Preview

Blanque Cheque Construction

Good Essays
Open Document
Open Document
429 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Blanque Cheque Construction
II. Statement of the Problem
• State the problems facing the manager/key person
The manager Joe of Project Scheduling at Blanque Cheque Construction (B) is facing late competition of his first project due to schedule slipping and unforeseen circumstances and it can be damaging to his career due to serious consequences and other penalties.

• Identify and link the symptoms and root causes of the problems.
Upon analyzing this case I identify the warning sign of schedule slipping. The manager Joe was worry with how far behind the schedule was slipping. Schedule slipping was the root of the problem since schedule was slipping “through sequence of accidents, late supplier deliveries, bad weather, and other unforeseen circumstances. “(Pinto, pg. 315) Due to these circumstances project was delayed more than once and for Manger Joe it was impossible to complete project within the next four months.
• Differentiate short-term problems from long-term problems.
Due to schedule slipping and unforeseen circumstances that Joe was facing, his boss decided to give him “some “wiggle room” in the form of $30,000 of optional budget money”(Pinto, pg.315) that will solve short-term problem. Since he got extra $30,000 Joe can speed up the schedule tasks that need to be completed before the due date of the project. The long-term problem here is that the “delivery date for the project is fixed and cannot be altered without incurring substantial penalties.” (Pinto, pg.315) Due to limited time frame, extra money cannot help Joe’s team to complete all late schedule tasks and deliver project on time. To solve the long term Joe decided to crash the remaining activities with optional money to speed up project to its finish line.

• Conclude with the decision facing the manager/key person
The manager Joe of Project scheduling at Blanque Cheque Construction (B) is facing late delivery of the project due to Schedule slipping and unforeseen circumstances and the fact that the

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    • The project schedule is liberal in respect to time for completion of each phase, because not keeping up with the…

    • 1244 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points)…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    An increased resources and materials can cause issues that will affect the project severely if not monitored and addressed in time. The probability may be low, but can change due to several economic and/or political issues that may arise. If such an event happens, it can easily have a ripple effect throughout the project. It can cause the budget to be derailed, which can cause the project be put on hold until more affordable materials can be acquired, or the project as a whole not come to completion. To address this issue, the budget and the economic situation must be closely monitored.…

    • 362 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    From what we can determine so far the main issues revolving around your construction project are unionized workers starting strikes and weather concerns during December. We are also informed that the company will suffer from a $500 per week penalty fee on overhead expenses if the construction project is not finished on time. It is also stated in the contract that a penalty clause of $15,000 per week of delay beyond February 15 of the following year will be implemented.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Good Essays

    My partners and I have made a list of areas that might cause the project delays or failure with their respective outcomes. We have listed the risk below that can prevent the project to finish on time.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Delays for equipment will cause an extension of project task and completion times, therefore, forcing the project manager work through additional conflict. The delay of equipment will cost the project time and money; this where revisions in the project will need to be made. The project manager must identify areas of opportunity to make up time and reduce or cut costs. With inevitable delays, the project manager must communicate with the Vice President and the General Contractor of the revisions made to cut costs and make up time. For example, the project manager may jump to other tasks, related to the project, to keep the project moving forward. The project manager may also revise the plan to eliminate a non-detrimental portion of the project scope to recover loss of funds caused by the…

    • 1059 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    LISD1 Case Study

    • 1080 Words
    • 5 Pages

    There were some delays in the execution of Project. With time extension of the project, the contract was able to manage to complete all the Project activities and deliverables. Conclusions are as follows:…

    • 1080 Words
    • 5 Pages
    Good Essays
  • Better Essays

    Bayonne Packaging

    • 4281 Words
    • 18 Pages

    According to the analysis of this company, there are three major problems that have a huge impact on the way the organization functions which are: quality, delivery time and cost of the final…

    • 4281 Words
    • 18 Pages
    Better Essays
  • Good Essays

    The contractor, Hill Construction (Bob Hill) was given a 270 days deadline for the project. There will be a contract penalty of $10,000 per day for running late. Hill again reviewed the data and noted that the optimistic time estimates can be used as crash times. He gathered his foremen and told them, “Folks, if we’re not 75% sure we’ll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days— also for 240 days. I want to be early, not just on time!”…

    • 966 Words
    • 4 Pages
    Good Essays
  • Better Essays

    The Five Pmlc Models.

    • 987 Words
    • 4 Pages

    He should work into the project contingencies with respect to unforeseen budget and time creep.…

    • 987 Words
    • 4 Pages
    Better Essays
  • Good Essays

    There are two issues in small customer project management. Firstly, the line managers don’t realize that only the project manager can make commitments to the customer as well as on company policy. The other one is that it is hard to keep balance in allocating resource and weight between different projects. The solutions to these problems are to do stringent requirements for the line managers and to get approval during the treating processes. And making a modification of the priority scheduling computer package is the method to make sure the fairness. Also, the staffs in this division are less to handle so many customers.…

    • 420 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    The problem is arising as paying attention on emergency job orders companies move back in the schedule non-emergency orders so they are not meeting their predicted deadlines.…

    • 3977 Words
    • 16 Pages
    Powerful Essays
  • Good Essays

    In the last years there was a raising concern among managers about the many slippages and budget overruns of key projects, while in several cases the promised benefits were not realized after project ends. Understanding the importance of smooth project delivery ability of GE, I – as the Project Management Office Manager of Budapest Bank, GE – propose in this document to initiate a research project to answer questions about reasons of project failures.…

    • 4309 Words
    • 18 Pages
    Good Essays
  • Good Essays

    Fitzberg Tire Company

    • 796 Words
    • 4 Pages

    The Fitzburg Tire Company's construction manager, Max Bierman, has been working on a plant in Cuernavaca, Mexico. This plant is Bierman's first assignment outside the U.S. and it is not going according to his expectations. After merely three months, the project is running behind schedule and overriding its forecasted budget. The occurring…

    • 796 Words
    • 4 Pages
    Good Essays