Problem 1

The following data were obtained from a project to create a new portable electronic.

Activity Duration Predecessors
A 5 Days ---
B 6 Days ---
C 8 Days ---
D 4 Days A, B
E 3 Days C
F 5 Days D
G 5 Days E, F
H 9 Days D
I 12 Days G

Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19)

Step 2: Answer the following questions: (15 points total)

a) What is the Scheduled Completion of the Project? (5 points)
Answer: 32 days

b) What is the Critical Path of the Project? (5 points)
Answer: B-D-F-G-I

c) What is the ES for Activity D? (1 points)
Answer: Day 6

d) What is the LS for Activity G? (1 points)
Answer: Day 15

e) What is the EF for Activity B? (1 points)
Answer: Day 6
f) What is the LF for Activity H? (1 points)
Answer: Day 32

g) What is the float for Activity I? (1 points)
Answer: 0 Days

Problem 2

The following data were obtained from a project to build a pressure vessel:

Activity Duration Predecessors
A 6 weeks ---
B 6 weeks ---
C 5 weeks B
D 4 weeks A, C
E 5 weeks B
F 7 weeks D, E, G
G 4 weeks B
H 8 weeks F
I 5 weeks G
J 3 week I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions: (15 points total)

a) Calculate the scheduled completion time. (5 points)
Answer: 30 weeks

b) Identify the critical path (6 points)
Answer: B-C-D-F-H
c) What is the slack time (float) for activity A? (1 points)
Answer: 5 weeks

d) What is the slack time (float) for activity D? (1 points)
Answer: 0 weeks

e) What is the slack time (float) for activity E? (1 points)
Answer: 4 weeks

f) What is the slack time (float) for activity G? (1 points)
Answer: 5 weeks

Problem 3

The following data were obtained from a project to design a new software package:

Activity Duration Predecessors
A 5 Days ---
B 8 Days ---
C 6 Days A
D 4 Days C, B
E 5 Days A
F 4 Days D, E, G
G 4 Days B, C
H 3 Day G

Step 1: Construct a

You May Also Find These Documents Helpful

  • Satisfactory Essays

    payoff of the put? b) If the stock is trading at $23 in 6 months, what will be the payoff of the put? c) Draw a payoff diagram showing the value of the put at expiration as a function of the stock price at expiration. Long put value at expiration: a. $2 b. $0 c. Draw payoff diagram: Problem 20-11 on Return on Options Based on Chapter 20 Consider the September 2012 IBM call and put options in Problem 20-3. Ignoring any interest you might earn over the remaining few days’ life of the options, consider…

    • 1042 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Homework #2 Solutions

    • 1721 Words
    • 7 Pages

    Physics 221 Summer 2012 HOMEWORK #2 Due Friday June 22, 2012 1 A 70.0-kg person stands on a scale placed on the floor of an elevator. Find: - the weight of the person (magnitude and direction), - the normal force by the scale on the person (magnitude and direction), - and what the scale reads (in kilograms) in the following cases: (a) The elevator moves up with a constant speed of 2.0 m/s2 . (b) The elevator has a constant upward acceleration of 2.0 m/s2 . (c) The elevator has a constant…

    • 1721 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    Homework 2 Solution

    • 1170 Words
    • 5 Pages

    Homework 2 Solution 1. Consider the diagram of the electronic system, which shows the probabilities of the system components operating properly. The entire system operates if assembly III and at least one of the components in each of assemblies I and II operates. Assume that the components of each assembly operate independently and that the assemblies operate independently. What is the probability that the entire system operates? 0.9 0.9 0.8 0.8 0.7 I II III 0.95 Solution: P = [1-(1-0.9)*(1-0…

    • 1170 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    Aib Homework Wk3 Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Solutions Homework 2

    • 1266 Words
    • 4 Pages

    Name: ___________________________________ Date:_____________ Period: _______________ 1. Where on the normal curve are the inflection points located? Where the slope starts to drop off at. 2. What is the standard normal distribution? A standard Normal distribution is a Normal curve with a mean of 0 and a standard deviation of 1. 3. What information does the standard normal table give? The area that falls to the left of the given z-score. 4. How do you use the standard normal table (Table…

    • 1266 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    AIB Problem

    • 565 Words
    • 3 Pages

    Week Three Homework: AIB Problem PROJ586 Project Management Systems Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of…

    • 565 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    W3 Quiz Solutions

    • 657 Words
    • 4 Pages

    questions below, the correct answer is identified with an asterisk 1. (See Exhibit 2-2 on page 58 in your BUSN 5200 Custom text Version 2) Assume Main Street Store’s Net Sales in 2010 were $1,000,000 and it’s Net Income in 2010 was $17,000. Thus, between 2010 and 2011 Main Street Store’s net sales increased 20%. During the same period what percentage did net income increase? a. 5.6% From Exhibit 2-2 on page 58: b. 17.0% 2010 net income: $17,000 2011 net income: $18,000 c.…

    • 657 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    AIB Simulation

    • 771 Words
    • 4 Pages

    Before starting this homework assignment, please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram, and how to do a forward and backward pass to determine the ES, LS, EF, LF and slack (float). You will also learn how to determine the duration of the project, and the critical path. In this homework assignment, you will be working through four Activity In Box (AIB) problems. Using the activity, duration, and…

    • 771 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) b) What is the Critical Path of the Project? (5 points) c) What is the ES for Activity D? (1 points) d) What is the LS for Activity G? (1 points) e) What is the EF for Activity B? (1 points) f) What is the LF for Activity H? (1 points) g) What is the float for Activity I? (1 points) Problem 2 The following data…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) 32 days b) What is the Critical Path of the Project? (5 points) BDFGI = 32 days c) What is the ES for Activity D? (1 points)…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays