Preview

Dispute and Cost Control in the Provision for Variations - a Comparative Analysis of Nec3 & Psscoc

Powerful Essays
Open Document
Open Document
1911 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Dispute and Cost Control in the Provision for Variations - a Comparative Analysis of Nec3 & Psscoc
Dispute and Cost Control in the provision for Variations - a Comparative Analysis of NEC3 & PSSCOC

A. Variations (cost control)
B. Dispute Resolution

A. Cost Control in Variations

Generally, cost control in the provision of Variations under most of the building contracts are stated in different steps. Hence, the steps can be generally divided into 3 stages which are variation notification, quotation submission and valuation based on rate, quantity or daywork. The comparison on the Variations was done under NEC and PSSCOC.

Clause 60 of NEC, defines the variations in Compensation Events base on the PM instruction on the changing of work information which is unreasonable to him.

Clause 19.1 of PSSCOC, defines the variations as “any change in the original contract intention”.

A.1 Variation Notification

In the provision of clause 61.1 of NEC, PM give instruction and the Contractor has to submit quotation on the changing decision event. Clause 61.3 states that the Contractor has to notify PM within 8 weeks from the event happened, failing which he is not entitle to claims on the cost and time implication. Under clause 61.4, PM has to reply within 2 weeks of the Contractor notification, or else the notification will be treated as acceptance by PM.

Under clause 20.2 (1) of PSSCOC, the Contractor has to carry out and comply with SO instruction even though the instruction may not a variation to the Contractor. However, the Contractor may request for variation from SO under clause 19.2 in writing within 14 days from the date of SO receipt of the instruction.

A.2 Quotation Submission

Under clause 62.2 of NEC, PM instructs the Contractor to submit his quotation and any delay to the completion date that assessed by the Contractor. However, by clause 63.2, if there is any cost saving or omission that reduce the total Defined Cost/ Contract Sum, the price are not reduces unless stated in the Contract.

By clause 19.3 of PSSCOC, SO may request the Contractor to submit

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Is3350 Unit 1 Assignment

    • 2098 Words
    • 9 Pages

    cases, the entity should disclose the nature of the change and the amount of the adjustment made to…

    • 2098 Words
    • 9 Pages
    Satisfactory Essays
  • Better Essays

    Midterm Comm293

    • 5099 Words
    • 21 Pages

    Part A Brigante Construction Ltd. entered into a contract on October 1, 2002 with the province of British Columbia to construct a multi-unit residential complex in Whistler. The contract price is fixed at $500 million and Brigante expects that the project will be complete by the end of 2005. Other information re: the contract is provided below. Brigante has a December 31st year-end. In $ millions Costs incurred (during the year) Estimated costs to complete at the end of the year 2002 $ 80 320 2003 $ 125 235 2004 $ 140 130 2005 $ 75 0…

    • 5099 Words
    • 21 Pages
    Better Essays
  • Satisfactory Essays

    According the scenario and section according to § 2-206 contract existed verbally only. Establishing the terms should have followed the verbal agreement but it did not happen. § 2-206 said that either or party should follow up on the obligations of agreement or contract and none did so now under new management contract never existed do to not following up properly.…

    • 543 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Wright, we have a situation where implied terms can be involved. What makes this case implied is because we are dealing with a modern contract that allows certain situations of the contract to be somewhat flexible. In this case, Cerdes is suing Wright for breach of contract. Cerdes did not finish the job in enough time that was suitable for Wright. Therefore Wright proceeded to hire other service to complete the job. Due to the fact that time was the purpose of the change in contractors, implied terms can be enforced. The length of time that should be assumed in this case if not stated in the contract should be based on the job and how long it should typically take for a construction of a house. You would be able to determine this by an average number of homes that size being built. If the Cerdes is discovered to have taken too much time, then he should not be awarded the full amount of the…

    • 605 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Love

    • 790 Words
    • 4 Pages

    At the meeting, the decision was made to utilize detailed design and engineering specifications so as to obtain competitive bids on the project. The executive committee required completion of the building within twelve months since the new facility would allow for production necessary to meet a new government contract. The contract was of vital importance to Peach since it would yield additional net income of $4,000,000 annually. Within 2 months after the meeting, Don issued a request for proposal using the recommended specification method with a specific construction time of 9 months. Four proposals were received. Don reviewed them quickly since he had 3 weeks to award the project and execute a contract.…

    • 790 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    From the case we discuss, LabCo’s accounting policy for recognizes revenue from construction contract is reasonable. According to ASC605-35-25-61, an entity… shall use the completed-contract...for which reasonably dependable estimates cannot be made or for which inherent hazards make estimates doubtful. LabCo Company uses a normal standard for its accounting policy which is using Percentage of complection method base on how it determine the profit (cost-to-cost method); but in contract with Halibut, LabCo experiences unexpected difficulties includes: revising design, outsourcing engineering, price of material rising unforeseeably. These are the factors that make cost estimation harder. Percentage of Completion method is appropriate under ASC605-35-25-57, criteria B, The buyer can be expected to satisfy all obligations under the contract and C, The contractor can be expected to perform all contractual obligations. Completion of contract method is used according to ASC605-32-25-90, When lack of dependable estimates…inherent hazards relate to contract conditions or external factors that raise questions about contract estimates and about the ability of either the contractor or the customer to perform all obligations under the contract. Percentage of completion method is inappropriate for this contract, not only because it’s difficult to estimate the cost, but also the product fails to fulfill the buyer’s need. In this case, choosing completion of contract is better decision; based on previous experience, LabCo underestimate the cost and ability of complete the contract is the main reason forces them to change the policy.…

    • 596 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Scenario 7-2

    • 4682 Words
    • 19 Pages

    If it is determined the government actually required a more stringent testing, the government must submit a change order and an equitable adjustment may occur from this contract modification. This equitable adjustment would be towards the target cost so as to not penalize the contractor’s profit.…

    • 4682 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    Graduate Student

    • 2210 Words
    • 9 Pages

    3. Does the customer have the right to expect the contractor to perform risk analysis and…

    • 2210 Words
    • 9 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Interoffice Memo

    • 363 Words
    • 2 Pages

    As you can see in points number one (1) and two (2), we are legally obligated to follow through with notice if the client is potentially…

    • 363 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    If, after termination pursuant to this clause, it is determined for any reason that CONTRACTOR was not in default, the rights and obligations of the Parties shall be the same as if the notice of termination had been issued pursuant to General Condition 46, titled OPTIONAL TERMINATION.…

    • 329 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Three Selected Clauses

    • 984 Words
    • 4 Pages

    The liability of completing additional work requirements resulting from change order directives is shifted toward the subcontractor through the inclusion of a change order clause. This is applicable to the conditions stipulated within the change order clause stricken from the contract. The owner under this clause is given authority to freely issue work order directives with the consideration of the contractor. These changes potentially leave the subcontractor subjected to any actual damages suffered from persistent changes to contractual work obligations. The assumed work liability of the subcontractor is further enhanced by the ambiguous language used to outline the owner and contractor’s responsibilities when determining the acceptance of an issued change order directive. This can lead to an increase in vulnerability for a subcontractor who is bound to the changes made in an arbitrary decision making process. To mitigate the risk of change order directives, I recommend replacing the existing change order clause with a condition defining the parameters for substantial completion of work. The term substantial completion is often used to defend against claims made by the owner against a contractor accused of a breach in the contract. This term can also be utilized to defend…

    • 984 Words
    • 4 Pages
    Good Essays
  • Good Essays

    • Well defined, and adequate documentation, – Presence of a detailed SOP. For the SOP to be adequate it carry name of person who prepared and reviewed it and should be approved by respective functional head.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Downloaded from ascelibrary.org by University College London on 08/31/13. Copyright ASCE. For personal use only; all rights reserved.…

    • 7571 Words
    • 31 Pages
    Good Essays
  • Powerful Essays

    Businesslaw-Take Home Exam

    • 2902 Words
    • 12 Pages

    It is expressly understood and accepted that this is not an employment and as such the Contractor will have no claim to Company benefits or employee considerations, including but not limited to profit sharing, pension, shares or bonuses. Upon expiry of this contract it is understood that the relationship between the parties has ended.…

    • 2902 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    The contractor indicates that the work will last for about six weeks, and no additional funds will be needed. However; the contractor’s crew starts the work in the building three weeks after the agreed date and after eight weeks later the work is finished only about 50 percent. In addition, the work is of poor quality as well as the materials used. Mr. Smith tried to contact the contractor but failed to receive any answer on the project.…

    • 610 Words
    • 2 Pages
    Good Essays