Preview

Ron Engineering Case Summary

Better Essays
Open Document
Open Document
1347 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Ron Engineering Case Summary
MJB
Introduction:
Bid for tender was requested by Defense Construction to construct a water pump, and distribution system. Important specifications for tender were a lump sum price, and would submitted a unit price for the construction of the distribution system. Four bids were collected. The contract was awarded to the lowest bid, Sorochan Enterprises Ltd.
Issues:
Does the statement of privilege allow the owner to choose a bid other than the lowest even if it breaches the terms of the tender? Facts:
One of the tender documents was that the lowest bid or tender shall not necessarily be accepted.
There were multiple types of materials that could be used for the sub grade for installing the pipe, and the owner wanted to see only a single
…show more content…
Defense Construction declared that it was just a clarification and accepted the bid.
Analysis
The appellant used the Ron Engineering, Supra case to conclude that there was a contracted formed between the owner and each of the tenderers. The contract was Contract A. Since there was a formal contract introduced, the breach by Sorochan Enterprises Ltd. for introducing a stipulation for their bid, in the form of an additional charge, and because Defense Construction accepted this non-compliant bid, the Contract A between the other tenderers was broken.
The appellant argues that because there was a formal invitation to submit a tender for a project, the rules and regulations set forth by Canadian Construction Documents Committee Guide to Calling Bids and Awarding Contracts are applied for this scenario. In order for this to have merit, a statement from M.J.B Enterprises, supra. stating,
“We certify that Tenders for trades named under (a) and (b) below were received through the Alberta Bid Depository Ltd., ... in accordance with the Standard Rules of Practice for Bid Depositories (Federal Government Projects) as required by this

You May Also Find These Documents Helpful

  • Powerful Essays

    When a procuring agency fails to adhere to the regulations and/or the terms listed within the solicitation, a bid protest may be filed (Nacke & Ralston 2011). A bid protest is a tool that a contractor can use to legally contest the process or result of a government contract award. In order to file a protest, one must be considered an interested party, meaning they are an offeror or prospective offeror who would be financially affected by either the award or the non-award of the contract. There are three different types of protests available to contractors. Each has differing procedures but they share the main requirement; In order to win, they must provide supporting information which would prove that they have been prejudiced by the government agency. The two most common forms of bid protest are the agency-level protest and the Government Accountability Office (“Bid Protests,” 2010).…

    • 4029 Words
    • 17 Pages
    Powerful Essays
  • Good Essays

    Part 14 Sealed Bidding; Part 15 Contracting by Negotiation; Subpart 6.2—Full and Open Competition After Exclusion of Sources;Subpart 6.4—Sealed Bidding and Competitive Proposals…

    • 928 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Case 8 Rfq

    • 2161 Words
    • 9 Pages

    The subject materials have been selected for competitive bid, the RFQ has been issued, and responses from nine potential vendors have been collected. The variations in the bid responses are staggering, causing concern for the validity of the RFQ process. Should we decide to proceed with the lowest bidder, we would do so at our own risk, as the bidder may not have understood the requirements of fulfilling the contract. I propose that we re-evaluate the RFQ documents to ensure that the bidders have a consistent understanding of the Statement of Work. This is the best way to offer our company the value created by the competitive bid process.…

    • 2161 Words
    • 9 Pages
    Powerful Essays
  • Best Essays

    Peter Smythe V Thomas

    • 2716 Words
    • 11 Pages

    The justice also found that the defendants claim to only have created an invitation to treat was unjustified on the grounds that the bid met the time period, the minimum bid, the plaintiff was the highest bidder and didn 't impose a qualification on the bid. It is for these reasons that the judge found a binding contract between the buyer and vendor and henceforth implemented an order for specific performance, instructing the contract to be…

    • 2716 Words
    • 11 Pages
    Best Essays
  • Satisfactory Essays

    Kuenzi Vs. Radloff Case

    • 1496 Words
    • 6 Pages

    The lawful purpose of the contract is approved of by the Industrial Commission. The form of the contract was written. Gayton states, “Upon receipt of the signed proposal”…

    • 1496 Words
    • 6 Pages
    Satisfactory Essays
  • Good Essays

    Tercon Case Summary

    • 501 Words
    • 3 Pages

    Certainties:- The BC Ministry of Transportation and Highway issued a demand for proposal(RFP) for the development of a Highway. Six groups reacted with accommodation including Tercon and Brentwood Enterprises Ltd. Soon thereafter, the territory educated the six advocates that it now planned to outline the roadway itself and issued a demand for recommendations for its development. The RFP likewise incorporated a statement barring all cases for harms "because of taking an interest in this RFP" (s. 2.10). Brentwood gone into a pre-offering concurrence with another development organization ("EAC") which was not a qualified bidder to embrace the work as a joint wander. Eventually Brentwood presented an offered in its own name with EAC recorded as a "noteworthy part" of the group .Brentwood and Tercon were the two short-recorded defenders and the Province chose Brentwood for the venture. Tercon got an activity harms against the area.…

    • 501 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Only one of which is actually relevant to the legal action brought on by the City. The case of the Queen in right of Ontario et al. v. Ron Engineering in the Supreme Court of Canada in 1981, established that the tendering process consists of two contracts, Contract A and Contract B [1]. Contract A is a tendering agreement and while the Contract B is the actual contract to do work [2]. In this case, the City of Waterloo's call for tenders and the following bid by SoftX Programmers constitutes Contract A between the two parties. However, Contract B was never formed as it was never signed by SoftX. This might constitute a breach of Contract A; however, this idea will be explored further. In Contract A, it is an implied term that the contracting party can only accept a "compliant bid" and to treat all bidders "fairly and equally" [1]. As such, one could argue that the City of Waterloo did not properly follow tendering procedures because errors in a bid make it no longer compliant. Furthermore, depending on the judge's judgment, it may appear unfair to the other bidders to accept a bid that was neither compliant nor was the bid that the party would have made had they not made an…

    • 1070 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Stadium Contracts

    • 1057 Words
    • 5 Pages

    a discussion on the criteria which would have been used to select the procurement strategy / building contract.…

    • 1057 Words
    • 5 Pages
    Good Essays
  • Better Essays

    2) Pressure from leadership. Interagency politics and lack of planning resulted in this procurement being somewhat rushed. Current year funds expiring and senior manager eagerness are not appropriate factors to force a contract specialist to consider.…

    • 1374 Words
    • 4 Pages
    Better Essays
  • Better Essays

    Statement of Issue Government employees involved in procurement activities, have rules and policies to uphold the integrity of the Government and equal treatment of all contractors and bidders. A violation of the integrity and ethics policies harm the Government and the public’s trust. Dishonest relationships with bidders and contractors can result in civil and criminal penalties Ethics & Procurement Integrity (2007).…

    • 1122 Words
    • 5 Pages
    Better Essays
  • Better Essays

    Ces2 Reflection

    • 905 Words
    • 4 Pages

    The purpose of the RFP was to replace the existing course on the Commission on Peace Officer Standards and Training (POST) learning portal. I was assigned and challenged to finalize the evaluation, to create Evaluation and Selection Report and to help complete all the required contract documents. Fortunately, during the final evaluation, only two bids were submitted. One bid was compliant to all requirements and the other bid was not compliant with all of the Administrative Requirements. With the background information that the previous procurement official provided me, and after scoring and evaluating the final bids submitted, I was able to generate the Evaluation and Selection Report. Before I issued the intent to award letter, I submitted the report to the evaluation team for review and approval, then to STPD management for final approval. Finally, I helped the POST procurement analyst by reviewing and completing all of the contract…

    • 905 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Oppa Essay

    • 343 Words
    • 2 Pages

    Any contractor, who claims to have suffered loss or injury due to a breach of these procedures by the Procuring Entity, may seek a review of the specific procurement process. Notwithstanding the foregoing, it should be noted that the following are not subject to review: (i) the selection of the method of procurement and (ii) the decision by the Procuring Entity to reject all tenders, proposals, offers or quotations.…

    • 343 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    2.What is the procurement integrity act? What are the ethical implications of the act? What is the relevance of this case?…

    • 440 Words
    • 2 Pages
    Satisfactory Essays
  • Best Essays

    Finch, R., 2011. NBS Guide to Tendering: for construction projects. 1st ed. Newcastle upon Tyne: NBS Publications.…

    • 1721 Words
    • 7 Pages
    Best Essays
  • Powerful Essays

    Contract Administration

    • 3153 Words
    • 13 Pages

    [ 2 ]. Phillip, Charles S. 1999 Construction Contract Administration [electronic resources] Littleton: SME 1999…

    • 3153 Words
    • 13 Pages
    Powerful Essays