Preview

Word File

Good Essays
Open Document
Open Document
474 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Word File
1.2. Timing of activities and Total Float
Burke (2007) states that the timing of a project is determined using forward pass and backward pass.
Forward Pass (FP) allows us to determine the Earliest Start Time (EST) and Earliest Finish Time (EFT).
Appendix 1 – sample calculation
Same goes for backward pass which allows us to determine the Latest Start Time (LST) and Latest Finish Time (LFT).
Appendix 2 – sample calculation
(Field, M. and Killer, L. (2007)p.194) states that total float can be determined by deducting either EST and duration(DUR) from LFT or EFT from LFT.
The time of activity that can be delayed without any affect in the whole project completion time is total float.
1.3. Project Duration and Critical Path
By addition, the number of the days which are needed for every activity on critical path can be determined as project duration. For Vobien Ltd , the project duration is 50 days.
Critical path are those node which have zero float and cannot be delay or early in their activity of time. According to Field and Keller (1998),”Critical Path is normally easily spotted as they pass through nodes with same earliest and latest time.”
For Vobien Ltd, the critical path is A B C F G K L M N O Q R

1.4 The earliest date which the project could be completed is on Friday 20th September 2013 when the date is calculated by deducting the weekends (i.e. Saturday and Sunday) and continuing to count of 50 days from the Monday 15th July 2013.
1.5. The reasons
a) If there is delay by 1 day on activity E, it doesn’t effect on completion time of project since it doesn’t lies in critical path.
b) Same as activity E, activity P doesn’t lies in critical path therefore will have no effect on completion time of project while delay by 2 days.
c) If the activity Q is completed 1 day early then the whole project will be finish 1 day earlier which will be total of 49 days.
1.6. The limitation of Network Diagram * Costly

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) b) What is the Critical Path of the Project? (5 points) c) What is the ES for Activity D? (1 points) d) What is the LS for Activity G?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points)…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    According to the requirements that we have set for this project we will not be able to complete it by the expected date of November 2013. With the amount of resources that we need to complete the project our new projected end date is January 30, 2014. There are a few options that we can take to reduce the amount of time needed to complete this project by the proposed date of November 2013.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Scheduled completion time = 20 weeks Critical Path = B, C, D, F, H c. What is the slack time (float) for activities A, D, E, and G? A=3 weeks D=0 weeks E=2 weeks G=3 weeks…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    1. The project is estimated to be completed in 260 working days. The project starts on January 2nd, 2015 and ends on January 8th, 2016.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    C. Inform the colleague as soon as you know there is a delay and provide a new workable completion time…

    • 507 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Operation Management Case

    • 435 Words
    • 2 Pages

    c. Suppose you want to shorten the completion time as much as possible, and you have the following options each at an additional cost of $1500:…

    • 435 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Zuma Project

    • 1253 Words
    • 6 Pages

    If the project is resource constrained, then the finish date will be 2/18/09, since there was an additional 40 days added to the project duration. Additional personnel should be added in order to meet the desired new deadline.…

    • 1253 Words
    • 6 Pages
    Good Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.…

    • 814 Words
    • 4 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Construction itself started with activity 14 (19.75 months); there were 13 �� 19.75 months of work (�� 32.75 months) out of 60 months, or 55% of the time was spent prior to building beginning.…

    • 294 Words
    • 2 Pages
    Satisfactory Essays