Preview

conveyer belt project parts 1 and 2

Powerful Essays
Open Document
Open Document
851 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
conveyer belt project parts 1 and 2
1.0 Conveyer Belt Project
1.1 Hardware
1.1.1 Hardware Specifications
1.1.2 Hardware Design
1.1.3 Hardware Documentation
1.1.4 Prototypes
1.1.5 Order Circuit Boards
1.1.6 Assemble Preproduction Models
1.2 Operating System
1.2.1 Kernel Specifications
1.2.2 Drivers
1.2.2.1 Disk Drivers
1.2.2.2 Serial I/O Drivers
1.2.3 Memory Management
1.2.4 Operating System Documentation
1.2.5 Network Interface
1.3 Utilities
1.3.1 Utilities Specifications
1.3.2 Routine Utilities
1.3.3 Complex Utilities
1.3.4 Utilities Documentation
1.3.5 Shell
1.4 System Integration
1.4.1 Architectural Decisions
1.4.2 Integration First Phase
1.4.3 System Hardware/Software Test
1.4.4 Project Documentation
1.4.5 Integration Acceptance Testing
The work breakdown structure essentially is a decomposition of the work to be completed by the project team in order to successfully accomplish the project objectives and deliverables. It’s a very practical tool to visualise the work that needs to be done, however that is about all it’s useful for. The information provided by the work breakdown structure is not enough to allow the project team to identify any milestones or points of significance in the project. At this stage each element of the project has only been identified, none of them have been time scheduled, cost estimated or placed in a definitive chronological order, making it difficult to identify any significant milestones.
Network scheduling refers to the graphical representation of activities that define the sequence of work in a project. It is an important tool used to visualise the chronological order of activities needed to be completed in order to meet the project deliverables and objectives. The project team decided to use Microsoft project to develop the network schedule for the conveyer belt project. However before a network schedule could be produced it was necessary to enter some important information into Microsoft project. Firstly the work calendar had to be

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    Create a project schedule using Microsoft Project. Project schedule will built from and contain the following information:…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    For this purpose the company has hired our services in order to manage the whole project. This project is to be split into two major parts; first, the construction of a new premises and second, the transfer of resources from old to new premises. The project manager therefore, needs to plan the whole project first with taking all areas of the project into consideration so that nothing is left behind one of the most reliable and suggested to do this is through using the Work Breakdown Structure (WBS). This will allow the manager to have a wide-ranging grip into all concerned areas of the project, by breaking the project into smaller tasks and assigning these tasks to individuals who are considered most suitable for them. This will enhance the level of specialisation and expertise implied into the project by planning all the phases of the project with specialised human as well as capital…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Good Essays

    Huntsville Plant

    • 654 Words
    • 3 Pages

    A Work Breakdown Structure can be the key to assurance that the employees will know what task that they are responsible for completing.…

    • 654 Words
    • 3 Pages
    Good Essays
  • Best Essays

    1. Nowadays, majority of projects, irrespectively of their scope or nature, can be outlined by various charts and diagrams. Such kind of representation of a project gives a clear picture of the project’s activities along with their start and finish dates and the sequence they are performed. This also aims to provide smooth coordination and implementation of the project, which is very crucial to the management.…

    • 3462 Words
    • 14 Pages
    Best Essays
  • Powerful Essays

    Nt1310 Unit 9 Lab Report

    • 2537 Words
    • 11 Pages

    International Journal of Computer Science and Network (IJCSN) Volume 1, Issue 3, June 2012 www.ijcsn.org ISSN 2277-5420 On Line Real Time Health Monitoring of ICU Patients using ARM7 1 1 Mrs. Rajashri Patil , 2Prof. Balaji Hogade Electronics Department, Datta Meghe College Of Engg , Airoli , Navi Mumbai , Maharashtra 400708, India 2 Department of Electronics, Terna Engg College, Nerul, Navi Mumbai , Maharashtra , 400708 , India…

    • 2537 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    The Work Breakdown sometimes is not requested, like when the task is simple and don’t need to be broken in several steps. The milestone in poor planning will not be accurate due the lack of information or miss use from engineer, and will request a bunch of change orders. Therefore the Statement of work is affected by a planning with lack of expertise. However all of them is important for the planning of a project but the most important part in my opinion is the Specification, which tell us in detail all the dimensions and what need to be done, all the goals and objectives for the project…

    • 1006 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Assignment Problems Graded Discussion Topics Week 3 TCOs C & E Scheduling Networks Project Management for Business, Engineering and Technology Chapter 6: Project Time Planning and Networks (pp.196-231) Graded Discussion Topics Quiz Week 4 TCO E Advanced Scheduling and Crashing Project Management for Business, Engineering and Technology Chapter 6, Section 6.6: Scheduling with Resource Constraints (pp. 217-225)…

    • 390 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project?…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week Dqs

    • 274 Words
    • 2 Pages

    A projects scope must be tied to the work breakdown structure or (WBS) because the WBS documents lists task deliverable and identifies all the activities needed to accomplish the final project deliverables. It is utilized to identify the phases of activities, break activities into smaller tasks, estimate the duration of tasks, sequence the tasks, identify needed resource for each task and estimates the resource costs. It forms the basis for other management processes like time, scheduling, cost control and risk management. If the projects scope is not adhered closely then activities may not be defined properly to the projects team, not having a clear understanding of the project leads to confusion on what needs to be done, this will cost the company time and…

    • 274 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project 5

    • 608 Words
    • 5 Pages

    The project plan here will be the brief introduction for all three cases and relative questions: Case 1: Database for Modesto Nuts minor league baseball team We are developing a customer database for the Modesto Nuts minor league baseball team and development activities with predecessor relations are given. We will draw the project network and calculate the time parameters including activity slack. After the calculation done, we will analyze those parameters to check how long will this project take and whether the project schedule is sensitive or not? Case 2: A network plan study…

    • 608 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Best Essays

    Project Management Plan

    • 2196 Words
    • 8 Pages

    The work breakdown structure is breakdown of the hardware, services, and data that is required to help produce the finish product or service. It will show how the work will be performed and will reflect in project costs and data will be reported. (Kerzner, 2013) The purpose of the work breakdown structure for this scenario will provide all the executives with internet access smartphones. The company has decided to expand the program to all their employees that have cell phones or laptops in the hope to save them money.…

    • 2196 Words
    • 8 Pages
    Best Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    1. The activities involved for the project schedule can be represented using Central Path Method (shown below) showing various interdependence and parallelism among activities.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    The information that provided in part 1 alone is not enough to allow the project team in defining any milestones of the project. Actually the hierarchical breakdown of the activity can be designed out of this information but for defining milestones; the project team may well require the following:…

    • 576 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Pinto Pm2 Ism Ch10 1

    • 3754 Words
    • 21 Pages

    Key Terms Solved Problems Discussion Questions Problems Integrated Project: Developing the Project Schedule Case Study 10.1 – Project Scheduling at Blanque Cheque Construction (A) Case Study 10.2 – Project Scheduling at Blanque Cheque Construction (B) MSProject Exercises PMP Certification Sample Questions Bibliography TRANSPARENCIES 10.1 NETWORK INCOPORATING FINISH TO START LAG OF 4 DAYS Lag 4 10.2 FINISH TO FINISH NETWORK RELATIONSHIP 10.3 START TO START NETWORK RELATIONSHIP 3 days 10.4 START TO FINISH NETWORK RELATIONSHIP 3 days 10.5 BENEFITS OF GANTT CHARTS 1) They are very easy to read and comprehend 2) They identify the project network coupled with its schedule baseline 3) They allow for updating and project control 4)…

    • 3754 Words
    • 21 Pages
    Satisfactory Essays