Preview

Hardware Replacement Project Case Study

Good Essays
Open Document
Open Document
1112 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Hardware Replacement Project Case Study
Hardware Replacement Project Steve Smithers

How do the five major variables of project management—scope, time, cost, quality, and risk—relate to this scenario?
Time – This would be the amount of time required to complete the project. Typically it is broken down into the time required to complete the components of the project. This is then broken down into the time required to complete each task contributing to the completion of the project
Cost - Cost will typically be determined by the consultant or contractors hourly rate multiplied by an estimated time to complete the project on time or if it is late.
Quality - The amount of time put into individual tasks determines the overall quality of the project. Some tasks may require
…show more content…
Most risks or potential failures can be overcome or resolved, given enough time and resources.
Three of these variables can be given by external or internal customers. The value(s) of the remaining variable are then set by project management, ideally based on solid estimation techniques. The final values have to be agreed upon in a negotiation process between project management and the customer. Usually, the values in terms of time, cost, quality and scope are contracted.
To keep control over the project from the beginning of the project all the way to its natural conclusion, a project manager uses a number of techniques: project planning, earned value, risk management, scheduling and process improvement.
What considerations must be applied when selecting projects that deliver the best business
…show more content…
As a manager it is there responsibility to do the best to minimize the risk in projects, but to minimize it as soon as possible. Some of the factors would be project size, project structure, and the level of technical expertise of the information systems staff and project team. The first step in managing the risk of a project is to review the situation. By identifying all of the risks that you think are possible in the project. The review should include factors for the project such as resource changes, failures, and sponsor availability. All of the external factors such as a change in company direction or a change of technology direction. Most of all it should include the things that are new in the project. If the project is working with a new technology, new development methodology, or even if there are new team members, these need to be listed as potential risks to the project. The purpose of the review phase isn't to classify the risk or identify its importance. The goal is to collect all the risks. Once there is a complete list of potential risks, it’s time to evaluate them. Each risk should be evaluated based both on its probability and the impact that it would cause if it happens. The loss of a key team member may not have any affect. However, the impact to the project could be great if the team member plays a key role in the project. The other factor to evaluate when looking at a risk is its

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points)…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    How do the five major variables of project management-scope, time, cost, quality, and risk – relate to this scenario?…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Date constraints –> Date constraints establishes time milestones or benchmarks on a project that the entire construction team works toward…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    Unit 6 Assignment 2

    • 878 Words
    • 4 Pages

    Without going into details regarding the theory of project risk management we present still, the definition of this concept as it is proposed by the Project Management Institute professionals who, in The Project Management Body of Knowledge Guide, [Duncan, W., R.,…

    • 878 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    It221 Final Project

    • 2390 Words
    • 10 Pages

    Currently Cyber Solutions has satellite locations in 15 major cities around the United States that provide onsite IT solutions for companies within their service area, but do not have an integrated database that updates…

    • 2390 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Case 3 Risk Management

    • 1053 Words
    • 5 Pages

    The main factor for not completing the project is team failure which is because of poor overall initial planning. When there are unrealistic goals being set, creating a chaotic working environment there is bound to be nothing but pure failure of the project and its successin the near future. There can be two major causes for the team project failures; overdue or missed time standards, and going beyond set financial plans. With the interpretation of day to day basis risk assessments into team developed projects, there is a more realistic set of guidelines, and procedures put into place. The definition of a risk assessment states , “ that it is theidentification, evaluation, and estimation of the main levels of risks involved in a situation, their comparison against benchmarks or standards, and determination of an acceptable level of risk”. With set risk assessment techniques, the team may further eradicate all possible liabilities or future occurrences within the project team.…

    • 1053 Words
    • 5 Pages
    Good Essays
  • Better Essays

    Lessons of Valujet 592

    • 1044 Words
    • 5 Pages

    Identify one or two risks your project is encountering and strategies that might mitigate them…

    • 1044 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    Educare Ltd Project Report

    • 3316 Words
    • 14 Pages

    The Project Duration is the time taken to complete the whole project. In this project, it will be 40 days. This is done by adding the number of days from Activity A to R. When there are multiple activities, the latest time is taken.…

    • 3316 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    1. Patrick, Charles (2004). Construction Project Planning and Scheduling. Upper Saddle River, New Jersey: Pearson Prentice Hall. (ISBN-10: 0130924806)…

    • 1051 Words
    • 5 Pages
    Satisfactory Essays
  • Better Essays

    In order to revamp the complete CRM it will encompass all five variables. These variables are scope, time, cost, quality, and risk. As the project manager I will need to review each area and develop a sound plan taking in consideration any issues that may arise. The purpose of revamping the CRM is to improve the relationship with customers. This will need to be done by replace all hardware that is out-of-date, installing the correct software to have programs to track the customer’s wants and needs and create a user-friendly webpage for the company.…

    • 1548 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    Implementation Plan

    • 3502 Words
    • 15 Pages

    The three basic steps to select the best project management include: ensuring the basic project essentials are in place and mesh well with other projects and how the company executes the projects, examine, evaluate, and add appropriate advance project engineering and business related offerings, and interview those persons about to be hired, (Nita, 2007).…

    • 3502 Words
    • 15 Pages
    Powerful Essays
  • Better Essays

    These costs are on account with a specific work package. Direct costs are attributed to efforts made by the project manager, project team, and folks executing the work package. These costs signify actual outflow and are compensated as the project evolves. Examples of direct costs are labor, equipment, materials, and other (Gray & Larson, 2005).…

    • 1970 Words
    • 8 Pages
    Better Essays
  • Powerful Essays

    cost drivers, and typically may be physical, performance, or operational characteristics associated with the project to…

    • 3309 Words
    • 18 Pages
    Powerful Essays
  • Powerful Essays

    Project Charter

    • 3052 Words
    • 13 Pages

    The project charter defines the scope, objectives, deliverables and overall approach of the work to be completed. The scope of this document covers the critical element for initiating, planning, executing, controlling and monitoring the project. This document will serve as an agreement between the following parties: Project Sponsor, Project Manager, Project Team, and other personnel associated with and/or affected by the project, stating at a minimum:…

    • 3052 Words
    • 13 Pages
    Powerful Essays
  • Satisfactory Essays

    Sasasasasasasas

    • 344 Words
    • 2 Pages

    QUANTITY OF WORK – The amount of acceptable work accomplished and the ability to complete work within the time scheduled.…

    • 344 Words
    • 2 Pages
    Satisfactory Essays

Related Topics