Excavation Safety Quiz
-------------------------------------------------
Top of Form
1. Plywood cannot be used as a structural member for shoring systems unless the system is designed by a professional engineer.
True False
2. The "four-foot rule":
Refers to your means of escape from an excavation Says a means of escape must be provided if an excavation is more than four feet deep Says the exit must be within 25 feet of every worker All of the above
3. Employees in a trench must wear hard hats at all times.
True False
4. All excavations are trenches.
True False
5. In the event of an accident:
Heavy equipment may be used to free the victim All workers should go to the accident area to assist the rescue First aid should only begin after rescue personnel have arrived An emergency response procedure should be followed
6. Welding pipe in a trench creates a potential hazardous atmosphere.
True False
7. The top width of a short duration trench in type "A" soil that is 10 feet deep and 4 feet at the bottom is:
24 feet 14 feet 19 feet 12 feet
8. Remotely located excavations may be left open and unprotected provided no one is working in the area.
True False
9. Excavation material must be kept at least ______ feet from the edge of the trench.
1 1 1/2 2 None of the above
10. The maximum allowable slope for a type "B" excavation less than 20 feet deep is:
45 degrees 90 degrees 53 degrees 34 degrees
11. Ramps are the only acceptable means of entering and exiting a trench.
True False
12. Statistics show that the majority of trenching fatalities occur in excavations less than ______ feet deep.
6 9 15 18
13. The daily inspection of the excavation site done by the competent person includes:
Checking for possible cave-ins Checking for hazardous atmospheres Checking for hazardous conditions All of the above
14. A trench having 19.5% oxygen is always safe to enter.
True False
15. Emergency rescue equipment must be available and maintained at

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Soil Investigation: Prior to any foundation design or excavation work to take place, soil Geotechnical Investigation using process is carried out by a competent contractor, this to explore the surface and subsurface of each foundation. A CME-45B Truck Mounted Auger Drill is used retrieve soil samples, all samples are tested in an off-site laboratory. The truck operators are usually exposed to various types of…

    • 456 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Netw310 Week #4

    • 313 Words
    • 2 Pages

    What are the exact detailed compaction requirements as listed in the manual provided by the city for restoration of any surface that is trenched?…

    • 313 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Nt1330 Unit 5

    • 800 Words
    • 4 Pages

    5. Are there any encroachments between the structure and 900mm of the site boundary or 1.8m of other buildings in the same allotment? (Except Facias, gutters, downpipes, eves with non-combustible linings, flues, chimneys, pipes. Domestic fuel tanks cooling or heating appliances, light fittings,…

    • 800 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    NETW320

    • 403 Words
    • 2 Pages

    6. What are the exact detailed compaction requirements as listed in the manual provided by the city for restoration of any surface that is trenched?…

    • 403 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Technical Writting 12.3

    • 407 Words
    • 2 Pages

    7. Safety boots and hardhats are to be worn by all technicians working within 100 yards of the construction site.…

    • 407 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Unit 4222-264 Answers

    • 302 Words
    • 2 Pages

    Every setting will have visitors from time to time. We need to ensure that everyone entering are clear on which areas they can access, where fire exits are and what contact, if any, they have with…

    • 302 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    WestBan Construction Limited provided the City of Edmonton with work schedule, work plan, WBS and bulk excavation for reviewing on May 25, 1993 for evaluation. All documents…

    • 1987 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    You may need to assess the situation, never rush as this could result in bad manual handling. Check the area around you is safe, and if not remove all hazards. Only administer emergency first aid if you are trained to do so. Get help so they can phone emergency services or if alone call yourself but make sure you know the facts before you call. Make sure you report everything…

    • 1017 Words
    • 5 Pages
    Good Essays
  • Good Essays

    ANT 120

    • 579 Words
    • 3 Pages

    When it comes to excavation, a mixture of test pits as well as large trench excavations will be utilized. At MARV-75 (8739750 Northing, 335395 Easting), we would use a series of test pits in the site. In regards to this site, we are given information that there is evidence of "a village with public…

    • 579 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Oshe Paper

    • 1346 Words
    • 6 Pages

    The general requirements of a confined space as designated by CRR 1910.146 are as follows. The employer shall evaluate the workplace to determine if any spaces are permit-required confined spaces. If the workplace does contain permit spaces, the employer shall inform exposed employees, by posting danger signs or by any other equally effective means, of the existence and location of and the danger posed by the permit space. If the employer decides that their employees will not enter permit spaces then the employer shall take effective measures to prevent its employees from entering the permit spaces and shall comply with the other regulations of this code.…

    • 1346 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    Check for hazards and health, safety and security risks while I am working, taking appropriate action if there is the likelihood of an accident, injury or harm.…

    • 356 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Basement works requires extra work because of the slopes and the root of the trees.…

    • 640 Words
    • 3 Pages
    Good Essays
  • Good Essays

    • You have to put your application with Dial-Before-You-Dig for burrowing close underground framework. Additionally, you can ring up their national call focus at…

    • 1028 Words
    • 5 Pages
    Good Essays
  • Good Essays

    * In case of Stone Crushing Plant operating with CTE /CCA of the Board existing since long, which are located at a distance less then 200 meter from highways, the unit shall provide minimum 6 meter high compound wall or barrier of GI sheets along their plot periphery towards highway/road side. 2)…

    • 797 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Civil Engineering

    • 723 Words
    • 3 Pages

    The maximum differential settlement in foundation on clayey soils and sandy soils should not exceed 40mm and 25 mm respectively. The maximum settlement should generally be limited to the following values:…

    • 723 Words
    • 3 Pages
    Good Essays