Contract Award
During this period Altex Corporation was elated when it learned that it had just been awarded the R& D phase of the Advanced Tactical Missile Program (ATMP). The terms of the contract specified that Altex had to submit to the Army, within 60 days after contract award, a formal project plan for the two-year ATMP effort. Contracts at that time did not require that a risk management plan be developed. A meeting was held with the project manager of R& D to assess the risks in the ATMP effort.
PM:“I’m in the process of developing the project plan. Should I also develop a risk management plan as part of the project plan?”
Sponsor:“Absolutely not! Most new weapon systems requirements are established by military personnel who have no sense of reality about what it takes to develop a weapon system based upon technology that doesn’t even exist yet. We’ll be lucky if we can deliver 60-70 percent of the specification imposed upon us.”
PM:“But that’s not what we stated in our proposal. I wasn’t brought on board until after we won the award, so I wasn’t privileged to know the thought process that went into the proposal. The proposal even