Preview

TPV1 Sample Questions

Satisfactory Essays
Open Document
Open Document
453 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
TPV1 Sample Questions
CompTIA Project+ Practice Questions
Question 1
Which of the following are risk responses? (Select TWO)
A. Delaying
B. Analysis
C. Acceptance
D. Avoidance
E. Work around

Question 2
When handling multiple changes on a project, which of the following would be the BEST format in which to inform the team?
A. Follow the communication plan
B. Email documentation
C. Fax documentation
D. Hold a meeting with the project team

Question 3
While developing a project schedule, which of the following are purposes of a milestone? (Select TWO)
A. Milestones are not required since the major events are already placed in the project work plan without durations
B. Milestones are considered a placeholder in time for a major event
C. Milestones have no duration
D. Milestones are indicators that any of the project major events have already taken place
E. Milestones require a duration indication as to provide the key stakeholders of information as a key performance indicator (KPI)

Question 4
Which of the following is a formula for estimating?
A. (BAC-EV)/CPI
B. Actual Cost + Estimated Time to Completion
C. EV/PV
D. (Optimistic + (4 x Most Likely) + Pessimistic) / 6

Question 5
Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies?
A. Arrow Diagramming Method (ADM)
B. Work Breakdown Structure (WBS)
C. Precedence Diagramming Method (PDM)
D. Critical Path Method (CPM)
Question 6
Which of the following is the key characteristic of the WBS?
A. It represents the entire scope of work for the project
B. assists the project manager with the qualified vendor selection process
C. It should be developed by others outside the project team as to eliminate bias
D. Eighty percent of the work packages will be developed by twenty percent of the project team

Question 7
Which of the following tools is used for determining activity schedules based on optimistic, most likely and pessimistic estimates?
A.

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 5 Days --- B 8 Days --- C 6 Days A D 4 Days C, B E 5 Days A F 4 Days D, E, G G 4 Days B, C H 3 Day G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    (TCO B) For a project, the objective is usually defined in terms of which three items?…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Pm592 Week 5 Assignment

    • 589 Words
    • 3 Pages

    3. Assess the project performance to date? Do you get to have the celebration? NO, at the end of month 4, over budget and behind schedule.…

    • 589 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    7) Refer to the figure. Suppose that additional resources are provided to crash the project completion time below its expected normal completion time. Which activities would be potential…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    Paper

    • 1169 Words
    • 5 Pages

    3.) In my opinion the company should accept the project based on the financial gain of the project.…

    • 1169 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Nt1310 Unit 3 Skills Lab

    • 994 Words
    • 4 Pages

    C. One problem with working in groups is coming to an agreement on how a project will be accomplished. When multiple people all have different ideas on how to do a project it is difficult to decide what ideas are not worth doing or which idea is the best out of them all.…

    • 994 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Collaborative

    • 736 Words
    • 3 Pages

    7e: The two milestones I chose were the production trials and preparing the product launch. I chose these because there would be no product without trials and preparing the product launch means that they are ready to be sold.…

    • 736 Words
    • 3 Pages
    Better Essays
  • Powerful Essays

    ____ 6. A(n) ________ path for a project is the series of activities that determine the earliest time by which the project…

    • 2493 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    5. One sensible milestone is the Product Design Selection because it is the start of a critical merging activity and completions are used as milestones. The completion date for this is 4/3/2015.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Short Term Goal Outline

    • 440 Words
    • 2 Pages

    • Professional milestones: finishing each class will be a milestone, finishing the program will be a milestone towards my long term goal…

    • 440 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    The information that provided in part 1 alone is not enough to allow the project team in defining any milestones of the project. Actually the hierarchical breakdown of the activity can be designed out of this information but for defining milestones; the project team may well require the following:…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    9. (TCO C) Why are activities drawn in a serial relationship on a network diagram?…

    • 814 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Task goals- includes bottom line targets that are measured by KPIs, production goals, deadlines, and quality standards…

    • 295 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Career Aspiration

    • 485 Words
    • 2 Pages

    | |Planned professional development |Targets (include timelines) |To be completed prior to a mid-year performance review |To be completed prior to a end-of-year performance |…

    • 485 Words
    • 2 Pages
    Satisfactory Essays

Related Topics