Preview

Project Management

Better Essays
Open Document
Open Document
1194 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management
Spring 11 IE 5541: Project Management Homework #6
You can work on this assignment individually, or in a group of 2 or 3. If you work as a team, please turn in one copy of the assignment.

PROBLEM 1: A&D HIGH TECH (25 POINTS)
The product management aspect of this case is showing its age: published in 2006, and set in 2002 - 3. Some of you will question their technology choices. Do your best to focus on the PM aspects, assuming that their technology choices were appropriate for a conservative company at that time.

Objective
A major managerial challenge is analyzing project plans rendered in MS Project (or other software) and determining their chance of success. Rather than looking at the basic issues of a project, many managers simply verify that the finish date on Line 1 of the project plan is acceptable. In this assignment, you will build a plan, and then analyze it for its chances of success. You will turn in several reports and a short write up (both are described below).

Create Project Schedule
Read A&D High Tech (A): Managing Projects for Success from your course pack (be careful, there is also a case titled A&D High Tech (B)) 1. Review Exhibit 6 and note that estimates are given in Work (not Duration) and that the Work is stated in Days (not Hours). Let’s set our MS Project parameters (Tools>Options>Schedule) o o o Set Default Task Type = Fixed Work Set Work is entered in Days Set Show that Tasks have Estimated Duration = OFF (no checkmark)

2. Create your indented WBS (Exhibit 5) (there is an .xls file on Moodle that has done the typing for you. You’ll just have to cut, paste, and indent). 3. Input your estimates (Exhibit 6). Remember, they are Work estimates 4. Create Network (Exhibit 9) o o o Start project on 5/26/031 Note that Exhibit 9 creates links from summary tasks. While I don’t encourage this practice, we’ll adapt to A&D High Tech’s practice (as good consultants always do) Check your work (Work = 1061.1 days).

5. Input your Work

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    Create a project schedule using Microsoft Project. Project schedule will built from and contain the following information:…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Powerful Essays

    The project staff analysed with basis in a series of factors like training staff, adequate to legislative requirements, measuring risks, availability of the budget and quality standards to set a timeline. Once every step is scheduled, the whole staff can work with a estimated and real parameter of timeline.…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Satisfactory Essays

    The estimated effort hours and project costs may be depicted in many ways, including by team members, by deliverable, by milestone, or by category (internal labor, external labor, travel, training, supplies, etc.). Also include a chart showing the project start date, major milestones, and end date. The deliverables included in this milestone chart should all be described in the scope deliverable section. (Remove this comment section from final document.)…

    • 1713 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    CP1 Essay

    • 1082 Words
    • 5 Pages

    Now that your project schedule has been created, your resources have been loaded, and your resource costs have been allocated, please analyze your results and answer the following questions.…

    • 1082 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Mgmt8665 - H M S Pinafore

    • 297 Words
    • 2 Pages

    Your task is to construct a network diagram for this project, identify the critical path and address a number of managerial issues. Given the case presentation, you will extract a work breakdown structure and an activity list. Enter your project data on to MS Project. Save the project baseline. This represents the half the assignment grade because it evaluates your use of the project management software.You will find that there is a difficulty in meeting the opening night schedule (if you follow the text exactly). Your task is to solve the scheduling problem by considering the impact on the quality of the performance as well as the additional stress on the participants. Implement your scheduling solution by saving a second baseline. Deliverable: Write a short report (6-10 pages) which extracts the key data from the schedules created in MS Project. The topics are to include (15 points): * Description (5) * A brief description of the Pinafore project task * A brief description of the main task areas (i.e. upper level of the WBS) * The logic behind the schedule (give reasons for predecessor and successor relationship; what are the key schedule constraints) * Original Solution (5) * Statement of the original schedule: i. Your Gantt chart ii. Your entry table including the task name, Duration, start, finish, predecessor, successor, Resource and cost (see below) iii. Comment on the scheduling problem * Your Solution (5) * Statement of the final schedule: iv. Your Gantt chart v. Your entry table including the task name, Duration, start, finish, predecessor, successor, Resource and cost (see below) * Justify your solution: clearly identify the impact on project risk, quality, cost and human resources Submit a word document only to LMS…

    • 297 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Natural Blends

    • 556 Words
    • 3 Pages

    Project Management Case Assignment - Use Microsoft Project to analyze this case. This is an example of a construction project. The construction for a large corporate building must be started by February 15th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. The details of the project activities are as follows – The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared. The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins. Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 15th, 2010 which is a Monday and that you work five days a week for 8 hours every day. Analyze the following questions based on the estimates of the above activities 1) When do you complete the project?…

    • 556 Words
    • 3 Pages
    Good Essays
  • Good Essays

    project management

    • 2580 Words
    • 7 Pages

    Prepare a five to seven paragraph response proposing leadership styles you would recommend for the Denver Airport Project. Please choose a combination (two or three) of the eight leadership styles presented in the Thompson textbook (Chapter 11: Leadership: Managing the Paradox). Please note that you are to also use three other sources from the internet or the DeVry online library. All sources must be cited.…

    • 2580 Words
    • 7 Pages
    Good Essays
  • Satisfactory Essays

    Part I 1. Project management: a) Is the planning, scheduling and controlling of project tasks to meet objectives. b) Is used primarily in construction and public works. c) Requires less communication than ongoing process management. d) Focuses on well-understood, unambiguous tasks and relationships. Using the following project, with activity times estimate in days and a critical path of CH-J-K, to answer the next 3 questions: Activity A B C D E F G H I J K Immediate Predecessor A A A, B C C E, F, G H D, I, J Optimistic 2 4 6 5 3 8 4 3 5 12 1 Most Likely Pessimistic 5 3 7 12 4 9 6 7 7 13 3 6 7 10 14 5 12 8 8 12 14 4…

    • 2606 Words
    • 11 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Management

    • 1620 Words
    • 7 Pages

    A _______________ is a temporary endeavor undertaken to create a unique product, service, or result.…

    • 1620 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Planning

    • 3473 Words
    • 14 Pages

    This course provides the foundation for understanding the broad concepts of successful planning, organization, and implementation within the realm of information technology. This course uses real-world examples and identifies common mistakes and pitfalls in project management. Topics covered include project scoping, estimating, budgeting, scheduling, tracking and controlling.…

    • 3473 Words
    • 14 Pages
    Powerful Essays
  • Good Essays

    ACC 497 Final Exam

    • 2281 Words
    • 11 Pages

    15) A simple diagram that shows estimated completion times versus actual completion times for the various activities in a systems implementation project…

    • 2281 Words
    • 11 Pages
    Good Essays
  • Satisfactory Essays

    Project Management

    • 273 Words
    • 2 Pages

    Project ManagementTop Down/Bottom Up methods Consensus methods Snr/middle managers’ guess
total project time & cost Discussing/arguing to reach a
decision on best guestimates Firms seeking greater precision: Delphi Method: Group decision process of chance of
certain events occurring Exp. familiar with project use insight/exp. guessing project costs/times Ratio methods Macro methods use ratios to guess time & cost E.g. contractors using no. of sq. ft. to guess cost/time to
build a house Apportion method Common in standard projects but may differ/customise Given good historical data, estimates made quick easy & accurately Costs apportioned to phases/deliverables Function point methods (software/system projects)…

    • 273 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Management

    • 488 Words
    • 2 Pages

    * Security at all the airports, railway stations, metro stations and major areas of the city.…

    • 488 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Project Management

    • 1064 Words
    • 5 Pages

    A project can be a wide variety of activities. According to Kerzner, 2006, a project can be considered to be any series of activities and tasks that have a specific objective to be completed within certain specifications, has defined start and end dates, has funding limits (if applicable), consume human and nonhuman resources (i.e., money, people, equipment), and are multifunctional (i.e., cut across several functional lines) (p. 2). Remodeling a home, restructuring an organization, opening an additional business location, purchasing new equipment, etc are all considered projects. All of these projects will contain an objective, defined start and ending dates, funding limits, consume resources, and are multifunctional.…

    • 1064 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Project Management

    • 703 Words
    • 3 Pages

    1. Describe Teresa Earnhardt’s leadership style. What do you think the advantages and drawbacks of her style?-…

    • 703 Words
    • 3 Pages
    Satisfactory Essays

Related Topics