Procurement Plan
Procurement planning Case Problem
Question 1 1 Machine | Quantity | Unit Price | Total | | | | | Moulding | | $285,000/unit | $304,950 | Resin | 125,000kg | $2 /kg | $250,000 | Labour | 4,166 Hours | $18/Hour | $74,988 | OH | | | $86,236.20 | Opportunity Cost | | | $80,000 | Total Cost | | | $796,174 | | | | | Purchasing | Quantity | Unit Price | Total | Purchase | 250,000 units | $3/unit | $750,000 | OH | 100 orders | $50/order | $5,000 | Inspection | | | $35,000 | Total Cost | | | $790,000 | 2 Machines | Quantity | Unit Price | Total | Moulding | | $285,000/unit | $304,950.00 | Resin | 125,000kg | $2 /kg | $250,000.00 | Labour | 8,332 Hour | $18 /Hour | $149,976.00 | OH | | | $172,472.40 | Opportunity Cost | | | $160,000.00 | Total Cost | | | $1,037,398.40 |
According to calculation above, because there are two machines in Firebird, such that difference in total costs will take place when either one or two are in use. Moulding unit’s future value is: $304,950=PV×(1+r)n=$285,000×1.071
Resin cost is: 125,000kg×$2/kg=$250,000.
When one machine is in use, two labours are required so it will be 2083 hour/labour×2 labours×$18/labour=$74,988 and cost would be double as $149,976 when two machines are in use as well as overhead costs. In terms of opportunity cost, as descripted in assumption, it is the cost that if the plant was not invested. Therefore, when one machine is in use, opportunity cost is $80,000, and it will double when two in use.
Thus, based on above results, purchasing method will be suggested because it costs less than the other two options.
Question 2: Cost to the Society
Unemployment
I. Stresses of possibly losing their ability to earn a living and support their families and indulging in criminal and illegal activities. II. Unemployment at home, along with movement to other areas/ countries, most workers at home country displaced by the

You May Also Find These Documents Helpful

  • Good Essays

    Siempro Baseball Field is in need of a practice field. The land chosen is approximately 20 acres and has a few structures and trees. The existing water and sewer lines will need to be inspected/connected and the project deadline will be 2 years from project start date. We will be selecting one General Contractor to complete this project. The end result should include an updated field, clubhouse, and parking area to hold about 50 cars. We will need existing plans, specs, and drawings to map out this new renovation. The intent of this document is to provide interested vendors and enable them to submit sufficient information for the project. There will be 2 vital phases to begin this project:…

    • 592 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Economics Quiz 2000

    • 1442 Words
    • 6 Pages

    E) long-term and chronic unemployment that exists even when the economy is producing at a normal rate.…

    • 1442 Words
    • 6 Pages
    Better Essays
  • Satisfactory Essays

    Study Guide

    • 470 Words
    • 2 Pages

    13. Jobs in the secondary work force are being moved to third world countries where women work for low wages…

    • 470 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    The Sorrel Pharmaceuticals Corporation manufactures a variety of drugs that are marketed internationally. Inventories on May 31 and June 30 were as follows:…

    • 2411 Words
    • 10 Pages
    Good Essays
  • Good Essays

    Since there is no work in process at year-end, all amounts in the Work-in-Process account must be transferred to Finished-Goods Inventory. Thus:…

    • 1216 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Midwest Office Products

    • 1136 Words
    • 5 Pages

    These costs are based on personnel costs. Manual costs consist of both entering basic information and an additional cost for each line item. The electronic entry has a single cost.…

    • 1136 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    The report entitled “BIDDING AND FINANCIAL ANALYASIS OF N.T.P.C. ” is about the purchase practices followed at NTPC. These practices are followed during all procurement by NTPC. The purchase procedure starts at Indenting by the department that requires the material and goes to the cost department and finance department for required approval. In between various activities like Liquidated Damages calculation, Spare Parts procurement terms, Guarantee in Liability Defect period etc are undertaken. Once all the terms and conditions are formulated and approved, the tender document preparation starts. The tender documents are issued to the prospective bidder for a cost that starts from Rs 200 to Rs 3000. The content of the tender document is prepared in such a manner that the prospective bidder comes to know about all the important details about the contract. The issuance of tender document is followed by the receipt of Bids from various vendors in the specified format. Once all the bids are received, they are opened in presence of some nominated…

    • 16309 Words
    • 66 Pages
    Powerful Essays
  • Powerful Essays

    procurement

    • 20590 Words
    • 83 Pages

    Act 663 Public Procurement Act, 2003 ARRANGEMENT OF SECTIONS Sections PART I—ESTABLISHMENT OF THE BOARD 1. 2. 3. 4. 5.…

    • 20590 Words
    • 83 Pages
    Powerful Essays
  • Powerful Essays

    Procurement

    • 3474 Words
    • 14 Pages

    Department of Building Economics, University of Moratuwa, Moratuwa, Sri Lanka; shiyalk@yahoo.co.uk The procurement system is a key means through which the client creates the pre-conditions for the successful achievement of project specific objectives. Different procurement systems are used for different projects and the appropriate selection may help to avoid problems and be the key to the attainment of project specific goals. In Sri Lanka, the practice of procurement selection is rather unstructured and ad hoc. Therefore a realistic and systematic approach for the selection of the most appropriate system is essential to aid clients in selecting procurement systems. This paper presents a construction procurement selection model based on decisive factors. It particularly examines and analyses factors in terms of clients’ requirements, project characteristics and the external environment in which the construction industry operates. Four rounds of Delphi surveys were carried out to investigate the most important factors and their level of influence on various construction procurement systems. It was found that client requirements are the most…

    • 3474 Words
    • 14 Pages
    Powerful Essays
  • Good Essays

    E Procurement

    • 4520 Words
    • 19 Pages

    K Bikshapathi Project Manager, eProcurement and P Raghuveer IFS Addl. Secretary (e-gov) Information Technology & Communications Department Government of Andhra Pradesh, Hyderabad…

    • 4520 Words
    • 19 Pages
    Good Essays
  • Satisfactory Essays

    The cost sheet shows that in 2009 the company started with an opening stock of Rs 43,49,117 thousand.After making a purchase of of Rs 24,50,317 thousand it was left with a closing stock of Rs 49,87,379 thousand.Thus the raw materials consumed amounts to Rs 18,12,055.There is no direct cost.The total of factory overheads amounts to Rs 25,97,095 thousand.With closing work in progress of Rs 86,545 thousand the net work in progress is Rs 43,22,605.The administrative expenses include employee cost, freight,transport,…

    • 340 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    E Procurement

    • 1315 Words
    • 6 Pages

    Lego group, a privately held company which is a construction toys company based in Billund, Denmark. The company was founded and formed by the Krik Kristiansen and his family in 1932.…

    • 1315 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    E Procurement

    • 354 Words
    • 2 Pages

    Southern Railway has successfully rolled out e-procurement system and all advertised tenders of Materials Management department have already been uploaded in the web site www.ireps.gov.in which can be accessed under the link www.ireps.gov.in→SR→COS In order to participate in e-tenders, it is essential that you register in the website using the link www.ireps.gov.in→New Vendors. Please note that possession of valid class-III type of Digital Signatures Certificate with Company Name is a pre-requisite for registration. Digital Signatures can be obtained from the certifying agencies ,details of which are available in the website www.cca.gov.in. In case DSC is available on individual name, necessary arrangement may be made to possess the DSC with Company Name Before registration, please visit the link www.ireps.gov.in→Learning Center→Vendor User Manual wherein the Vendor User manual with detailed guidelines for registration and participation in the tenders are available for downloading. To familiarise yourself with registration process,you can also register in our trial site www.trial.ireps.gov.in which does not require a digital signature certificate. On successful registration an e-mail will be generated by the system to your email id with username and password using which you can login and submit your bids electronically. If you find any difficulty in registering you can contact…

    • 354 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Project Plan

    • 686 Words
    • 3 Pages

    The project is entirely on the design and development of a soft starter converter that will satisfy and implement the soft starting and soft stopping for speed control of an induction motor. Soft starters also called solid state starter are used for gentle starting and stopping of induction motors. Pumps, centrifuges, compressors, escalators, belt conveyors, mills, fans, stone crusher and saws are typical applications. If a motor is not adequately protected the sudden change in rotation torque and speed, which occurs on starting and stopping will jolt the equipment linked to it. Over the long term this can lead to increase in mechanical wear of gearboxes, clutches, transmission and conveyor systems. Abrupt starting and stopping can also damage goods being handled by the mechanical equipment. For instance, the filling and distribution of glass bottles and containers loaded on to a conveyor holds a potential for a minor disaster. One sudden jerk during starting and stopping will surely cause the entire process line to engage in a mass of broken glasses and dripping liquids or sticky product. With pumps soft starters eliminate pressure shocks in pipes and valves when the pipe pump starts or stops. This poses a particular safety hazard when the transfer of volatile and/or inflammable liquid is involved.…

    • 686 Words
    • 3 Pages
    Good Essays
  • Better Essays

    E Procurement

    • 5124 Words
    • 21 Pages

    Limiting choices to only those suppliers, materials, and services that they are confident can meet pre-approved levels of price and quality.…

    • 5124 Words
    • 21 Pages
    Better Essays