Preview

Step for Vsm Handout

Good Essays
Open Document
Open Document
994 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Step for Vsm Handout
Differences between Process Maps and Value Stream Maps

Value Stream Maps Include:

1. Value Add and Non-value Add of steps/activities 2. The Information flow along with the process flow to make the product 3. More information/data on the processes 4. Closed Circuit from the Customer back to the Customer 5. No Takt Time taken into account in process maps

[pic]

Value Stream Maps

Information Flow goes from right to left while the process/material flow goes from left to right as seen below.

[pic]
General information about VSM. ▪ Based on a today’s inventory level ▪ Inventory shifts every day but you should be capturing a snap shot to gain a basic understanding (It may shift a little over time) ▪ Look at your big customers and look at the critical components from your suppliers (Pick a representative or critical flow)

Material Flow Icons

Information Flow Icons

General Icons

Possible List of Steps

The following is a list of steps that I generally follow but they may differ based on each scenario that is being modeled.

1. Title Block

It should go in the left hand upper corner and may include date, team members, what am I mapping, etc.

2. Customer Information

Who is the customer? What kinds of information are you getting from the customer? Place the customer near the upper right hand corner using the external source/factory symbol

3. Process Blocks

▪ Add the process blocks from raw material to finished product ▪ Use it to track transactional and/or manufacturing processes ▪ May include DCs as well during this step ▪ May include trucks for traveling between process ▪ Can include parallel and serial process flows as seen in figure below.

[pic]

4. Data Boxes

Next place data boxes below each of the processes done in the previous step. What is going

You May Also Find These Documents Helpful