Preview

Two Business A2 Level Critical Path Analysis Questions

Good Essays
Open Document
Open Document
711 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Two Business A2 Level Critical Path Analysis Questions
Q1) Discuss the benefits to Balfour Beatty of using critical path analysis in order to plan its construction projects. (15 marks)
Critical path analysis identifies the most efficient and cost effective way of completing a complex project. The various activities which together will make up the project are identified, and the order of these activities are identified. Then, the duration of each activity is estimated and these factors are then arranged as a network or graph, showing the whole project from start to finish, and showing which tasks can happen at the same time. The sequence of tasks which have to be done one after another with no gaps in between is called the Critical Path.

One benefit of Critical Path analysis to Balfour Beatty is that it always finds the shortest time possible for completing a complex project. “The customer requested completion in 124 weeks but through careful planning using Critical Path Analysis, Balfour Beatty was able to plan the project for completion in 79 weeks.” This can give a competitive edge and is an important element of time-based management. If a company is able to complete the task faster than others, it is more likely that they will get chosen, providing the company with more customers, more revenue and therefore more profit.
A second benefit of Critical Path Analysis to Balfour Beatty is that it allows managers to operate Just-in-time production. Resources such as raw materials, labour and equipment can be employed right at the earliest start time. Construction companies rely on subcontractors to complete certain tasks and for certain equipment to be hired at specific times, so with Critical Path Analysis, a manager could predict the exact time a certain piece of equipment would be needed and book the particular equipment early on to ensure that the company will have it when needed. This saves on the storage costs and opportunity costs of stock holding, and improves liquidity.
Overall, I believe that Critical

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Introduction to Project Scheduling IX. The Critical Path Method (CPM) X. Program Evaluation and Review Technique (PERT) XI. Project “Crashing”…

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    Market Analysis, Product Design, Product Design Selection, Detailed Project Design, Build Prototypes, Field Test Prototypes, Finalized Product Design, Final Manufacturing Process, Order Components, Order Production Equipment, Install Production Equipment, and Celebrate.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Lean Production

    • 2877 Words
    • 12 Pages

    One method used by Metov’s is critical path analysis (CPA). CPA is the process of planning the sequence of activities in a project in order to discover the most efficient and quickest way of completing it. Metov’s have recently been able to incorporate this technique due to recent advancement in the companies ICT system so that more advanced software which could run CPA could be utilised. There are many advantages to this technique. Metov’s constructed a CPA for setting up a new factory in Dover, in doing this they were able to work out the latest finish time was 19 weeks. This meant they were sure that two majors customers with orders worth £1million and £2million respectively would get there orders in time and this increased customer satisfaction. In addition CPA has helped with particular concentration on speed of delivery. This enabled less factory space to be wasted on storage of raw materials and more production to take place, which was of real benefit as the factory was already crowded. With increased speed of production comes an increased level of production which means they were able to sell more products and satisfy more orders/customers. CPA also assists in helping to control and review. Metov’s will be able to analyse CPA to monitor the progress against the original plan thus highlighting any delays and steps which could be taken to rectify a problem.…

    • 2877 Words
    • 12 Pages
    Powerful Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    4. The critical path for the project is found by calculating slack as per CPM as shown in the table below. The activities marked in green forms the critical path, I e.,…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Does this information (WBS) allow you to define any milestones of the project? Why or why not? What are they?…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    What is a critical path, and why is it important to project managers? How do you…

    • 702 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    2- What is the critical path and how long is the project expected to take?…

    • 294 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is the critical path in the project? How would you assess the level of risk in the project?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays