allows…

    • 475 Words
    • 2 Pages
    Good Essays