Project Management
TYPES OF PROJECT CONSTRAINTS

Project constraints delay the start of project activities. Three project constraint need to be considered in scheduling.
1. Technological or Logical Constraints: These constraints show the sequence in which project activities must occur. A project network framing a house might how three activities i-e (1) pour foundation, (2) build frame, (3) cover roof. All of thee three activities are in sequence because each activity depend on previous one. We can say that we cannot perform activity 2 until 1 I completed.
2. Physical Constraints: Physical constraints are in rare situation that cause activities that would normally occur in parallel to be the constrained by environmental condition. For example, renovation of a hip compartment might allow only one person to perform an activity because of pace limitation, the procedures for handling physical constraints are similar to those used for resource constraints.
3. Resource Constraints: A project network planner may assume adequate resources and show activities accruing in parallel because parallel activities hold potential for resource conflict. For example you are planning a wedding reception that includes four activities which are
1) Plan
2) Hire band
3) Decorate hall and
4) Purchase refreshments.
Each activity takes one day. Activity 2, 3 and 4 could be done parallel be different people. Thee activities are not technically dependent on each other. If one person performs all these activities, the resource constraint requires the activity to perform in sequence. So the consequence is delay and the very difficult set of network is shown. Resource dependency takes priority over technical dependency, but does not violate the technical dependency. That is hiring band, decoration and purchase of refreshments are in sequence rather then concurrently but they must be completed before arrival of the guests.
Even in the small projects in interrelationship and interactions

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    A) The triple constraint of project management describes the interdependency between the three cornerstones of a project: 1. Scope - all the work we have to do in order to create the clearly specified product. 2. Schedule - the time we need in order to create that product. 3. Budget - the total amount of money we need in order to create that product. If the scope is increased because of additional features added to the product then the time and amount of money has to increase as well. In order to shorten the time we could reduce the scope and consequently reduce the budget of that project. The time could be shortened as well by involving more resources…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Any restriction that defines a project’s limitation in project management is a constraint. Three project constraints- scope, cost and schedule are also known as the triple constraints or the project management triangle. Each of these constraints relates to each other and cannot be altered without affecting at least one of the others.…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Our text book mentioned some of the critical success factors when scheduling. Some of these factors are when attempting to reduce the duration of a path activities that has a negative slack, focus on activities that are near term and activities that have long estimated duration, the person who will be responsible for performing the activity should approximate duration for that activity, the key to effective schedule control is address any paths with negative or deteriorating slack values aggressively as soon as they are identified, and activity estimated duration should be yet realistic (Gido & Clements, 5th Ed, pg 180). Based on the factors above, the schedule should be revised to find activities with negative slack and timing interval. For example, recruiting & training, create building design estimated duration time could be adjusted to shorter period. This will cause the earliest start and earliest finish time of other activities around these tasks to be adjusted and hence it might create some positive slack time. The Gantt chat also reveals that during the…

    • 611 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Date constraints –> Date constraints establishes time milestones or benchmarks on a project that the entire construction team works toward…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Meredith and Mantel (2000, 302) state that a schedule is the conversion of a project action plan into an operating timetable. As such, it serves as the basis for monitoring and controlling project activity and taken together with the plan and budget, is probably the major tool for the management of project. In a project environment, the scheduling function is more important than it would be in an ongoing operation because projects lack the continuity of day-to-day operations and often present much more complex problems of coordination.…

    • 536 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Project Network is the diagrammatic representation of interconnected activities in project. Activities in a project network are either successor or predecessor activities. Project Network is also known as Precedence Diagram. Project Networks are composed of Nodes and arcs. Time sequenced from Left to Right. All activities except start and finish time must have at least one predecessor and one successor.…

    • 446 Words
    • 2 Pages
    Good Essays
  • Good Essays

    E Alfonzo

    • 711 Words
    • 3 Pages

    For resource-constrained projects, resource scheduling (leveling) reduces flexibility because (after leveling) slack is reduced and the amount of critical/near-critical activities increases; therefore, the number of CP’s may also increase. Further, scheduling complexity increases due to the fact that resource constraints are ADDED to technical constraints. The original CP concept…

    • 711 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Triple Constraint

    • 1267 Words
    • 6 Pages

    The triple constraint of project management is the balance of the project’s scope, time and cost. Triple constraint is used to determine whether or not a project’s objectives are being met. During the planning phase of a project, a project manager will define the scope, time, and cost of a project. As the planning phase continues, the project manager discovers that there may be some changes or adjustments needed in the project’s scope, time and/or cost. When one aspect needs change or adjustment, then it directly affects one of the other factors of the triple constraint.…

    • 1267 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    McMullen, T. B., 1998. Introduction to the 'Theory of Constraints (Boca Raton, Florida; St. Lucie Press).…

    • 2978 Words
    • 12 Pages
    Powerful Essays
  • Satisfactory Essays

    The goal of every project is to make profit. The sooner the project is completed, at least by the deadline, the better it is for the project to accrue its potential benefits –and vice versa. Constraints, negatively affect project goals. In the triple-constraints (time, cost, scope), time remained the most impacting constraint to projects. The critical chain resolved this issue by removing protection time from tasks, aggregating them into feeding and project buffers, and placing them in strategic locations within the project network where they will serve to protect the project as a whole. This way, the fixed elements of each task is the aggressive but possible estimate, whilst the variable components are called safety. The safety is managed and adjusted time after time to the needs of the schedule. However, time is not the only constraint affecting projects, and the technique of Theory of Constraint (TOC) deals with these constraints to optimize project performance.…

    • 718 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    use case senario

    • 825 Words
    • 4 Pages

    Constraints - The formal rules and limitations a Use Case operates under, defining what can and cannot be done. These include:…

    • 825 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Project Management of KLIA2

    • 5171 Words
    • 81 Pages

    Kuala Lumpur International Airport 2 (KLIA2) is a low-cost carrier terminal at the Kuala Lumpur…

    • 5171 Words
    • 81 Pages
    Good Essays
  • Satisfactory Essays

    Chief

    • 2199 Words
    • 9 Pages

    Level: 3 Assignment Code: SIM335 Issue date: 12 November 2012 Contribution to module assessment: 100% dition, a This is an individual assignment - complete both tasks 1 and 2 Background: The assignment is intended to bring out the benefits and limitations of different approaches to project planning and control by relating these to the circumstances in the cases outlined. It is also intended to allow students to demonstrate their learning and competence in respect of the management of resources generally, but in particular elements of scope, schedule, quality, and cost. Case 1: Mangeist Ltd is an organisation which provides plant and materials to the building sector. These products include: Cement Mixers, Dump Trucks, Compressors and Pneumatic Drills, Lighting rigs, and Vibrating Plates. As part of your job as the Mangeist Ltd special projects manager, you have produced a list of activities that need to be addressed to source a new range of industrial forklift trucks for supply to the sector. The details are shown in the table provided. Please note: You must use the methodology detailed above table 1 headed “essential methodology”. Task 1 (40% marks) 1) Draw the network diagram (use activity on the node). (8 marks) 2) Explain how you determined the timing of activities and the total float. (6 marks) 3) Explain how you determined the project duration and the critical path. (6 marks) 4) If the project starts on the Monday 7 January 2013, what is the earliest date it can be completed using a 5 day working week? Assume no other holidays (explain how you calculated the figure). (4 marks) 5) If the following happened what would be the effect on the duration of the whole project? Explain the reasons. (6 marks) a) Activity B is delayed 1 day. b) Activity P is delayed 1 day. c) Activity 0 is delayed 2 days 6) Explain the limitations of Network diagrams. (10 marks) Module: SIM335 Managing Projects Module Leader: Michael Cassop-Thompson Return…

    • 2199 Words
    • 9 Pages
    Satisfactory Essays
  • Powerful Essays

    Planning & Scheduling

    • 2577 Words
    • 11 Pages

    Abstract: World is driven by projects. Every change that happens, is an outcome of a project. Projects are cause for change since ancient times. Be it building Great wall of China of Marvelous Taj Mahal, Building of and fort or palace or any Stadium. We see projects all around us as a change initiator. There was a time when projects like building Taj Mahal took twenty two years to complete, or The Great wall of China took more than fourteen years. Those were the projects influenced by the king to show love for his wife or by and emperor to save his country. Although they had a time limit for their completion but as they were being done for the first time and need extremely good quality of materials. Engineering and resources for their long life, they were allowed to take so long time. Considering today’s life changing projects may include making satellites, dams, bridges like Bandra-Worli Sea Link in Mumbai or many other such projects which influences human life, these projects have a bigger impact on mass population, linking them with benefits of financial or non-financial organizations. This linkage with the general public and need of staying in the market arises need for completing them in even lesser time. New technological interferences and competition among private players in the business have further increased stakeholders expectations in terms of money and time. Planning and Scheduling plays an important role for achieving these endeavors. This paper illustrates the need of planning and scheduling in today’s project driven world and importance of system’s approach in planning processes required to achieve time, cost and quality targets of any project.…