Preview

Law- Case Study

Good Essays
Open Document
Open Document
321 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Law- Case Study
Arbitration means “a neutral third party or panel of experts hears a dispute and imposes a resolution of the parties” (Miller & Jentz, 2008, p.50). However, both parties must sign and agree to the above statement for it to be acknowledged as a legal judgment. In the case of Thomas Baker and Osborne Development Corporation it gets a little bit more involved. For starters, Osborne Development purchased the home warranty program administered by Home Buyers Warranty and signed the agreement of arbitration with them. However, the agreement of submitting disputes to arbitration also involved home owner and not just the builder, warranty issuers and HBW. Consequently, I don’t think the homeowners should abide by the arbitration process since they never signed the agreement papers. Thus, Thomas Baker and others could possible take the case to court because there is an issue of arbitrability, “a dispute arises as to whether the parties have agreed in an arbitration clause to submit a particular matter to arbitration” (Miller & Jentz, 2008, p.51). Unfortunately, if the homeowners did sign an agreement to abide with settling disputes by the process of arbitration then they may not take this to court. More specifically, Thomas Baker and others may not sue the builder in court but they could still dispute the scope of arbitrable issues stating they do not involve defects within the house. Now a similar case of disputing the scope of arbitrable issues was NCR Corp v Korala Associates, Ltd. NCR took the judgment of arbitration to the court but “because the arbitration clause in the 1998 Agreement was so broad, the appellate court reasoned that a trial court should follow the presumptions of arbitration and resolve doubts in favor of arbitration” (Miller & Jentz, 2008, p.51). So the same principle applies here, if the homeowner signed the arbitration agreement without defining the scope then they must abide by the arbitration

You May Also Find These Documents Helpful

  • Good Essays

    In this scenario the arbitration had been implemented mandatorily. The keywords in the contract that binds the customers to this contract of arbitration are the following : “ By signing below, you acknowledge that you consent to the terms of these documents including the binding arbitration provision contained therein (assignment2)”. Binding arbitration eliminates the right to appeal decisions made by the arbitrator. By signing the document all parties forfeit the power to go to any other court system to resolve the dispute. Courts will agree with the arbitration decision because of the fact the contact was valid.…

    • 527 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Case Outlines

    • 1034 Words
    • 5 Pages

    The court ultimately ruled with the defendant. The main reason was the language of the contract. The terms and conditions were too specific and definite to rule any other way but in the favor of Billy Cannon, as the absence of the Commissioner’s contract was…

    • 1034 Words
    • 5 Pages
    Good Essays
  • Good Essays

    On August 16, 2001, Mrs. Rebar paid for the renewal of the contract and submitted an "Addendum to Customer Agreement". The agreement changed the terms of the contract, including a statement that "Arbitration shall not be required for any prior or future dealings between Cook's and Customer." The addendum also stated that "Continued honoring of this account by [Cook's Pest Control] acknowledges agreement to [the] terms."Procedural HistoryOn August 30, 2001, the Rebar filed action against Cook's Pest Control alleging fraud, negligence, breach of contract, breach of warranty, breach of duty to warn, unjust enrichment, breach of duty, negligent training, supervision and retention of employees, and bad-faith failure to pay and bad-faith failure to investigate a claim. Cook's moved to compel arbitration based upon the arbitration provision contained in the agreement. The Rebars opposed the motion to compel arbitration. On December 18, 2001, the trial court denied Cook's motion to compel arbitration. Cook's Pest Control appealed.…

    • 413 Words
    • 2 Pages
    Good Essays
  • Better Essays

    Arbitration is a relatively fast way to arrive upon a decision when two parties are in a dispute. Arbitration has definite benefits such as being flexible and not as formal as a traditional courthouse. Usually, arbitration can be scheduled quicker and with less working parts than a trial. In rare instances, if all parties involved come to an agreement, arbitrators can sometimes create rulings that judges are not allowed to decide. In arbitration, both sides present all evidence to an arbitrator in efforts to prove each side’s case. The arbitrator reaches a final verdict and decides whom the winners and losers are. An arbitrator does the job that a traditional judge or jury would normally do in court if the matter escalated to that point (Hill…

    • 997 Words
    • 4 Pages
    Better Essays
  • Good Essays

    Contract Scenario

    • 998 Words
    • 4 Pages

    Recently, Danny Davidson sold a family home to his friends Paul and Priscilla Peterson whereby entering into a $250,000 verbal agreement for the purchase of new home. However, Danny neglected to tell Paul and Priscilla about Ned the neighbor and the emerging dispute pertaining to the boundaries of the south property. Once the purchase was final the Petersons proceeded to invest an estimate of $65,000 for landscaping as well as implementing a new Italian bathtub in the bathroom. As the Peterson’s proceed to upgrade their new home cracks developed in the new tile whereby causing the bathroom floor to sink because of a landscaping issue with the soil on the property. Subsequently, a breach of contract emerged whereby causing the Peterson’s to file a suit against their friend.…

    • 998 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Laurel Creek requested that the trial court hold the matter in abeyance and order the parties to proceed to arbitration in accordance with the mandatory arbitration provision contained in the admissions paperwork signed by Gilbert’s wife. Laurel Creek renewed its motion under KRS 17.050, et seq., to hold the matter in abeyance and compel arbitration. The trial court denied the motion on the ground that Anna was not Bishop’s agent and had no legal authority to make decisions for him. Laurel Creek now appeals, arguing that the trial court’s last finding of fact is not supported by substantial evidence and is incorrect as a matter of law.…

    • 882 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    The Federal Arbitration Act states that arbitration arrangements or agreements concerning commerce are valid, applicable, irrevocable, irreversible and enforceable contracts, unless some grounds are present at law or equity (e.g., fraud, duress) to revoke them. (Cheeseman, 2013, p. 74) This means that arbitration contacts are legally binding as long as they are fair and nobody was physically forced to sign it. The FFA authorizes one party to acquire a court order to coerce arbitration if the other party has failed or declined to act in accordance with an arbitration agreement. (Cheeseman, 2013, p. 74) Basically, Capital had every right to file for a motion to compel or force the consumers to abide by the arbitration agreement. The court would have to decide whether there is fraud present in the case or if one of the parties were under duress at the time the agreement was signed. The court would also have to ensure the fairness of the arbitration agreement to ensure it was not one sided. If none of those elements were present then there would not be a case against voiding the arbitration agreement and both parties would be sent to an arbitrator to settle their disputes. This would mean that the consumer would not be allowed to proceed with their lawsuit in state court.…

    • 401 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Knzales And Barkley Case

    • 2126 Words
    • 9 Pages

    As previously mentioned the contract was negotiated with an underage minor, who we are not sure if he had contractual powers while his father was away, could be one way to legally dissolve the contract. Chetum may claim that he was duped into believing the contract was valid since the external appearance of Barkley led him to believe that Barkley was a legitimate agent for the firm. Second, the fact that Chetum, K & B, and the plumber are all negligent of carbon monoxide poisoning and that K & B wants to distance themselves from Chetum, might be a reason for breaking the contract, it should be noted that parties to an illegal contract (keeping the flow of carbon monoxide going in the apartment complex) are responsible for their actions and their actions during the contract may have no standing in court. Not having complete knowledge of Virginia’s public policy on carbon monoxide exposure in apartment complexes, a breach of ethics is a concern. K & B’s actions, with the boiler repair/carbon monoxide poisoning, will no doubt hurt their fine reputation in the region for providing building maintenance that Knarles’ worked years to…

    • 2126 Words
    • 9 Pages
    Better Essays
  • Satisfactory Essays

    should your immediate superior not be able to satisfactorily resolve the grievance, the matter should be referred either verablly or in writing to the home owner whose decision will be final…

    • 596 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    should your immediate superior not be able to satisfactorily resolve the grievance, the matter should be referred either verablly or in writing to the home owner whose decision will be final…

    • 1488 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    should your immediate superior not be able to satisfactorily resolve the grievance, the matter should be referred either verablly or in writing to the home owner whose decision will be final…

    • 431 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    If the tribunal took the view that they were in fact two separate houses then only one house can be disregarded and the respondents…

    • 1088 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    It is undeniable that the Sale and Purchase Agreement is between the developer and the purchaser. The loan to finance the house is between purchaser and financier. There was no direct connection between both developer and financier, but at the end of the day, failure in delivering the house to purchaser resulting burden to the purchaser in the sense of paying back the mortgage to the financier.…

    • 2547 Words
    • 11 Pages
    Powerful Essays
  • Powerful Essays

    Law of Case Studies

    • 1521 Words
    • 7 Pages

    1) Review the motivation theories discussed in this chapter. How would each one describe and explain the problems with Simon Lucas’s motivation?…

    • 1521 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    2, 3, 23 NOVEMBER 1989 Contract - Consideration - Performance of contractual duty - Performance of existing contractual duty - Agreement to pay additional money to ensure performance of existing contractual duty - Whether sufficient consideration for payment of additional sum - Whether promise by plaintiff to fulfil existing contractual duty good consideration - Whether defendant obtaining benefit from payment of additional sum - Whether obtaining of benefit amounting to consideration for payment of additional sum - Whether agreement to pay additional sum enforceable. The defendant building contractors entered into a contract to refurbish a block of 27 flats and sub-contracted the carpentry work in the refurbishment to the plaintiff carpenter for a price of £20,000. It was an implied term of the sub-contract that the plaintiff would receive interim payments related to work completed. After completing the carpentry work on the roof and nine flats, and carrying out preliminary work on the remaining flats, for which work he received interim payments of £16,200, the plaintiff found that he was in financial difficulties because the price was too low and he had failed to supervise his workmen properly. Furthermore, he had by then received over 80% of the sub-contract price but still had far more than 20% of the work to complete. The defendants, who were liable under a penalty clause in the main contract if it was not completed on time, were aware of the plaintiff's difficulties and that the sub-contract had been underpriced. They called a meeting with the plaintiff at which they agreed to pay the plaintiff an extra £10,300 at the rate of £575 per flat on completion to ensure that the plaintiff continued with…

    • 11550 Words
    • 47 Pages
    Satisfactory Essays