Production and Operations Management
296

HANDOUT:
CONTINUOUS FLOW (PRODUCT ORIENTED LAYOUT) AND BOTTLENECK ANALYSIS

Reference: Operations Management by Mark A. Vonderembse and Gregory P. White.

The Product Layout and System Capacity

The capacity of a product-oriented system can be visualized as a series of pipes of varying capacity, with the smallest diameter or capacity holding back the entire system. Exhibit 9.3 illustrates five pipes (departments or machines) with different diameters (capacities). The output from one pipe becomes the input to the next until the finished product exits pipe number five. In Exhibit 9.3, pipe number two cannot handle all the flow that pipe number one can deliver, and therefore it restricts the flow. Because of pipe number two’s limited capacity, it restricts the flow from upstream pipes and starves the downstream pipes. Pipes three, four, and five can work on only what pipe two can deliver. This restriction is called a bottleneck, and it determines the system’s capacity.

Analysis of System Capacity

In a product-oriented layout, identifying the bottleneck is critical. The importance of this analysis cannot be overstated because the results are used not only in determining capacity, but also in planning and scheduling production, which will be discussed in Part III on planning and managing operations.

The approach to determining the bottleneck is illustrated in Exhibit 9.4. Start at the beginning of the system, and determine the capacity of the first operation or department. This is the system capacity so far. Use this capacity as the input to the next department in the sequence. Can that department take the total input from the previous department and process it completely? If it can, then the system capacity has not changed. If it cannot, then the system capacity is reduced to the capacity of that department. The procedure continues until the end of the process is reached and the system capacity is known.

Consider the example

You May Also Find These Documents Helpful

  • Good Essays

    Super study guide2 MIS 373

    • 2143 Words
    • 11 Pages

    - Goal: To achieve a match between the long-term supply capabilities and the predicted level of long-term demand…

    • 2143 Words
    • 11 Pages
    Good Essays
  • Good Essays

    The Goal Book Report

    • 642 Words
    • 3 Pages

    The hiking example was an example of a bottleneck. Nobody behind the fat kid get to the finish until he did. His speed determined the throughput of the entire group of hikers finishing. This concept is one that could be applied to manufacturing. What happens in manufacturing is not an averaging out of the fluctuations, but an accumulation of the fluctuations.…

    • 642 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Kouvelis P, Chambers C, Yu D., 2005. Manufacturing operations manuscripts published in the first 52 issues of POM: Reviews, trends, and opportunities. Production and Operations Management, 14, 450-567.…

    • 11337 Words
    • 46 Pages
    Powerful Essays
  • Satisfactory Essays

    Goal Report

    • 645 Words
    • 3 Pages

    The bottleneck is defined as the resource such that the capacity is equal to, or less than the demand placed on it. To identify the bottleneck for this particular case, those processes were analyzed after which there is usually a shortage of material…

    • 645 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Due to the incompatible product natures and production processes, transferring production to other plants is not a sensible move. The low-overhead, high-throughput operations at a flow shop like Lancaster or Saginaw depend on the high-volume and standardized nature of the products manufactured there. Bringing a variety of low-volume and customized products into the mix could clash with current production force competencies, disrupt the production flow, and consequently reduce efficiency at the flow shops. In…

    • 596 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    What is the situation with manufacturers in your area? Are they firing workers or hiring more? What are some of the environmental factors affecting local plants?…

    • 1309 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Ncc Case

    • 1281 Words
    • 6 Pages

    The next vulnerable bottleneck is the “Jumbo Separator” system. Once the Drying station capacity is increased to meet the input rates, the input rate (20 Trucks/hr) for Jumbo Separators exceeds the maximum capacity of the station (16 Trucks/hr).…

    • 1281 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    Materials Request

    • 5451 Words
    • 22 Pages

    Kumar, A, 2004. PRODUCTION PLANNING AND CONTROL. ., [Online]. ., .. Available at: http://www.du.ac.in/fileadmin/DU/Academics/course_material/EP_08.pdf [Accessed 25 January 2012].…

    • 5451 Words
    • 22 Pages
    Powerful Essays
  • Good Essays

    definition of Bottleneck

    • 501 Words
    • 2 Pages

    “A bottleneck is defined as any resource whose capacity is less than the demand placed upon it” (Chase, Jacobs, & Aquilano, 2006, pg. 725), when dealing with vendors many items can cause an issue or constraint on the resource. Dr. Eli Goldratt stated that businesses do not do as good a job at controlling their resources and stock levels. He solved the problem by using OPT or optimized production technology, by doing this he was able to identify nine rules of production scheduling that maximize production by identifying and reducing bottlenecks. During my evaluation from the first three weeks I have encountered two definite bottleneck situations.…

    • 501 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Three Basic Strategies for Timing Capacity • Average Capacity Strategy – capacity is increased to meet average expected demand – moderate strategy…

    • 604 Words
    • 18 Pages
    Satisfactory Essays
  • Good Essays

    bottleneck for firms as far as production is concerned. So is the case for SPC GmbH. Therefore,…

    • 1194 Words
    • 5 Pages
    Good Essays
  • Better Essays

    A discrepancy between the capacity of an organization and the demands of its customers results in inefficiency, either in under-utilized resources or unfulfilled customers. The goal of capacity planning is to minimize this discrepancy. Demand for an organization 's capacity varies based on changes in production output, such as increasing or decreasing the production quantity of an existing product, or producing new products. Better utilization of existing capacity can be accomplished through improvements in overall equipment effectiveness (OEE). Capacity can be increased through introducing new techniques, equipment and materials, increasing the number of workers or machines, increasing the number of shifts, or acquiring additional production facilities.…

    • 909 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Work-in progress- output of preceding stage becomes input for succeeding stage Inventory decisions require analysis of workstation capacities, resource availability & bottlenecks…

    • 849 Words
    • 4 Pages
    Satisfactory Essays
  • Best Essays

    operations management

    • 1845 Words
    • 7 Pages

    Slack, N., Chambers, S., & Johnston, R., (2010). Operations Management, (6th Ed) Financial Times Prentice Hall.…

    • 1845 Words
    • 7 Pages
    Best Essays
  • Good Essays

    Production and Operations Management ("POM") is the transformation of production and operational inputs into "outputs" that, when distributed, meet the needs of customers.…

    • 441 Words
    • 2 Pages
    Good Essays