Preview

Nt1330 Unit 6 Paper

Powerful Essays
Open Document
Open Document
579 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Nt1330 Unit 6 Paper
Background:
The Custom woodworking Company has been in the custom furniture business since the early 1950’s. Since their inception they have grown their business and reputation steadily. This growth has demonstrated a need for the company to expand its existing factory floor space. Therefore, the companies stakeholders have agreed to expand the existing property by adding “additional production capacity equivalent to 25% of the existing floor space” (Wideman). Moreover, the floor space would contain “air-conditioning, a dust-free paint and finishing shop, an automatic wood working production train, as well renovated offices for the President and Executive Vice President” (Wideman). The total renovation costs have been outlined not to exceed
…show more content…
Task estimations not defined
9. Budget overruns
10. Project timeline exceeded two years
Proposed Solution:
In order to successfully complete the project a five phased approach based on the PMBOK will be taken.
Phase 1 – Initiation
1. Define the project SOW.
2. Requirements gathering.
3. What are the “project goals, budget, timelines, resources, etc?” (Reynolds, 2010)

Phase 2 – Planning/Designing
1. Define the project team. Identify all key roles and responsibilities within the team
2. Complete a “WBS of all the work that must be done to complete the project” (Wysocki, 2009).
3. Design Review meetings
4. Task duration estimates.
5. Estimate project Costs
6. “Build a project network diagram and establish task dependencies using FS, FF, SS, and SF where needed” (Wysocki, 2009).
7. Resource allocation
8. Define critical path(s)
9. Create a project schedule using Microsoft Project. Project schedule will built from and contain the following information:
a. WBS
b. Project Network Diagram which includes tasks, task estimates, task dependencies, resource names, and completion %.
c. Gant Chart
Phase 3 – Execution
1. Establish open lines of communication to internal/external resources, contractors, sub contractors, and

You May Also Find These Documents Helpful

  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    analytical diagrams of one or more of the projects you are discussing. Tafuri discusses the…

    • 640 Words
    • 3 Pages
    Good Essays
  • Good Essays

    The total duration of the construction project by adding the estimated task duration serially would give us 70 weeks. But some tasks within some activities can be done in parallel sequence or simultaneously, which would significantly reduce the construction project completion time using the critical path method (CPM). In this method the longest path is the critical path which runs through one of the route in the project network diagram from start to finish. This project network diagram is illustrated on the printed assignment page, we have 10 tasks listed from A to J. Below is an activity list of the tasks;…

    • 1246 Words
    • 5 Pages
    Good Essays
  • Good Essays

    The network diagram is a logically schematic display provides graphical view for the project details like the tasks required to be performed, the relations between them and the duration’s estimations for the task itself and for the entire project including the earliest time to beginning the work in a every task the earliest predicted finishing date of the project. Network diagrams used for detailed planning, analyzing scheduling in project implementation and as a control tool in the monitoring and control phase. Two methods used to build the network diagram task-on-the-arrow (TOA) method and the recently one called the task-on-the-node (TON) method, or, the precedence diagramming method (PDM).…

    • 941 Words
    • 4 Pages
    Good Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Develop a critical path chart taking care to show longest path through the network diagram – it is the minimum duration of the project (so that tasks can occur…

    • 397 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    To draw project network, Gantt chart and timing use the project templates from Appendix 1.…

    • 1208 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    The initiation phase is the beginning of the project. In this phase, the idea for the project is explored and elaborated. The goal of this phase is to examine the feasibility of the project. In addition, decisions are made concerning who is to carry out the project, which party (or parties) will be involved and whether the project has an adequate base of support among those who are involved.…

    • 3082 Words
    • 13 Pages
    Powerful Essays
  • Better Essays

    Task Dependencies

    • 1175 Words
    • 5 Pages

    Wysocki (2012, pp.204) identified dependencies as “a relationship that exists between pairs of tasks”. In projects planning, the work breakdown structure (WBS) forms the basis for determination of tasks and their dependencies. Once the WBS is established - often in diagrammatical form, tasks and their dependencies can be easily mapped in the project network diagram. Project network diagram graphically represents project commencement and ending with tasks, activities, various paths to attaining deliverables, etc, in between.…

    • 1175 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Project schedules for the pilot project will be created using MS Project 2010 starting with the deliverables indentified in the project's Work Breakdown Structure (WBS). Activity definition will identify the specific work packages which must be performed to complete each deliverable. Activity sequencing will be used to determine the order of work packages and assign relationships between project activities. The duration of activity estimating will be used to calculate the number of work periods required to complete work packages. Resource estimating will be used to assign resources to work packages in order to complete schedule development.…

    • 454 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Project Network

    • 1752 Words
    • 8 Pages

    A project network illustrates the relationships between activities (or tasks) in the project. Showing the activities as nodes or on arrows between event nodes are two main ways to draw those relationships.…

    • 1752 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    Put the tasks that make up the project into the right sequence and draw a network diagram.…

    • 482 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Network Scheduling

    • 2805 Words
    • 12 Pages

    The basis approach of scheduling techniques (e.g. PERT and CPM) is to construct a network of activity/work element relationships. This network graphically shows the sequence, and interdependencies between activities in a project. Two major steps in solving the…

    • 2805 Words
    • 12 Pages
    Powerful Essays
  • Satisfactory Essays

    International Ratail

    • 678 Words
    • 3 Pages

    ‘A network diagram is originally a flow chart that includes all of the project events and relation of each activity.’ (Rick A. Morris)…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project Management

    • 963 Words
    • 4 Pages

    ‘The network diagram is defined as a graphical presentation of the project’s activities shows the planned sequence of work’ Burke (2003, p.131). It is also called as precedence diagramming method (PDM). ‘It is a method of constructing a project schedule network diagram that uses boxes or rectangles, which referred to as nodes, to represent activities and connects them with arrows that show the dependencies’ The Project Management Book of knowledge (PMBOK) (2004, p. 132). The network diagram (Appendix 1.0) has been drawn out accordingly to the table 1 for Jashol Ltd in order to show activities and period it takes to customise luxury cars for its customers.…

    • 963 Words
    • 4 Pages
    Good Essays

Related Topics