Preview

Sim 335

Good Essays
Open Document
Open Document
642 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Sim 335
Task 1:
1. Network Diagram (activity on node)
The network diagram is method of creating a graphical figure briefly showing how to execute a project following its planned sequence (Burke, 2003). In order to prepare an appropriate schedule for Fencefall Limited’s Special Project, an activity-on-node version of the network diagram, which was described in details by Field and Keller (2003), was applied as the standard format to implement the drawing, based on the provided activity list.
2. How to determine the timing of activities and total float
EST
Duration
EFT
Activity
LST
Float
LFT
Figure . Activity-on-node task information
According to Field and Keller (2003), every node have associated with 2 pairs of timings and the total float:
Earliest start time (EST) and earliest finish time (EFT), which are done calculating in a forward pass through the network, starting from the Start node way down to the Finish node. The very first task node always has its EST equal to 0, and its EFT will be calculated following the function:
EFT = EST + Duration (Units: days)
The next node will have its EST equal to the EFT of the previous node

Latest start time (LST) and latest finish time (LFT) are proceed in a backward pass, from Finish node to Start node. The LFT of the very last task node equals to its EFT, and its LST function is:
LST = LFT – Duration (Units: days)
The next node will have its LFT equal to the LST of the previous node

Total float = LFT – EFT – Duration = LST – EST – Duration (Units: days)

3. How to determine the project duration and critical path
The duration for this project is 76 days for completion, which is the sum of its LST and the duration of all activities (Project Management Institute, 2008). Besides, the critical path is always defined as the path of activities which all have zero total float. So this project’s critical path is: A →B→C→D→E→H→I→K→L→N→O→R
4. If the project starts on the 1st August 2014 what is the earliest date

You May Also Find These Documents Helpful

  • Good Essays

    WGU JGT Task #1

    • 1134 Words
    • 5 Pages

    Catherine Pang provided the assembly schedule which denotes cycle time which is the maximum amount of time the boot is allowed to spend at each workstation. Upon initial inspection of the workflow, it is noted that a “bottleneck” is noted due to a variance between stations B and C (with a three minute difference) and stations E and F (with one minute difference). Both variances in sequential steps cause…

    • 1134 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    Determine each of the following: Task Earliest Start Latest Start Earliest Finish Latest Finish Slack A 0 6.5 3 9.5 6.5 B 0 0 7 7 0 CRITICAL C 3 9.5 7.5 14 6.5 D 7 7.5 18.5 19 0.5…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    The time column shows the time relative to the first packet. By default, the packets are displayed in increasing order of this time.…

    • 320 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    3) Refer to the figure. What is the slack time, in days, associated with activity E?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    BSBMGT402A ASSESSMENT 1

    • 2713 Words
    • 14 Pages

    In a previous task, you developed a project flow chart and identified a critical pathway for…

    • 2713 Words
    • 14 Pages
    Satisfactory Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Powerful Essays

    Mgt150 Assignment 1

    • 970 Words
    • 4 Pages

    University of Management and Technology MGT 150 Project Management Assignment 1 Bottom-up cost estimating exercise (Module 3, pp. 19-20) 1.0 Research 1.1 Birdhouse Book…………………………………………………. …… $ 30.00 1.2 Jimmy’s time to read up on birdhouses…………………….… …… $ 4.00 1.3 Dad’s time………………………………………………………. ….… $ 80.00 2.0 Materials acquired 2.1 Lumber…………………………………………………………..…

    • 970 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    PERT diagrams in actual practice are so large (often covering entire walls), project leaders normally use a computer to identify the longest paths through such networks. Within a PERT diagram, the longest path to project completion is called the critical path, which is also the shortest completion time of the entire project.” (p. 435)…

    • 911 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Background: The assignment is intended to bring out the benefits and limitations of different approaches…

    • 1135 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is the critical path in the project? How would you assess the level of risk in the project?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    IS SECURITY CONSULTING

    • 1893 Words
    • 8 Pages

    (not the specifics of each task) which tasks do you think are risky and why?…

    • 1893 Words
    • 8 Pages
    Better Essays
  • Satisfactory Essays

    Astable Multivibrator

    • 439 Words
    • 2 Pages

    The circuit diagram for the astable multivibrator using IC 555 is shown here. The astable multivibrator generates a square wave, the period…

    • 439 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    IELM4200

    • 1317 Words
    • 6 Pages

    Basics of Supply-Chain Management IELM 4200, Fall 2011 Dr. Emily Au Dept. of IELM, HKUST Note02: Basics of OM 1 What is a supply chain? • A supply chain is a goal-oriented network of _________ and ____________ used to deliver goods and services to customers. Fundamental activity: flow of entities through processes Note02: Basics of OM 2 Key performance measures • Throughput (TH): the rate at which entities are processed by the system. • Work in Process (WIP): the number of entities in the system, which can be measured in physical units (e.g., parts, people, jobs) or financial units (e.g., dollar value of entities in system). • Cycle Time (CT): the time it takes an entity to traverse the system, including any rework, restarts due to yield loss, or other disruptions.…

    • 1317 Words
    • 6 Pages
    Satisfactory Essays

Related Topics