Ilab Week7
Review Questions Name ____________________________

Answer the following questions: 1) Why is it best not to enter a percentage (%) completion?

Because using the percentage at competition is very subjective. Great care has to be taken to ensure that everyone involved in the project understands what the percentages mean before utilizing them.

2) According to your Project Summary, is this project on schedule? Will you be over or under budget and by how much?

According to the Project summary, this project is currently on schedule. The project summary is currently indicating that the project is coming in under budget by $1,720.00.

3) After printing out the Earned Value report, define (you may use MS Project help) the following terms and write in the Total Values of each from your Earned Value Report (Make sure your current date is properly set to 11/14/2011).

PV: this is the amount of budget planned to be spent during a given period of time = $22,919.23

EV: this is a value indicating how much of a budgeted cost should have been spent given the amount of work actually completed = $7,120.19

AC: this is the amount of money actually spent on the completed work = $6,783.85

SV: this variance is used to calculate how much a project is over or under budget = -$15,799.04

CV: this variance is used to determine if a project is ahead or behind schedule = $336.35

EAC: the expected total cost required to finish complete work = $34,489.68

BAC: this is total cost of the project at completion = $36,199.69

VAC: variance of total cost of the work and expected cost = $1,710.01

Turn in this sheet with your MS Project file to the Week 7 iLab

You May Also Find These Documents Helpful

  • Good Essays

    Proj586 Week 4

    • 660 Words
    • 3 Pages

    Based on the information given in the cost table, the total budget for this project is $2,633,148, and is within the budget of $2.75 million set forth by the board of directors.…

    • 660 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    Given the following information for a one year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Course Projectb Acct. 505

    • 636 Words
    • 3 Pages

    ACCT505 Part B Capital Budgeting problem Data: Cost of new equipment Expected life of equipment in years Disposal value in 5 years Life production - number of cans Annual production or purchase needs Initial training costs Number of workers needed Annual hours to be worked per employee Earnings per hour for employees Annual health benefits per employee Other annual benefits per employee-% of wages Cost of raw materials per can Other variable production costs per can Costs to purchase cans - per can Required rate of return Tax rate…

    • 636 Words
    • 3 Pages
    Good Essays
  • Good Essays

    HRM 517

    • 902 Words
    • 4 Pages

    In order to move forward with an immediate resolution, I am scheduling a meeting via cyber communications. The meeting is scheduled for 4p.m. sharp this Friday, December 20, 2013.During the meeting I will discuss the budget concerns and what is needed to move forward to improve current issues. All team leaders should submit time reports and must document if your team is on proposed schedule. This function will serve as a tool to manage the project from over budgeting. It is imperative that all members utilize their time and efforts wisely while keeping the organizations standards and goals on the forefront. With the revised plan moving forward, it is intended to address currents situations, makes the necessary adjustments and eliminate where needed in order to keep the budget from going off course.…

    • 902 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Pm 586 Week 4 Essay

    • 415 Words
    • 2 Pages

    1. What is your total budget for this project? Was the project within the budget as set forth by the board of directors?…

    • 415 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    gap analysis. You should include tasks, resources, cost estimates, and time estimates in the project plan.…

    • 313 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    It221 Final Project

    • 2390 Words
    • 10 Pages

    Currently Cyber Solutions has satellite locations in 15 major cities around the United States that provide onsite IT solutions for companies within their service area, but do not have an integrated database that updates…

    • 2390 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Assessment Task 3Title

    • 786 Words
    • 9 Pages

    Goals, objectives, deliverables, schedule, budget, and success criteria (Were they met, partially met, or missed?).…

    • 786 Words
    • 9 Pages
    Satisfactory Essays
  • Powerful Essays

    Proj 592 - CP3

    • 1453 Words
    • 11 Pages

    After setting the entire project to 40% complete on Oct 1, 2008 we can see that the project is behind schedule. The schedule variance of the entire project is $ (736,599) and Schedule performance index is at 0.68, which indicates that for every $1.00 spent in the project we are only getting $0.68 worth of work done. Since we do not have actual cost data, the MS Project calculates the budget is under budget by a negligible $80.…

    • 1453 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    This variance is calculated by subtracting the actual quantity of input used with the standard quantity of input allowed for the actual number of units produced times the standard cost per unit of the input ((AQ-SQ) x SC). This variance is favorable due to the budgeted quantities of material being 30,000 units and the actual quantity of materials used being 31,000. The favorable 7,750 efficiency variance shows how Peyton Approved was efficient when it came to the consumption of materials. This means that the manager of production had very good control over the consumption of material. The total material cost variance for Peyton Approved is favorable 7,750, which tells someone that the company was able to have efficient control of material costs and remain within standards. With good management of materials and opportunities available Peyton Approved looks to be heading in the right…

    • 552 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Earned Value (EV) Budgeted Cost for Work Performed (BCWP) How much work has been done?…

    • 760 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    W4 Hw Ev

    • 534 Words
    • 3 Pages

    In this homework assignment, you will be working through two crashing problems and four earned value problems. All the information you need is included within this Homework packet. Make sure you answer all parts of the questions in their entirety.…

    • 534 Words
    • 3 Pages
    Good Essays
  • Good Essays

    It is critical that any new project be kept on a schedule and have time frames and milestones along the way. Without a properly executed schedule the likelihood of failure rises exponentially. Schedules provide not only the project team a common operational picture but they are also used to inform sponsors and stakeholders. The main purpose of the Schedule Management Plan is to layout which approach the project team will utilize. Additional items in this plan will explain how the project team plans on monitoring the project schedule and manages changes.…

    • 456 Words
    • 2 Pages
    Good Essays
  • Good Essays

    1. When is the project estimated to be completed? How long will the project take?…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    And the other one, Variance at Completion (VAC), predicts what your variance will be when the project is done.…

    • 1414 Words
    • 6 Pages
    Good Essays