Preview

Project Management Questions In Class

Satisfactory Essays
Open Document
Open Document
564 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management Questions In Class
COMM 225: Production & Operations Management
TOPIC: PROJECT MANAGEMENT – QUESTIONS (To be solved in class)
Q1 (Ref: Q. 17-7, p658 of textbook): Three recent university graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table.
(a) Draw the precedence network.
(b) What is the probability that the project can be completed in 24 days or less? In 21 days or less?
(c) Suppose that now is the end of the seventh day and that activities a & b have been completed while activity d is 50 percent completed. Three-point estimates for the remaining duration of activity d are now 5, 6, and 7 days.
Activities c and h are ready to begin. Determine the probability of finishing the project by the end of (a) day 24 and (b) day 21.
Duration in Days
Activity

Precedes

Optimistic

Most Likely

Pessimistic

a b c d e f g h i

c h e f End g End i End

5
8
6
9
5
5
2
4
5

6
8
8
12
6
6
3
4
7

7
11
11
15
9
7
7
5
8

Q2 (Ref: Q. 17-13, p660 of textbook): The project manager of the construction of a domed stadium had hoped to be able to complete the construction prior to the start of the next season. After activity duration estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener.
Given the following information, determine the minimum-cost crashing schedule that will shave five weeks off the project length.
Crashing Costs
Activity

Precedes

Normal Duration (weeks)

First Week

Second Week

A
B
C
D
E
F
G
H
I
J
K
M
N
P

B
K
D, E, F
G
H
I
M
N, P
J
P
End
End
End
End

12
14
10
17
18
12
15
8
7
12
9
3
11
8

$15,000
10,000
5,000
20,000
16,000
12,000
24,000

30,000
25,000
10,000

40,000
20,000

$20,000
10,000
5,000
21,000
18,000
15,000
24,000


25,000
10,000


20,000

Q3(Ref: Q. 17-18, p663 of textbook): Consider the construction of a research building for Eli Lilly & Co., a pharmaceutical company, a few years ago. This 550,000 ft2. 4-story

You May Also Find These Documents Helpful

  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    4) Refer to the figure. What is the slack time, in days, associated with activity D?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Good Essays

    Northern Drilling case

    • 1152 Words
    • 5 Pages

    Likelihood to fail to perform the job and perform on time (for 3 and 4)…

    • 1152 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Updated June 2012. This summary sheet only contains a subset of the recommendations from the US MEC. For complete guidance, see: http://www.cdc.gov/reproductivehealth/unintendedpregnancy/USMEC.htm…

    • 3136 Words
    • 13 Pages
    Satisfactory Essays
  • Good Essays

    Natural Blends

    • 556 Words
    • 3 Pages

    Project Management Case Assignment - Use Microsoft Project to analyze this case. This is an example of a construction project. The construction for a large corporate building must be started by February 15th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. The details of the project activities are as follows – The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared. The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins. Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 15th, 2010 which is a Monday and that you work five days a week for 8 hours every day. Analyze the following questions based on the estimates of the above activities 1) When do you complete the project?…

    • 556 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Blue Zuma Part 2

    • 310 Words
    • 2 Pages

    Once the changes are in place, the duration of the project has been reduced from 290 days to 274 days. This improvement has reduced the overall length of the project, thus allowing the deadline set by the Mr. Lane (President). We are confident we can now complete the project by January 27.…

    • 310 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    2 and Profit

    • 379 Words
    • 2 Pages

    Problem 15 Suppose that any firm intending to produce SOMA must build an integer number of plants: 0, 1, 2,.... Building Q plants costs each firm 3.5 × Q dollars. Each plant produces one unit of SOMA. If firm 1 builds Q1 plants and firm 2 builds Q2 plants, the market price p for one unit of SOMA will be 9 − (Q1 + Q2). For example, if firm 1 builds 2 plants and firm 2 builds 4 plants, the market price will be 9 − (2 + 4) = 3 per unit. At this price firm 1 will make a profit of 2 × 3 − 2 × 3.5 = −1 while firm 2 will make a profit of 4×3−4×3.5 = −2. Assume, no firm will build more than 4 plants.…

    • 379 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Building Project

    • 7428 Words
    • 30 Pages

    Building X is a 20,000 square foot facility that houses administrative and morgue space for the client’s examiners. The total construction cost of this facility was approximately $xx million. The project began construction on date xx. The project was occupied by the users on/or around date xx. The commissioning process was fully…

    • 7428 Words
    • 30 Pages
    Powerful Essays
  • Good Essays

    Jtdjzrfg

    • 1305 Words
    • 6 Pages

    You will have 22½ hours to complete these tasks. Research tasks can be carried out outside timed…

    • 1305 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Task Description Duration Predecessor A Develop Schedule 4 - B Produce Schedule 6 A C Obtain Hardware 17 A D Programming 60 B E Install Hardware 10 C F Initial Hardware 14 D G Create Web Page 25 D.F H Program Test 30 E…

    • 387 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    List the Activities that are on the Critical Path and fill in all columns in the table below (add rows as needed): (4 pts)…

    • 846 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Building Process

    • 386 Words
    • 2 Pages

    Finally the actual construction can begin. Typically some changes in design and plans are made during this period. There is always something unexpected appearing or happening…

    • 386 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    (b) Identify 3 ways that you can overcome these problems if you are asked to do early…

    • 805 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Discuss the process of defining project scope in more detail as a project progresses, going from information in a project charter to a project scope statement, WBS, and WBS dictionary.…

    • 1086 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    As of the 26th of August, what is the project schedule and cost? What are the trends? What is the critical path?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    OTM ASSIGNMENT

    • 2622 Words
    • 13 Pages

    e) All the three assignments are to be completed by due dates (specified from time…

    • 2622 Words
    • 13 Pages
    Powerful Essays