Preview

Woody's Project Outline

Good Essays
Open Document
Open Document
600 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Woody's Project Outline
1. Statement of Work (Wysocki, 2012, pg11)
• Obtain required documentation;
• Installation of air conditioning for facility;
• Dust free paint and finishing shop installation;
• Additional compressor capacity installation;
• Installation of semi-automatic woodworking production train-research how to employ Industry Foundation classes (IFC) (Boukamp, Akinci 2007);
• Mandatory regulatory inspections.
• Resource allocation
• Project duration 18 months
• Production capacity area enlarged by the equivalent of 25% of existing production capacity;

2. Joint Project Planning Session (Wysocki 2012 pg 157-163), McGowan et al (1993)
• Create WBS including Activity List
• Subject matter experts develop further decomposition.(Laufer et al 1992)
• Estimate task duration and resource needs.
• Construct project network diagram
• a. Proposed methodology- three point technique
• b. Critical Path and Milestones
• c. Overall Project Schedule
• Revision and approval of completion date
• Finalization of resource schedule
3. GANTT CHART
4. WORK BREAKDOWN STRUCTURE
5. RISK IDENTIFICATION & MITIGATION
• Risks - Weather conditions – not being familiar with weather in British Columbia we will assume that it will be winter time which will have an effect on project execution and schedule.
• Schedule has minimal flexibility. Project execution, delivery of resources and equipment as well as regulatory inspections, need to be monitored.
• Obtaining mandatory licenses and permits in a timely manner
(b)Mitigation of the risks
• Weather –advisable to require contractors to protect the work site
• Schedule – effective monitoring and control of tasks especially critical path tasks. If tasks are at risk of falling behind, extra manpower will be provided.
• Mandatory licenses and permits – Scope and Planning processes allow for slack to obtain licenses and permits. RISK MONITORING AND CONTROL
• Upon identification,



References: Bass, B.M. & Leavitt, H.J. 1963, "Some Experiments in Planning and Operating", Management Science, vol. 9, no. 4, pp. 574-585. Boukamp, F Dawood, N. & Sriprasert, E. 2006, "Construction scheduling using multi‐constraint and genetic algorithms approach", Construction Management & Economics, vol. 24, no. 1, pp. 19-30. Laufer, A McGowan, P.H. Randall, C.W & Homer, R.M. W. (1993): Resource significant models for estimating, planning and control in construction. CIB W78 Workshop, 13, August, National University of Singapore Rahmat, I Rezakhani, P. 2012, "Classifying Key Risk Factors in Construction Projects", Bulletin of the Polytechnic Institute of Iasi - Construction & Architecture Section, vol. 62, no. 2, pp. 27-38. Wideman, M Wysocki R. K (2012) Effective Project Management: Traditional, Agile, Extreme 6th Ed. Indianapolis, Wiley Publishing. City of Pit Meadows (2007), Website, Available at: http://www.pittmeadows.bc.ca/EN/main/business/1156/1187/1283.html, (Accessed: 22 April 2011) City of Vancouver (2011), Website, Available at: http://vancouver.ca/business.htm, (Accessed: 22 April 2011)

You May Also Find These Documents Helpful

  • Powerful Essays

    Pm595 Course Project

    • 2651 Words
    • 11 Pages

    Cited: Sources of risks in construction projects may be classified as follows (PM Book, 2012):…

    • 2651 Words
    • 11 Pages
    Powerful Essays
  • Better Essays

    Mgmt404 Project Plan

    • 1494 Words
    • 6 Pages

    I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen…

    • 1494 Words
    • 6 Pages
    Better Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    Risk Identification I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen as key risks are bolded below and appear in the Risk Assessment Table.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Introduction to Project Scheduling IX. The Critical Path Method (CPM) X. Program Evaluation and Review Technique (PERT) XI. Project “Crashing”…

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Not just that these activities cannot be delayed any further, their total time need to be reduced by at least 1 week so that the project can be finished on time. Following are a few techniques that can be used to cover this 1 week gap:…

    • 708 Words
    • 3 Pages
    Good Essays
  • Good Essays

    This project plans to develop a methodology to estimate future projects’ costs and their appropriate contingency reserves for changing prices in constructional projects. Based on the methodology, recommendations will be given in order to change Ministry of Construction’s policies that relates to project budgets, and how to deal with the current policies if they are not changed.…

    • 311 Words
    • 2 Pages
    Good Essays
  • Better Essays

    Citations: Heldman, Kim (2005). Project Manager’s Spotlight on Risk Management. San Francisco, CA: Jossey-Bass: Wiley…

    • 2381 Words
    • 9 Pages
    Better Essays
  • Good Essays

    Risk Matrix Pm586

    • 1234 Words
    • 5 Pages

    With the Huntsville, Alabama plant I identified a few areas that may be an issue. The first one was rain. With any construction project rain will be an issue. For some areas rain is a major issue but I felt as though 35% was a pretty good estimate. Not too high or low. This is why it is important for the project manager to monitor the weather forecast days in advance. If a torrential down pore is expected an action plan needs to be in place.…

    • 1234 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    HKH DFC USM Paper JCEM 2013

    • 9802 Words
    • 51 Pages

    Abstract: A model for project budgeting and scheduling with uncertainty is developed. The traditional critical-path method (CPM) misleads…

    • 9802 Words
    • 51 Pages
    Powerful Essays
  • Good Essays

    Week 7 Discussion

    • 960 Words
    • 4 Pages

    Wysocki,R.K .(2012) Effective Project Management: traditional, agile, extreme. 6th edn. Indianapolis: Wiley Publishing, Pp. 311-320…

    • 960 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    1. Patrick, Charles (2004). Construction Project Planning and Scheduling. Upper Saddle River, New Jersey: Pearson Prentice Hall. (ISBN-10: 0130924806)…

    • 1051 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    Shtub, Bard and Globerson (2005, 457) identify that resources scheduling is the process by which the project manager decides which resources to obtain, from which sources, when to obtain them, how to use them and when and how to release them. Given the finite nature of resource availability, a project plan may have to be modified so that it is practical. This is the major thrust of resource planning and management.…

    • 536 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Project Management

    • 3681 Words
    • 15 Pages

    Project constraints delay the start of project activities. Three project constraint need to be considered in scheduling.…

    • 3681 Words
    • 15 Pages
    Good Essays
  • Good Essays

    References: Robert K Wysocki (2012) Effective Project Management, Traditional, Agile, Extreme, 5th ed. Indianapolis: Wiley Inc…

    • 956 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Critical Path Analysis

    • 2901 Words
    • 12 Pages

    Specific plans and projects. Scheduling is concerned about the implementation of activities necessary to achieve the laid down plans. The function of control is to institute a mechanism that can trigger a warning signal if actual performance is deviating (in terms of time, cost and some other measures of effectiveness) from the plan. If such a deviation is unacceptable to the concerned manager, he will be required to take corrective action to bring performance in conformity with the plans. The PERT and CPM models are extremely useful for the purpose of planning, scheduling and controlling the progress and completion of large and complex projects or for carrying out the analysis of these three managerial functions. Before we describe the basic concepts used in the construction and analysis of these models, let us first understand the meaning of a project.…

    • 2901 Words
    • 12 Pages
    Powerful Essays

Related Topics