Preview

TM Ch07 Managing Risk

Powerful Essays
Open Document
Open Document
3988 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
TM Ch07 Managing Risk
Chapter 7

Managing risk

Chapter Outline

1. Risk Management Process
2. Step 1: Risk Identification
3. Step 2: Risk Assessment
A. Scenario Analysis
B. Probability Analysis
4. Step 3: Risk Response Development
A. Mitigating Risk
B. Avoiding Risk
C. Transferring Risk
D. Sharing Risk
E. Retaining Risk
5. Contingency Planning
A. Technical Risks
B. Schedule Risks
C. Cost Risks
D. Funding Risks
6. Contingency Funding and Time Buffers
A. Budget Reserves
B. Management Reserves
C. Time Buffers
7. Step 4: Risk Response Control
8. Change Control Management
9. Summary
10. Key Terms
11. Review Questions
12. Exercises
13. Case: Alaska Fly-Fishing Expedition
14. Case: Silver Fiddle Construction
15. Case: Peak LAN Project
16. Case: XSU Spring Concert
17. Appendix 7.1: PERT and PERT simulation
A. PERT—Program Evaluation Review Technique
B. A Hypothetical Example Using the PERT Technique
18. Appendix Case: International Capital, Inc.—Part A

Chapter Objectives

To describe the risk management process
To identify different kinds of risks
To illustrate approaches for risk identification, analysis, and assessment
To suggest approaches for responding to project risks
To propose the use of contingency reserves to cover risk events
To recognize the need for a change control process/system for any size project.

Review Questions

1. Project risks can/cannot be eliminated if the project is carefully planned. Explain.

Project risks cannot be eliminated. It is impossible to be aware of all things that might happen when a project is being implemented. Undesirable events identified before the project begins can be transferred, retained/reduced, or shared. Contingency plans with trigger points and responsibility should be established before the project begins.

2. The chances of risk events occurring and their respective costs increasing change over the project life cycle. What is the significance of this phenomenon to a project manager?

The chances of risk events and

You May Also Find These Documents Helpful

  • Satisfactory Essays

    iii.Install water saving devices such as native plants, tank, dual flush toilet systems, 5-6 star (WELS) dishwasher.…

    • 565 Words
    • 3 Pages
    Satisfactory Essays
  • Better Essays

    Mgmt404 Project Plan

    • 1494 Words
    • 6 Pages

    I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen…

    • 1494 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    The benefits of risk response control are improves effectiveness and efficiency of the risk approach during the project implementation. Risk response control includes the following elements throughout the project:…

    • 1596 Words
    • 7 Pages
    Powerful Essays
  • Better Essays

    The available of technology, such as, computers, tablets, ebooks, and even Internet are absent in many households in America still. As of 2013, the Census Bureau suggested that “84% of U.S. households own a computer, and 73% of U.S. households have a computer with a broadband connection to the…

    • 3939 Words
    • 16 Pages
    Better Essays
  • Good Essays

    Why? Risk Management should be an integrated part of the business which the Project Management team surely demonstrated by holding Risk Management to the highest regard from inception to closing. It was clearly a part of every decision made in the project. We learned that risk management should be a ongoing process that is revisited throughout the project and the team followed that protocol to the “T” an example of this at the beginning when the focus was on technical and cost optimization the risks were revisited and focus shifted to schedule along with the risk management processes that had already been established. We see the use of the contingency plans were geared at avoiding or mitigating any identified risks yet supported the project’s main objectives. In addition they were revisited in order to ensure the project stayed on…

    • 1178 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Coffeeville Risk Analysis

    • 742 Words
    • 3 Pages

    The scope of this Risk Analysis Report is to examine the likelihood and all the possible consequences of the risks identified by using all the information gathered through research in Assessment Task 1, as well as the given simulated business information provided on this task. This report shows the risks identified according to priority and urgency. It also includes different options that are carefully picked and assessed according to how much it would most address the risk identified.…

    • 742 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Case 3 Risk Management

    • 1053 Words
    • 5 Pages

    The main factor for not completing the project is team failure which is because of poor overall initial planning. When there are unrealistic goals being set, creating a chaotic working environment there is bound to be nothing but pure failure of the project and its successin the near future. There can be two major causes for the team project failures; overdue or missed time standards, and going beyond set financial plans. With the interpretation of day to day basis risk assessments into team developed projects, there is a more realistic set of guidelines, and procedures put into place. The definition of a risk assessment states , “ that it is theidentification, evaluation, and estimation of the main levels of risks involved in a situation, their comparison against benchmarks or standards, and determination of an acceptable level of risk”. With set risk assessment techniques, the team may further eradicate all possible liabilities or future occurrences within the project team.…

    • 1053 Words
    • 5 Pages
    Good Essays
  • Good Essays

    RISK MANAGEMENT

    • 1958 Words
    • 15 Pages

    The purpose of this project is to open a new coffee shop in the local area of Covington, Ga. Charming Café will be owned by two partners, Allison Hatchell and Marshall Brumfield. This area has a high number of passing shoppers which is supported by a large and growing local population. There are a very few coffee shops in the area. Allison has experience in the restaurant business and Marshall in the commercial development industry there is an opportunity for great success. The coffee shop will serve breakfast, lunch, pastries, and variety of coffee from open to close. Operation schedule will be Monday through Saturday 5am-10pm and Sunday 9am-6pm. For continued success three positions are filled for COO, CFO, and CEO. The COO is responsible for planning and implementing the operations of the business. CFO is responsible for the financials within the company. While the CEO is in charge of all administration tasks for the company.…

    • 1958 Words
    • 15 Pages
    Good Essays
  • Powerful Essays

    Manage Risk

    • 7591 Words
    • 24 Pages

    The reason the investigation was conducted was to gauge what was both good and bad about the new café opening, what needs to be changed in order to increase efficiency at work and any legislative laws involved.…

    • 7591 Words
    • 24 Pages
    Powerful Essays
  • Better Essays

    Proj595 Risk Paper

    • 1690 Words
    • 7 Pages

    Managing Risks in Large Projects and Complex Procurements. Hoboken, NJ: John Wiley & Sons, Ltd.…

    • 1690 Words
    • 7 Pages
    Better Essays
  • Better Essays

    Hillson, D. and Simon, P. (2012). Practical Project Risk Management: The ATOM Methodology. 2nd ed, Tysons Corner, VA: Management Concepts Press.…

    • 2381 Words
    • 9 Pages
    Better Essays
  • Powerful Essays

    Manage Risk

    • 6382 Words
    • 19 Pages

    d) Risk capacity: The amount a business is capable of loosing before it endangers its own sustainability…

    • 6382 Words
    • 19 Pages
    Powerful Essays
  • Good Essays

    As the continued poor showing of the project management and business analysis discipline results in the stagnant and unimpressive current project success rates, MCLMG’s Portfolio / Program / Project Management Research Division has designed, developed, and deployed a more effective and robust project risk management model that supersedes the current “industry practices” of the limited 2 dimensional risk model based on the unit-less assessment of project risk potentials. This current model evaluates project risk potentials in only two (2) dimensions of “severity” and “likelihood” assigning to each an integer value of 1 (low) to 5 (high) of each parameter where upon the risk assessment is made by simply multiplying these values to obtain a qualitative risk priority profile of a unit-less, non-rigorous plane of values ranging from 1 to 25 with the non-assignment of the values 7, 11, 13, 14, 17, 18, 19, 21, 22, 23, and 24 since these combinations are not valid products of two integer operands of 1 to 5.…

    • 4623 Words
    • 19 Pages
    Good Essays
  • Powerful Essays

    manage risk

    • 1369 Words
    • 10 Pages

    This Assessment Project is to be completed in addition to the learning and assessment tutorial activities you complete in class during the course.…

    • 1369 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    manage risk

    • 602 Words
    • 3 Pages

    Max Lionel Realty (MLR), in order to build customer goodwill and satisfy its legal and…

    • 602 Words
    • 3 Pages
    Satisfactory Essays