PSP Exam Questions
Page |1

PSP Paper - 1
P.1 Which of the following is generally the MOST correct use of a project network diagram?
A. Showing the project schedule
B. Documenting task interdependencies
C. Defining project resources
D. Defining the project costs
P.2 At a minimum, periodic forecasts must be done at what interval?
A. monthly
B. as requested by the owner
C. as requested by the project manager
D. as specified in the contract documents
P.3 The calculated duration for a project is 28.166. The standard deviation is 5.5. What technique would you use to compute the probability of completing a project on a specific day?
A. PERT formula
B. Monte Carlo simulation
C. Probability analysis
D. Variance analysis
P.4 The best reason to use multiple calendars is to ___________
A sequence the float for the benefit of the contractor
B more accurately show how the project will be built
C give specialty contractors the information they need
D track owner activities according to their specific calendar in order to develop a good working relationship P.5 During planning you discover that the time needed to complete the project is longer than the time available. What do you do?
A. Tell the customer that the required date cannot be met
B. Tell management that the required date cannot be met
C. Spend time determining what work can be done for the length of time available and accomplish only that work
D. Determine options for crashing and/or fast tracking the project and present management with your recommended option
P.6 Free float is the ____________
A difference between the early dates and late dates of an activity
B amount of time an activity can be delayed without impacting the early start of the successor activity. C difference in float value of the critical path activities and the float value of the specific activity
PSP S1

AACEI-UAE

Page |2

being analyzed
D difference between the early finish dates and late finish dates of an activity
P.7

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    30 b) Identify the critical path (4 points) B,C,D,F,H c) What is the slack time (float) for activity A? (2 points) 5 d) What is the slack time (float) for activity D?…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    AIB Simulation

    • 771 Words
    • 4 Pages

    Before starting this homework assignment, please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram, and how to do a forward and backward pass to determine the ES, LS, EF, LF and slack (float). You will also learn how to determine the duration of the project, and the critical path.…

    • 771 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    B. Inform the colleague that there is a problem and let them know when the job will be done…

    • 507 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Natural Blends

    • 556 Words
    • 3 Pages

    Project Management Case Assignment - Use Microsoft Project to analyze this case. This is an example of a construction project. The construction for a large corporate building must be started by February 15th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. The details of the project activities are as follows – The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared. The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins. Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 15th, 2010 which is a Monday and that you work five days a week for 8 hours every day. Analyze the following questions based on the estimates of the above activities 1) When do you complete the project?…

    • 556 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    ARIBA Team 2

    • 263 Words
    • 3 Pages

    ARIBA IMPLEMENTATION IN MED-X Case Team 2: Yusuf Akkoca Tom Bloom Karen Delton Shweta Hire Eric Johnson David Mahzonni Greg Roy Which of the two components are underperforming according to the plan? How do you know this? • Technical Infrastructure is both behind schedule and over budget as indicated by the SPI (94.4%), Control Ratio (< .9) and CPI (91.7%)…

    • 263 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Scripted Services

    • 534 Words
    • 3 Pages

    a. Study each element of work to determine the “one best way” to do it.…

    • 534 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Gantt Chart

    • 2465 Words
    • 10 Pages

    This section consists of a suite of potential options broken out by sample phases. While it may be useful for grantees to consider these deliverables in designing their project, the particular suite of deliverables and the organizational structure that is ultimately incorporated will be project-specific. The grantee may also ask the Vendor to provide cost estimates on a per-deliverable basis in the bid response.…

    • 2465 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    The estimated project completion date is TUE 11/13/13 with duration of 127 days. After leveling and re-allocating work along the project line, the project got delayed for 3 days so that the completion day moved up to FRI 11/21/13 (total duration of 130 days). (MS Project 2007)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    (d) Why is it important to determine the critical path of a project? What happens if activities…

    • 805 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Subway Project Plan Overview

    • 10327 Words
    • 42 Pages

    This project entails opening two Subway Restaurant franchises. The project is described and potential problems identified. The mission, scope, and measuring the progress of the project are also discussed. The first step is applying to Subway for a franchise. Once the application has been accepted, the real work begins. Using Microsoft Project, each phase of the project can be monitored to ensure successful completion.…

    • 10327 Words
    • 42 Pages
    Powerful Essays
  • Good Essays

    Project Management

    • 836 Words
    • 4 Pages

    It is believed that project managers who estimate activity times provide an estimate that has about an 80 to 90 percent chance of being completed on or before the estimated time (Larson and Gray, p.295). Using the Critical…

    • 836 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Gantt Chart Analysis

    • 1192 Words
    • 5 Pages

    The project that I am scheduling will take a lot of time to complete due to the size of the said project, according to the duration of each task that I have been provided with, the project will take at least sixteen months to complete as none of the tasks can be attempted until the tasks previous to it have been completed successfully.…

    • 1192 Words
    • 5 Pages
    Powerful Essays