Preview

Solutions to Week 4 Homework (Crashing and Ev)

Satisfactory Essays
Open Document
Open Document
817 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Solutions to Week 4 Homework (Crashing and Ev)
PROBLEM 1
Use the network diagram below and the additional information provided to answer the corresponding questions. [15 points]

a) The crash cost per day per activity [10 points]

Activity A: Crash Cost = ($800 - $300) / (7-3) = $500 / 4 = $125 per day

Activity B: Crash Cost = ($350 - $250) / (3-1) = $100 / 2 = $50 per day

Activity C: Crash Cost = ($900 - $400) / (6-4) = $500 / 2 = $250 per day

Activity D: Crash Cost = ($500 - $200) / (3-2) = $300 / 1 = $300 per day

Activity E: Crash Cost = ($550 - $300) / (2-1) = $250 / 1 = $250 per day

b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? [3 points]

The diagram shows two paths: ABE and CDE. Based on normal duration estimates, ABE will take 12 days to complete and CDE will take 11 days. Therefore the earliest the project can be completed (on critical path ABE) is 12 days.

The total project cost based on normal time is: $300 + $250 + $400 + $200 + $300 = $1450

Activity on the critical path that can be accelerated at the lowest cost per day is Activity B @ $50.

If Activity B is crashed 1 day (from 3 days to 2 days), the total project duration = 11 days and project cost = $1500 (i.e. $1450 + $50)

There are now two critical paths ABE and CDE; both with 11 days. The activity with lowest cost per day on the CDE path is Activity C or E; both $250. Since Activity E is however on both paths, we should crash it by the one day available bringing the project completion to 10 days. This increases the total project cost to:

$1500 + $250 = $1750

This beats the alternative of crashing Activity C on the CDE path and Activity B on the ABE path. By crashing Activity B for 1 day

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) b) What is the Critical Path of the Project? (5 points) c) What is the ES for Activity D? (1 points) d) What is the LS for Activity G?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    RSM222 Midterm

    • 1583 Words
    • 9 Pages

    2. Abel Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 200 units and of Product B is 300 units. Selling price for A is $160/unit and B is $100/unit. There are two activity cost pools, with estimated total costs and expected…

    • 1583 Words
    • 9 Pages
    Good Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    Which activities would you expedite or crash based on the project schedule that you created for your project? Why are these the best candidate tasks to expedite? What would be the impacts to the triple constraints of time, budget or scope?…

    • 2212 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    3. The activity that has the greatest amount of slack is Detailed Marketing Plan, of 179 days.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    2. The red dotted line represents the circular dependency between activity A4 and activity A9.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    The activity-based costing cost per unit of Product A is closest to: (Points : 4)…

    • 831 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Zuma Project

    • 1253 Words
    • 6 Pages

    3.0.2. (Q#2) What options are available to meet this new deadline if the project is resource constrained? (1 pt.)…

    • 1253 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    a) What is the probability that the project will be completed between 35 and 45 days?…

    • 5665 Words
    • 87 Pages
    Satisfactory Essays
  • Good Essays

    Cost Questions

    • 377 Words
    • 2 Pages

    2) Workers paid $15.00 per hour with an overhead charge of 1.45 and a personal time allowance of 1.15, have what total direct labor cost for an 8-hour work day?…

    • 377 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Student

    • 1558 Words
    • 7 Pages

    The Assignment Problem and the Hungarian Method 1 Example 1: You work as a sales manager for a toy manufacturer, and you currently have three salespeople on the road meeting buyers. Your salespeople are in Austin, TX; Boston, MA; and Chicago, IL. You want them to fly to three other cities: Denver, CO; Edmonton, Alberta; and Fargo, ND. The table below shows the cost of airplane tickets in dollars between these cities. From \ To Denver…

    • 1558 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Pert

    • 292 Words
    • 2 Pages

    Task 1,2,4,5,6 are critical path. Task 3 is not in critical path , If task 3 delayed for 2 days will be no effect in the critical path.…

    • 292 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    minimize total costs and activity days. The model was implemented successfully with savings over $100 million…

    • 312 Words
    • 1 Page
    Good Essays