Week Three Homework: AIB Problem PROJ586 Project Management Systems Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of
Premium Critical path method Project management
Karen Brown PROJ586 Huntsville Project November Term Week Three Question #1 Estimated Completion Time of Project According to the requirements that we have set for this project we will not be able to complete it by the expected date of November 2013. With the amount of resources that we need to complete the project our new projected end date is January 30‚ 2014. There are a few options that we can take to reduce the amount of time needed to complete this project by the proposed
Premium Project management Construction