Preview

Rc Coleman Managerial Report

Powerful Essays
Open Document
Open Document
656 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Rc Coleman Managerial Report
RC Coleman Mnagerial report

Managerial Report
1.
Activity | Expected time | Variance | A | 6 | 0.44 | B | 9 | 2.78 | C | 4 | 0.44 | D | 12 | 7.11 | E | 10 | 1.00 | F | 6 | 0.44 | G | 8 | 7.11 | H | 6 | 0.44 | I | 7 | 2.78 | J | 4 | 0.11 | K | 4 | 0.44 | Total Expected time 76 weeks Activity | ES | EF | LS | LF | Slack | Critical | A | 0 | 6 | 3 | 9 | 3 | No | B | 0 | 9 | 0 | 9 | 0 | Yes | C | 9 | 13 | 9 | 13 | 0 | Yes | D | 13 | 25 | 17 | 29 | 4 | No | E | 13 | 23 | 13 | 23 | 0 | Yes | F | 23 | 29 | 23 | 29 | 0 | Yes | G | 13 | 21 | 21 | 29 | 8 | No | H | 29 | 35 | 29 | 35 | 0 | Yes | I | 29 | 36 | 32 | 39 | 3 | No | J | 35 | 39 | 35 | 39 | 0 | Yes | K | 39 | 43 | 39 | 43 | 0 | Yes |

Expected time to finish the project is E(t)=B+C+E+F+H+J+K =9+4+10+6+6+4+4=43 weeks
Standard deviation=the sum of the variances of the critical path =B + C + E + F + H + J + K =√2.78 + 0.44 + 1.00 + 0.44 + 0.44 + 0.11 + 0.44 = √5.56 = 2.38

At Time =40 z= (40-43)/2.38 = -1.26 Cumulative probability= 0.1038 or ~ 10%

The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.
2.
80% of a probability of ~0.7995 has a z score of 0.84. Thus 40-E(t)/√5.67=0.84 E(t)=38 weeks
If the project is shorted to 38 weeks, R.C. Coleman will be able to achieve the goal of 80% completion at 40 weeks. R.C Coleman should crash activities to reduce the expected project completion time to 38 weeks.

3.
Crashing decisions table; Activity | Normal | Crash | Normal Cost | Crash Cost | Maximum Reduction Time | Crash Cost per Day | A | 6 | 4 | 1,000 | 1,900 | 2 | 450 | B | 9 | 7 | 1,000 | 1,800 | 2

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    Pm592 Course Project 2

    • 3890 Words
    • 16 Pages

    After entering the data and setting the project to 40% completion, we noticed that the project is behind schedule. This was apparent by the Schedule Variance and the SPI (Schedule Performance Index). The Schedule Variance for the project is ($570,977.84) with a Schedule Variance Percentage of -35%. We also noticed that…

    • 3890 Words
    • 16 Pages
    Powerful Essays
  • Good Essays

    My partners and I have made a list of areas that might cause the project delays or failure with their respective outcomes. We have listed the risk below that can prevent the project to finish on time.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Expected completion time is 45.83 days. The expected completion is very close to the realtor’s due date for project completion. Required probability analysis will also be performed that the project will be completed, as follows as per the probability analysis…

    • 468 Words
    • 8 Pages
    Satisfactory Essays
  • Satisfactory Essays

    There are two important aspects that need to be considered. The first one is that we have three developers located in Florida and there is hurricane season over there. We need to assess the possibility that they will not be able to complete their work on time and that their tasks…

    • 503 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    operation management

    • 252 Words
    • 1 Page

    To conclude, we cut activity T by 2 weeks. The project can be completed in 14 weeks.…

    • 252 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    NB. Any individual submitting his / her work after the due deadline date without a reasonable excuse can only hope to achieve up to a maximum of 40% for this assignment. No marks will be awarded if the assignment is submitted two weeks after the deadline date.…

    • 306 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Pert Mustang

    • 1016 Words
    • 5 Pages

    A table containing the project activities, the time estimates and the precedence relationship will be prepared and a network diagram will be drawn to structure the immediate predecessor activities. The critical activities will be identified to indicate that the project can be completed within 45 working days.…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Proj 592 - CP3

    • 1453 Words
    • 11 Pages

    After setting the entire project to 40% complete on Oct 1, 2008 we can see that the project is behind schedule. The schedule variance of the entire project is $ (736,599) and Schedule performance index is at 0.68, which indicates that for every $1.00 spent in the project we are only getting $0.68 worth of work done. Since we do not have actual cost data, the MS Project calculates the budget is under budget by a negligible $80.…

    • 1453 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    Research: Some colors reflect light and heat energy. Other colors absorb light and heat energy.…

    • 326 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Risk Assessment

    • 768 Words
    • 3 Pages

    The project implementation deadline occurs in 9 months. Each month after the deadline is missed, a penalty of $100,000 is assessed. Three months after the deadline, the contract will be cancelled.…

    • 768 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Stats Histograms

    • 688 Words
    • 3 Pages

    b. I chose the number of classes based on the Sturges’ Rule table. I knew I had 80 observations so that put me between either 7 or 8 classes. I chose 8 for both because that allowed the data to completely taper off at the very ends of the data; meaning the extremely low values were caught within the first and the last classes. I chose the width of the classes by taking the lowest value minus the highest value and then dividing that number by the amount of classes I intended on using. For example, in the MPG histogram I took 44 minus 11 and then divided by 8. That gave me about 4.13 so I rounded up to five to make all the numbers whole numbers.…

    • 688 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    This Discussion will give you the opportunity to calculate or identify the three measures of central tendency. You will be asked to select an appropriate real life situation in which one measure would be more appropriate than the other two measures of center.…

    • 816 Words
    • 4 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    1. What is the estimated project completion date? (Assume there are no holidays and ignore the sunk cost of the planning team’s effort)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    ACC 497 Final Exam

    • 2281 Words
    • 11 Pages

    15) A simple diagram that shows estimated completion times versus actual completion times for the various activities in a systems implementation project…

    • 2281 Words
    • 11 Pages
    Good Essays