Preview

Contract and Additional Work

Good Essays
Open Document
Open Document
1331 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Contract and Additional Work
Gary Porter Construction v. Fox Construction, Inc., 2004 Ut.App. 354, 101 p.3d 371 (2004).

Facts: The University of Utah was in need of a women’s Gymnastics training facility so they subcontracted Fox Construction, Inc. to complete the project. For the soil and ground work Fox Construction, Inc. subcontracted with Gary Porter Construction. Gary Porter Construction, Inc. performed their work based on specific plans as well as some work outside of the plans. The combined total from the planned project was $146,740. The additional work completed at Fox’s request cost Gary Porter construction additional costs and Fox refused to pay for the additional work done outside the subcontract.

Procedure: A suit was filed by Gary Porter in the Utah State Court against Fox with alleging breech of an implied-in-fact contract. The court granted summary judgment for Porter, which Fox later appealed to a state intermediate court.

Issue: If sections of a contract are left out by mistake, is the contract still valid and enforceable? Were all the requirements of an implied-in-fact contract met?

Holding: Yes

Reasoning: The appellate court affirmed the lower courts summary judgment in favor of Porter. Fox knew that the additional work that Porter did would be followed up with an additional charge. Fox should have known that there would have been additional costs for the work outside of the planned procedure. Porter completed the work only after Fox’s manager requested it and it was implied to be additional from the start. The additional work not planned in the subcontract was valued at $161,309.08 as well as the $135,441.62 contacted value. The issue of the sections being mistakenly not represented in the contract is voided because Fox did not inform Porter about what all needed to be included.

Decision and Remedy: Gary Porter Construction won against Fox Construction, Inc. Fox was ordered to pay Porter the balance of $161,309.08 for the work done but was excluded in

You May Also Find These Documents Helpful

  • Good Essays

    The district court claimed that an express enforceable employment contract covered the same subject for the unjust-enrichment claim. On the second motion, the court dismissed the oral contract claim because there was a material price term in the oral contract which was never agreed upon and therefore the contract was not enforceable. Drew appealed the district court for determining there was an express oral employment contract separate and apart from the promise; and it prematurely dismissed the unjust-enrichment claim considering the Thomas Motors transfer was not enforceable.…

    • 934 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    ISSUES: Whether or not the Trial court’s final summary judgment in favor of Brown Realty Company will proceed for the reason that Donnie McGraw argues that the trail court erred when they granted Brown motion for traditional summary judgment on its breach of contract.…

    • 521 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Huether moved to dismiss based on failure to state cause for action. The court dismissed the case. Holy Cross Parish took this case to the appeals court stating that there was an error in law made. Holy Cross Parish, the appellant, has made it known that the contractors they hired failed to disclose any information pertaining the damages and irregularities. The appellant had the idea that the job would be performed correctly and no issues were brought to their eyes. The contractor also knew of the issues but did not inform anything to the appellant which was misleading. Also the architect and the appellant had a fiduciary relationship but because he remained silent about the final product that the contractor conducted, he has misled and created a breach of fiduciary duty to the appellant. The court of appeals has reverse this case based on the facts…

    • 317 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Issue: The issue is whether the objective circumstances indicate that the parties intended to form a contract…

    • 981 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Legal Memorandum

    • 1316 Words
    • 6 Pages

    Brett received his assignments from the customer service department. He had no contact with customers as any part of his job. After two years of working for Finance R Us, he received a job offer to do the same type of work at Titles Unlimited. He would again, have no contact with customers and receive his assignments from the customer service department. Finance R Us sues Brett for breach of contract due to violating the restrictive covenant in the employment contract.…

    • 1316 Words
    • 6 Pages
    Better Essays
  • Satisfactory Essays

    Love

    • 790 Words
    • 4 Pages

    Winstrom Construction was a local Ohio firm that had completed much of the construction at Wright-Patterson Air Force Base. They submitted a bid of $5,960,000 with a required deposit of $1,000,000. Winstrom had worked previously on a similar project for Peach and had finished it on-time. Don was concerned with the deposit given that Peach would have to supply these funds from capital reserves which were invested at 8% annually, but he rated their quality an A since he heard they had a partnership attitude in dealing with the inevitable problems on the AFB projects.…

    • 790 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Grocery Inc. immediately petitioned for an injunction to request Build to discontinue its construction because of the poor quality. In the mean time, Grocery Inc. sued Masterpiece for breach of contract and specific performance, although specific performance may not be the best choice. Specific performance is granted by the court only if the land or property is unique and/or antique; this is just a renovation of a grocery store. On the other hand, Grocery Inc. should sue Masterpiece for material breach of contract and against Build inferior breach of contract. Masterpiece’s failure to perform the job itself would constitute inferior breach, and material breach against Build for the poor quality of work.…

    • 1076 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Case: Can Cindy Sue Dark?

    • 1677 Words
    • 7 Pages

    The consequent issue regarding this part of the case is the lack of a presence of a legal contract. The question lies upon whether Dark is entitled to pay the maintenance amount of $100 per week to Cindy as agreed upon. More specifically, the case addresses the issue of whether Dark is bound by a possibly existent contract that is, Cindy and Dark have agreed upon the consideration of payment of maintenance and their joint credit card account, respectively.…

    • 1677 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    Caplans Case Study

    • 344 Words
    • 2 Pages

    The Caplans contract with Faithful Construction, Inc., to build a house for them for $360,000. The specifications state “all plumbing bowls and fixtures … to be Crane brand.” The Caplans leave on vacation, and during their absence, Faithful is unable to buy and install Crane plumbing fixtures. Instead, Faithful installs Kohler brand fixtures, an equivalent in the industry. On completion of the building contract, the Caplans inspect the work, discover the substitution, and refuse to accept the house, claiming Faithful has breached the conditions set forth in the specifications. Discuss fully the Caplan’s claim. (Cross 239)…

    • 344 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Parol Evidence Rule

    • 456 Words
    • 2 Pages

    4. Exception was when the language of the written contract was ambiguous, that made the agreement looked incomplete of explanation…

    • 456 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Day V Caton

    • 320 Words
    • 2 Pages

    In this case, the jury found for Plaintiff Day. I also agree with the decision. However, I want to emphasize that I think this lawsuit can be avoided. If plaintiff Day and defendant Caton can write down an agreement before building the wall, they will have an express contract. Plaintiff Day also can acknowledge defendant Caton that he will require a payment.…

    • 320 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    History: Vanderbilt brought the action against DiNardo for breach of contract. DiNardo removed the action to federal court, and both parties filed motions for summary judgment. The district court held that section eight was an enforceable liquidated damages provision, not an unlawful penalty, and that the damages provided under section eight were reasonable. The court held that Vanderbilt did not waive its contractual rights under section eight when it granted DiNardo permission to talk to L.S.U. and that the Addendum was enforceable and extended the contract for two years. The court entered judgment against DiNardo for $281,886.43. Dinardo appeals to U.S. District court.…

    • 634 Words
    • 2 Pages
    Good Essays
  • Good Essays

    The plaintiff, Geoffrey Chism, represented by attorneys Lindsay Halm and Thomas Breen. The defendant, Tri-State Construction Board of Executives including Ronald Agostino, Tom Agostino and Larry Agostino represented by attorneys Jillian Barron and Larry Agostino.…

    • 1501 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Business Law

    • 438 Words
    • 2 Pages

    K entered into a contract with W to supply W with baskets. The baskets were to be delivered by A and a rate was agreed upon between the party. After the first delivery A demanded more money from K before making any further deliveries to W. K unwillingly agreed to pay the extra money and A continued with the delivery. Later on K refused to pay the extra money to A and A sued K. It was held that A had not given consideration to K to buy K’s promise of extra money. A could not say that making the delivery was the consideration, as A was contractually bound to make these deliveries under the original contract. With the case of Dream Design the consideration will not be sufficient where a contractually duty already exist. The fact is that Parma Steel and Dream Design agreed on a written contract dated October 22, 2009 for the supply of fabricated steel at a cost of $165 per ton for “Grade60,000 and $156 per ton for “Hard Grade.” In this case Parma Steel could not say that making the deliveries was the consideration, as Parma Steel was already contractually bound to make these deliveries under t he original contract. According to Tucker J. there was no consideration for the new…

    • 438 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Contract and Indemnity

    • 3944 Words
    • 16 Pages

    1. A contract of guarantee must satisfy all the essential elements of a contract. (For example, the object…

    • 3944 Words
    • 16 Pages
    Good Essays